With nowhere to go but down, this basement addition carves
out extra living space from within the home’s existing
footprint
To accommodate their two growing kids, our clients wanted to
add a media room and another bedroom and bath. But because
their house is on a tight Atlanta lot with no room for an
addition — and we’d already expanded upward with a
previous master-suite addition — they faced a simple
choice: Find another house or finish the basement. They
didn’t want to move, so going down into the crawlspace
appeared to be the only option for creating the additional
1,000 square feet of living area.
We’ve taken on some interesting projects in our 29 years
in business, but this was the first time we ever had to remove
300 cubic yards of dirt from underneath an existing house
— by hand. If the lot had been larger, we might have used
the conventional approach — cribbing the house, removing
the existing foundation, mechanically excavating the basement,
then pouring a new foundation. There were two problems with
that approach: First, the tight lot lines would have made it
difficult to maneuver heavy equipment; and second, removing the
existing foundation would have required that we temporarily
support the home’s brick veneer. So instead, we decided
to leave the existing foundation walls intact and pour a new
full-height foundation within the perimeter (see illustration).
This would also make it possible for our clients to stay in
their house during the project.


Full-height concrete retaining walls formed within the
perimeter of the existing crawlspace stabilize the original
brick foundation and help support the floor framing. A
bentonite waterproofing membrane, installed before the
retaining wall was poured, keeps ground moisture out of the
concrete. Drainage is provided by a composite dimpled membrane
that channels water into a perimeter drain connected to sump
pits in the new egress window wells.
Excavation
The house was built in the 1930s. Its brick foundation was
supported by a double-brick footing set on the clay substrate
about a foot below grade (see Figure 1). Only a
10-foot-by-12-foot portion of the crawlspace had ever been dug
out, to a depth of around 8 feet. The plan was to dig down 11
feet below the bottom of the floor joists to provide plenty of
room overhead for upgraded mechanicals. Since excavating the
space by machine wasn’t feasible, we would dig by
hand.
Figure 1. Because the home’s tight
lot lines limited access (top), all the excavation for the
basement addition was done by hand, with dirt removed by
wheelbarrow through a small opening in the foundation (middle).
The clay-shale soil was firm enough to allow for nearly
vertical dirt walls within 2 feet of the existing brick footing
(bottom).
For access, we created an opening in the front foundation
wall, where the plans called for an egress window and window
well. The opening was close to the street, making it a
convenient place to back up a dump truck for dirt removal. To
ensure that we didn’t undermine the house, our structural
engineer, Tom Skywark, advised us to stop the digging 2 feet
from the foundation and to approach the excavation and new
concrete work in 4-foot-long sections. It turned out, however,
that the soil — a clay-shale mix — was much firmer
than predicted; in fact, we had to use jackhammers to loosen
it. As we chipped away, we had a hunch we could excavate larger
sections at a time. A soils engineer confirmed this and gave us
the go-ahead to dig out the entire space. Amazingly, we were
able to dig vertical walls down to the planned depth without
disturbing the soil beneath the footings at all.
Shoring
The floor framing was supported by at least a dozen posts,
several brick piers, and an old fireplace foundation (we had
already removed the actual chimney during the attic renovation
15 years earlier). Rather than using a lot of cribbing, we
replaced each support as we went. We worked in stages,
excavating a couple of feet down around the support, setting a
pair of temporary 6x6 posts on blocks on both sides, then
removing the support. Next we’d dig down another couple
of feet, set another blocked 6x6 post in the new hole, and
remove the flanking posts so we could keep going down. We
repeated this process until we reached the final depth —
11 feet below the floor framing — and moved on to the
next support.
As we swapped posts, we also reinforced the floor framing
according to the new framing plan. The original plans called
for steel beams, but we chose to use built-up LVL beams instead
because the individual members are lighter and easier to
maneuver in a cramped space.
Concrete Work
We planned to place the concrete in four steps: first, the
6-foot-wide perimeter footing, followed by the 8-foot-high
perimeter walls; then the massive footings for the center
support posts; and finally, after installing rough plumbing for
the bathroom, the basement slab. But before we could pour any
concrete, we had waterproofing and rebar to install.
Steel reinforcement. The massive
footing works in conjunction with the new foundation walls to
create a retaining wall that resists overturning and lateral
soil pressure (Figure 2). The finish slab locks the footing in
place and prevents sliding. The rebar schedule called for a
double L-shaped cage made from #4 rebar, with rods extending
horizontally from the footing to tie into the slab.
Figure 2. Shown here (top) is the first
of two layers of rebar designed to tie the 6-foot-wide footing
to the new concrete walls, creating an 8-foot retaining wall
inside the basement. The concrete was pumped in (middle), then
power-troweled for a smooth finish (bottom).
Waterproofing. Although the
80-year-old house had no perimeter footing drain, the basement
had stayed dry; as we removed soil, we found no evidence of
moisture. Still, we wanted to make absolutely sure that any
dampness in the soil couldn’t come in contact with the
new concrete foundation walls or the bottom of the slab. Since
the sides of the excavation would serve as the outside form for
the foundation walls, we lined the dirt with MiraDrain 6200
(Carlisle Coatings & Waterproofing, 888/229-0199,
www.carlisle-ccw.com),
a dimpled drainage membrane that allows water to move freely
through it. At the base of the excavation, we installed
MiraDrain HC, a 1-inch-thick by 6-inch-high perimeter drain
that collects any water at the base of the foundation wall and
directs it to sump baskets located in the egress window wells,
where it’s pumped out to grade.
On top of this drainage layer we installed Carlisle’s
MiraClay, a waterproofing membrane made with a layer of
bentonite clay sandwiched between layers of woven and nonwoven
polypropylene fabric (Figure 3). When exposed to water, the
clay expands and creates a self-sealing waterproofing barrier
for the concrete walls.
Figure 3. Before the walls could be
poured, the waterproofing subcontractor installed MiraDrain and
MiraClay membranes all the way to the top of the excavation
(top), then covered the exposed dirt at the top with a poly
vapor barrier (middle). He also spread poly over the dirt floor
in preparation for placing the slab (bottom).
Both MiraClay and MiraDrain come in 4-foot-wide rolls, so we
needed two courses to extend up the full height of the walls.
We pinned the membranes to the dirt walls with nails driven
through washers, and capped the walls with 15-mil reinforced
poly. We also spread poly on the ground underneath the new
footing, cutting in around the temporary shoring posts as
necessary.
Placing the Concrete
With the rebar placed, we pumped the concrete for the
footings, using a standard 3,000-psi mix. Because the top of
the footing would be part of the finished floor, we also
screeded it and gave it a smooth trowel finish.
Foundation walls. The following day we stripped
the footings and set the forms for the 1-foot-thick by
8-foot-high walls (Figure 4). Besides restraining the soil
under the existing foundation, these walls support the new LVL
beams used to carry the floor loads above.
Figure 4. Pressure-treated 2x4s shot into
the footing restrained the bottom of the one-sided wall forms
(left); diagonal braces secured to temporary posts and the
floor framing above held the top and middle (right).
We couldn’t use snap ties with a one-sided form, so we
needed rugged bracing. Since we would eventually be framing
interior stud walls inside the new concrete wall, we went ahead
and shot down permanent PT bottom plates, which we used to
brace the bottom of the forms. We also set 6x6 posts against
the footing every couple of feet and used these posts and the
floor framing above as nailers for diagonal bracing.
Again, we pumped in the concrete, bringing it up enough to cap
the soil next to the existing brick foundation.
Beam footings. Next we formed and poured three
grade-beam footings for the load-bearing basement walls (Figure
5), bringing their top elevation 2 inches below the finish
slab. We also poured the egress window wells at this time. The
window wells each have their own sump basket and pump to
redirect water to nearby landscaping beds, and were eventually
finished with Bilco ScapeWels (203/934-6363,
www.bilco.com).
The new bathroom required a sewage ejector
pump (top), which is located in the middle of one of the
footings designed for the basement’s bearing walls
(bottom).
Finished slab. Before pouring the slab, we
framed the load-bearing stud walls and finished installing the
LVL beams and posts to support the existing floor system. When
all the temporary supports were out of the way, we brought in
the concrete pumper once again. We took extra care in floating
and troweling the slab because it’s also the finished
floor. Sealed with a couple of coats of polyurethane, it would
be covered with rugs in each of the three main basement living
areas.
Insulation and Drywall
Once the perimeter 2x4 wall framing was installed and
rough-ins completed, we had our insulation sub spray a couple
of inches of high-density foam into the cavities (Figure 6).
The low-permeance foam completely covers the concrete, laps
over the top cap, and extends up the brick foundation wall to
the band joist. This effectively seals the narrow space between
the old and new foundations.
Figure 6. LVL beams now support the first
floor, with room above for mechanicals (top). New stud walls
around the perimeter were insulated with high-density
polyurethane sprayed directly against the new concrete and
existing brick (middle left). The new space includes two egress
windows (middle right) and a large exercise and media room
(bottom).
The small crawlspace at the top of the wall is accessible
through the mechanical room; some of the home’s ductwork
was rerouted through this conditioned space. The plan had been
to provide an uninterrupted flat ceiling, but when the
homeowners saw all the overhead space we’d allowed for
mechanicals, they requested a number of coffers, soffits, and
vaulted spaces to help break up the ceiling plane.
Cost
The cost for finishing basements ranges widely, but this one
was unlike any other we’ve ever done. The excavation, the
new foundation — including the slab and waterproofing
— and the structural work overhead to support the floor
framing took about four months to complete, and added around
$120,000 to the overall cost of the project.
Danny Feig-Sandoval owns Small Carpenters
at Large, a design-build remodeling firm in
Atlanta.