EIFS Revisited

EIFS Revisited

  • http://www.jlconline.com/Images/965860020_1012_JLC_EIFS_00a_tcm96-1079549.jpg

    true

    600

  • http://www.jlconline.com/Images/1743310768_1012_JLC_EIFS_01a_tcm96-1079550.jpg

    true

    600

    Before applying the WeatherSeal elastomeric waterproofing membrane, workers use plywood and duct tape to prevent the coating from dripping onto a concrete porch floor.

  • http://www.jlconline.com/Images/904830581_1012_JLC_EIFS_01b_tcm96-1079551.jpg

    true

    600

    The blue membrane is troweled onto seams and joints.

  • http://www.jlconline.com/Images/1607406250_1012_JLC_EIFS_01c_tcm96-1079552.jpg

    true

    600

    The membrane is reinforced with a special joint tape.

  • http://www.jlconline.com/Images/768926063_1012_JLC_EIFS_01d_tcm96-1079553.jpg

    true

    600

    Once the joints are treated, the entire surface will be skim-coated with the membrane.

  • http://www.jlconline.com/Images/281817767_1012_JLC_EIFS_02a_tcm96-1079554.jpg

    true

    600

    Once the WeatherSeal membrane has been installed, DrainEdge termination strips are stapled over door and window openings, followed by backwrapping mesh.

  • http://www.jlconline.com/Images/213865508_1012_JLC_EIFS_02b_tcm96-1079555.jpg

    true

    600

    The EPS panels are glued to the walls with adhesive that's been applied with a notched trowel. The notches are vertically oriented so that moisture can drain down the channels between the membrane and the foam and out of the wall assembly wherever the DrainEdge has been installed.

  • http://www.jlconline.com/Images/1103712931_1012_JLC_EIFS_02c_tcm96-1079556.jpg

    true

    600

    Installing the EPS panels.

  • http://www.jlconline.com/Images/1454916709_1012_JLC_EIFS_03a_tcm96-1079557.jpg

    true

    600

    Molded polyethylene kick-out flashings, like this one from Raintek, can be trimmed to fit different foam thicknesses. Kick-out flashings are installed with the step flashings.

  • http://www.jlconline.com/Images/548652376_1012_JLC_EIFS_03b_tcm96-1079558.jpg

    true

    600

  • http://www.jlconline.com/Images/1319012191_1012_JLC_EIFS_03c_tcm96-1079559.jpg

    true

    600

  • http://www.jlconline.com/Images/1063788178_1012_JLC_EIFS_03d_tcm96-1079560.jpg

    true

    600

  • http://www.jlconline.com/Images/38036237_1012_JLC_EIFS_04a_tcm96-1079561.jpg

    true

    600

    The author fabricates trim details like these bullnose returns with a hot wire cutter.

  • http://www.jlconline.com/Images/576511769_1012_JLC_EIFS_04b_tcm96-1079562.jpg

    true

    600

    After the foam has been glued to the walls, all of the gaps between panels are filled with spray foam.

  • http://www.jlconline.com/Images/1047203155_1012_JLC_EIFS_05a_tcm96-1079563.jpg

    true

    600

    Base-coat application can begin after the foam has been leveled with a rasping board and abraded with a grit-welded float. Inside and outside corners get a double thickness of reinforcing mesh bedded in the base coat.

  • http://www.jlconline.com/Images/979250896_1012_JLC_EIFS_05b_tcm96-1079564.jpg

    true

    600

    To help with adhesion, these walls received a second base coat, which was then scratched with diamond mesh lath.

  • http://www.jlconline.com/Images/72986563_1012_JLC_EIFS_06a_tcm96-1079565.jpg

    true

    600

    Most EIF systems have a smooth and uniform finish coat, but this home was given a deeply textured finish coat to match the Mediterranean architecture.

  • http://www.jlconline.com/Images/543677949_1012_JLC_EIFS_07a_tcm96-1079566.jpg

    true

    600

    Expansion joints are needed in EIFS cladding wherever two dissimilar substrates meet, such as at the foundation.

  • http://www.jlconline.com/Images/1082153481_1012_JLC_EIFS_08a_tcm96-1079567.jpg

    true

    600

    Corbels and other architectural details can be added to EIFS cladding by gluing foam profiles to the EPS before applying the base coat and finish. Areas that don’t require insulation, like the columns supporting the arches on this home, can be wrapped with cement backerboard instead of foam, which gives them better impact resistance.

  • http://www.jlconline.com/Images/1552844867_1012_JLC_EIFS_08b_tcm96-1079568.jpg

    true

    600

    The finished project

Base Coat and Mesh

The adhesive we use to attach the panels to the wall usually dries in about 24 hours, so we can start applying the base coat to the foam the next day (see slideshow). On most surfaces, we use TeifsBase adhesive, but on sloped walls we use waterproof Parex WeatherDry, which comes premixed in a bucket.

Impact resistance. The standard mesh we embed in the base coat weighs 4 to 5 ounces per square yard and comes in 38-inch-wide rolls. It provides impact resistance and helps us screed the base coat. For high-impact areas, we use higher-tensile-strength meshes of up to 20 ounces per square yard. These meshes have a factory-applied coating that helps prevent the portland cement in the base coat from corroding the glass in the mesh.

The project shown here had several high-impact areas that didn’t need exterior insulation, like the porch columns and garage. In these places, we installed cement board over the gypsum sheathing. To provide a thermal break that would help prevent the framing from showing through the stucco finish coat, we specified 30-pound felt paper between the cement board and the sheathing. We used what is called a direct applied finish system — or DAFS — over the cement board, which includes fiberglass mesh embedded in a base coat. The same finish can be applied to both DAFS and EIFS base coats.

Applying base coat. We start with the backwrapping, troweling base coat onto the exposed EPS panel edges, pulling the previously stapled mesh around the corners, and then using the trowel to bed the mesh in the mortar. Next we double-wrap the inside and outside corners with 9-inch-wide reinforcing mesh, using a 90-degree corner trowel to smooth out the inside corners and give them clean, straight lines.

When we apply the field mesh, we trowel on vertical courses of 1/16-inch-thick base coat that are a little wider than our roll of 38-inch-wide mesh. We bed the mesh in the base coat with our trowels, working from the center out and overlapping adjacent courses of mesh by at least 1 1/2 inches. When we’re done, the surface of the base coat is smooth, with no mesh visible.

Primer and Finish

Primer is optional under some Teifs finishes and required under others. It’s basically an acrylic paint that rolls on quickly; we like to use it because it seals the surface of the cementitious base coat and reduces water absorption and the risk of efflorescence. It also improves the bond between the base coat and the finish.

One of the strongest selling points of EIFS is the wide range of standard and custom stucco finishes that I can offer to my clients. The owners of this home wanted a thick aged limestone finish coat with a deeply mottled surface. As we worked with them to fine-tune its appearance, we had trouble getting the thick finish coat to adhere to the thin — but very strong — base coat. So we doubled up the thickness of the base coat with another trowel-on layer, then scratched the surface horizontally with diamond mesh lath intentionally cut to give it a rough edge. The new scarified base coat performed like a scratch coat under a traditional stucco finish, making it much easier for the heavy 3/16-inch-thick finish coat to adhere to it (see slideshow).

Cost

We always provide our customers with a breakdown of our costs when we bill them for EIFS. That way, they know exactly what they are paying for line items like setup and scaffolding, the WeatherSeal membrane, EPS foam, finish, and any sealers.

Without a detailed set of plans, I avoid giving customers an exact square-foot quote for a finish because prices can range so widely, depending on the size of the house, the type of trim, and the number of door and window openings. A large house with few openings will cost significantly less per square foot than a small house with lots of windows and doors. But for an average house with an average number of openings, it costs between $1 and $1.75 per square foot to apply the WeatherSeal waterproofing system. On this project, we charged about $10 per square foot for the 5-inch-thick EIFS cladding and custom finish (see slideshow).

Barry Jenkins is a stucco contractor in Knoxville, Tenn.