
I'm a residential contractor in Harwich, Mass., a coastal area
with salty air, strong winds, and cold winters. For the past
five years, my company has been building custom homes using the
ReddiForm ICF (insulating concrete form) system. While I
routinely use ICF foundations, many of my waterfront clientele
have also elected to build with ICFs above grade. A recent
project included an ICF home and a 24x36-foot freestanding
two-story garage with a drive-in basement. The garage had a
large single bay entry at the basement level, three car bays on
the main level, and a home office upstairs. The garage itself
was conventionally framed, but the main level had to be capable
of supporting three vehicles, a considerable live load. While
precast, hollow-concrete deck planks are available for this
kind of application, I decided to check out an ICF-related
system for pouring a structural concrete floor. The system,
called Insul-Deck (Florence, Ky.; 800/475-6720,
www.insul-deck.org), has been in use since
1978 and is licensed to ReddiForm under the name Reddi-Deck
(ReddiForm, Butler, N.J.; 800/334-4303,
www.reddiform.com).
Pouring a heavy concrete slab over fluffy-looking EPS
(expanded polystyrene) form panels may seem like taking the ICF
concept a step too far. Actually, the Reddi-Deck system offers
some advantages over precast concrete panels and conventional
cast-in-place floor methods. The panels are lightweight
— about 2 pounds per linear foot — and very
easy to handle (see Figure 1). Two workers can carry and place
a 40-foot-long panel without a crane or much strain. The
2-foot-wide panels connect with a tongue-and-groove flange and
assemble quickly.

Figure 1.At roughly 2 pounds per linear foot, the
interlocking deck panels can be carried and set in place by a
single worker with relative ease.
Spans up to 40 feet are possible without intermediate support.
The finished system is said to be less than half the weight of
a comparable precast system. And the manufacturer claims that a
trained crew can set the panels and steel reinforcement, ready
for pouring, at a rate of 1 square foot per minute. That claim
turned out to be fairly accurate in our case, even the first
time out.
Stay-in-Place Forms
In essence, Reddi-Deck is a concrete-slab-and-joist forming
system. The joist sections remain concealed within the EPS
formwork, while the underside presents a completely flat, fully
insulated ceiling profile (Figure 2).

Figure 2.
Conjoined foam panels create a negative
form of the cast concrete "T-beam" floor system. The
tongue-in-groove joist-forming flanges provide a positive seal
against concrete leakage between forms. Integral utility chases
provide convenient channels for plumbing, wiring, or hvac
runs.
Inside each 2-foot-wide foam panel are two side-by-side 4
3/4-inch-diameter round "utility chases" and four 1
1/2-inch-diameter wire chases. A pair of integral lightweight
steel Z-beams stiffen the form and allow clear spans up to 8
feet, including the live and dead loads of workers and
concrete. The bottom beams of these are exposed on the
underside of the form and provide visible, 12-inch-on-center
furring strips for drywall or other finished ceiling.
The 12-inch-thick forms, capped by a 4-inch-thick slab, create
a somewhat deeper floor system than a typical precast slab or a
concrete-on-steel deck. But it's no thicker than many I-joist
floor systems, so, as long as any headroom issues and height
restrictions are taken into consideration during the design
stage, floor thickness isn't a problem.
Two Pours in One
The Reddi-Deck system is designed to be compatible with an ICF
wall system. As with a supporting masonry wall, the high
compressive strength of the poured concrete wall provides more
than sufficient bearing for the heavy (70-psf dead load) floor.
And, by cutting the deck panels short enough to bear only on
the inner edges of the ICF wall blocks, the wall cores remain
exposed and accessible, allowing walls and deck to be poured
together in a single continuous operation. This saves the
expense of hiring a concrete pump twice.
Supporting walls. To set the
wall forms, we first poured a 24x36-foot thickened-edge
monolithic slab, level around the perimeter and sloped in the
field to drain toward the drive-in end. We stacked the ICFs 9
feet high, adding horizontal #4 rebar to every other course of
the foam blocks. In addition, we set vertical #5 rods in the
center of every other cell, about 20 inches apart. The rebar is
spaced and centered using proprietary wire chairs and guides.
However, it's important to have the rebar schedule designed or
approved by a qualified engineer; the manufacturer suggests
rebar weights, diameters, and distribution only for estimating
purposes.
To brace the ICF forms, we use site-made 2x4 staging brackets,
that both brace the forms and provide working access to the top
of the wall (Figure 3). Adjusting screws at the anchor end of
the diagonal braces make it easy to plumb the forms.

Figure 3.The author's site-made staging brackets
provide lateral support to the ICF wall forms during the pour,
as well as access to the top of the forms for pumping concrete
and setting the anchor bolts and sill plate. Backers on the
opposite side of the wall provide external bracing and catch
the 16-inch-long screws used to attach the staging to the form
work.
Backers. Since you can't
attach nails or screws directly to the foam, we use 2x4 backers
on the opposite side of the wall forms. The backers also help
to brace the wall form. We use 16-inch-long hex-head LogHog
screws (Olympic Manufacturing Group, Agawam, Mass.;
800/633-3800, www.olyfast.com), which I buy by the case,
to attach the brackets. We drive them through the narrow edge
of the 2x4 bracket uprights, through the foam, and into the
narrow edge of the backers. By aligning the brackets over the
webs in the foam blocks, rather than through the cells, we're
able to retrieve the screws for reuse. The best way we've found
to drive the screws is with an electric impact wrench.
With the walls braced, we apply Sealtight, a self-adhesive
waterproofing membrane (W.R. Meadows, Hampshire, Ill.;
800/342-5976, www.wrmeadows.com), to the exterior face
(see Waterproofing
ICF Foundations, 2/00). Ordinarily, I wait to do this until
after the forms were poured and the bracing removed, but on the
job shown here, I was concerned that the sandy excavation would
begin to cave in and partially bury the walls while we waited
for the deck forms to be delivered. It was a bit of a nuisance
to remove and replace the backers to apply the membrane, and we
had some little screw holes in the membrane to repair later,
but this seemed like a smart trade-off against heavy shoveling
and cleaning.
Perimeter Forms
To form the slab perimeter, we used full 4x8-foot sheets of
3/4-inch-thick Advantech subflooring, which we had on hand for
the top floor. To protect it for reuse, we stapled 6-mil poly
over it. We attached three 8-foot 2x4 vertical uprights on
4-foot centers to each panel, with a 2x6 "top plate" across the
top. We attached these temporary forms end to end around the
top of the wall, setting them 18 inches higher than the top of
the ICF forms (Figure 4).

Figure 4.Perimeter forms were required to contain
the edge of the poured floor system. Subfloor panels served
temporary duty as form panels, attached in the same manner as
the wall brackets, using 16-inch LogHog screws and 2x4 backers.
Plywood scraps pack out the bottom of the vertical braces to
hold the panels flush and parallel to the outside wall
surface.
To attach the forms, we drove LogHog screws through the
vertical braces and into 2x4 backers on the inside. Though we
connected the top plate sections with short 2x6 scabs, we still
had some bulging at the top edge during the pour, which we
fixed with screw jacks (Figure 5). But in the future, I'll use
a continuous second 2x6 plate to reinforce the top edge.

Figure 5.Excavation made it difficult to install
counter bracing on the exterior side of the wall. However, it
proved to be essential to countering the tendency of the
perimeter forms to bulge outward during the pour. Screw-jack
adjustments at the base of the braces pushed the forms back
into position.
Falsework
Like any cast concrete, cast-in-place joists attain the
designed structural properties only after a minimum 28-day
curing period. During the pour and the entire curing period,
the floor system is supported by "falsework," or temporary
shoring under the forming panels. At 70 psf, the weight of this
864-square-foot floor would top 30 tons.
I opted to rent ready-to-go falsework from A.H. Harris
(860/665-9494, www.ahharris.com), a large concrete
contractor and forming consultant that serves New England, New
York, New Jersey, and Virginia. The company provided a layout
plan for the falsework, ensuring that we'd have the proper
spacing and support for the overhead concrete. The entire
package cost about $1,000 for a one-month rental.
The falsework consisted of heavy-duty 4x6-foot steel pipe
staging, with screw jacks top and bottom (Figure 6). Each leg
was rated for a working load of 12,000 pounds. On top of the
staging, W8x10 I-beam strongbacks, set in U-head saddles over
the upper screw jacks, provided distributed support for the
deck forms.

Figure 6.The deck pan was supported by a series of
4x6-foot steel frames and braces, topped by sectional steel
I-beam strongbacks. The strongbacks were arranged in four
parallel rows on nominal 7-foot centers.
The falsework was delivered by flatbed trailer; but the truck
couldn't make the turn through the subdivision's narrow stone
gate. We ferried the frames and accessories to the site on a
smaller trailer, making a couple of trips. None of the
equipment was particularly heavy; at 13 pounds per linear foot,
the I-beams were the heaviest pieces, but none was over 7 feet
long. This was an unanticipated snag, however, and had we
ordered precast deck planks or panels, the problem would have
been much harder to solve.
We set the frames, braces, and beams up in four parallel rows
running the 36-foot axis, according to the shoring plan.
Drainage slope. We pitched
the falsework to provide floor drainage toward the overhead
door side by raising the opposite side 2 inches over the
24-foot-wide span. Not only is such drainage for a garage floor
required by code, but given the building's proximity to the
ocean and salt spray, I wanted to make sure that salty water
couldn't puddle and soak into the floor and corrode the
reinforcement steel. To ensure a flat surface, we stretched a
stringline across the 24-foot end wall to represent the
finished floor line at the planned pitch, then laser-leveled
each strongback course at its location along the line. Because
the ICF blocks were level around the perimeter, we glued
2-inch-wide foam rippings along the top of the 36-foot side.
Expanding urethane foam is the ICF adhesive of choice. We used
a combination of foam rippings and expanding foam to fill the
tapering, 24-foot end-wall returns.
Camber. To compensate for
the calculated dead-load deflection, I also planned to
introduce a 3/4-inch positive camber at center span. I didn't
want the floor to settle and allow water to puddle. We raised
the two middle strongbacks higher than the two outside courses,
creating a convex floor profile across the foundation. The
screw-levelers enabled us to make precise adjustments to the
floor line.