Download PDF version (370.9k) Log In or Register to view the full article as a PDF document.

Adding a bathroom to a finished basement greatly improves the livability of the space, though at first glance it appears to have gravity working against it. After all, in most basements the main drainpipe exiting the house is closer to the ceiling than to the slab below. Actually, this is an easy opportunity to triumph over client misgivings and Newton’s apple. There are two ways to connect a toilet to an existing overhead drain line: an in-floor ejector system or an above-floor system. The above-floor system uses a sealed pump tank, to which the bathroom fixture drains are connected. The tank can be concealed in an enclosure or closet, and requires little or no demolition of the concrete floor. On the down side, you’ll have to build a raised platform, about 6 inches high, to accommodate the waste pipe. This means that access to the toilet requires a step up. The platform may also impinge on headroom requirements.

Low-Profile Pumping

I prefer the in-floor system, and customers are usually happier with it because it provides a normal appearance and easy access to the toilet. In one recent job, I converted a raised-platform toilet to an in-floor installation (see Figure 1).

basem1a.jpg (13754 bytes)

Figure 1. A basement toilet on a platform (top) installs easily but is awkward to use. Using an in-floor basin with a sewage grinder pump creates a normal appearance and doesn’t impinge on headroom (bottom).

basem1b.jpg (6572 bytes)

In-floor installation requires some concrete demolition to install the sump basin and underfloor piping. The basin is a sealed unit, typically made of polyethylene, high-density polyethylene structural foam, or fiberglass, and contains a powerful grinder-ejector pump. These are rugged units that rarely require maintenance, although foreign objects may resist grinding and jam the works. Depending on the unit, the basin measures a minimum of 18 inches wide by 30 inches deep. It can be located anywhere in the basement floor, but it’s important to allow floor space for the basin and all of the related piping, with access for maintenance. I try to install the basin outside the bathroom, close to the point where it connects to the existing sewer line. This also eliminates anything unfamiliar in the look of the new bathroom.

Demolition

To install the in-floor system, I remove an area of the concrete floor about 24 inches square for the basin, and cut a trench about 8 inches wide for the waste piping from the bathroom fixtures. Concrete demolition is dusty work, but I keep the mess to a minimum by using an electric jackhammer instead of pneumatic tools. Normally, the amount of concrete to be removed is fairly small. I remove the concrete and subsoil, then dig the basin pit to a depth of about 30 inches, so that only the top of the tank will be exposed. The hardest part of the job is now done, and my plumber can take over.