Framing with Pre-Cut Components Continued
Any stud material that is not straight and true is moved to
the cut station, where it is used for cripples, blocking, or
plates for small walls. Lumber will always move. Crowns become
more pronounced. Twists and cups develop. We make sure that all
the studs that go into our packages at least start out
straight.
Final Assembly
As the wall plates and components are completed, they move to
the final assembly station. Yard foreman Dave Gonzales oversees
this critical step as the triple check in our quality-control
process. He begins assembling each package with the third copy
of the wall and component lists. He verifies that the plate
crew has provided every wall required and that the buildup crew
has delivered the correct type and quantity of component
assemblies. Dave is a real perfectionist. It's not uncommon to
see him breaking out his power planer to smooth blocks in a
channel that don't flush up just right. Anything that doesn't
look good to Dave is rejected. He knows that we count on him to
catch any errors that might have slipped by the rest of us. We
do not hurry him. If he is not 100% sure that a package is
correct he knows that he won't catch any grief from us if he
tears the whole thing down and starts over. When it leaves our
yard it has to be right.
Holding platforms. We developed a set of small
platforms to hold the stickers or support boards under the
package. Each platform is designed to hold a double 2x4 sticker
that is 48 inches long. The platforms provide a space so that
banding material can slide through beneath the double 2x4. The
4-foot-long double 2x4 stickers come from materials that I deem
to be "terminally crooked" at the cut station. Even the most
unruly board will find a home and a useful life in our shop.
Once the banding is in place, the sticker is secured to the
package. This gives us a full 3-inch clearance for the forks on
the lift. Providing ample clearance below the package enables
the forklift operator to unload and stack unit packages
unassisted. He never has to get off the lift because each
package has adequate blocking below it to allow his forks to
clear. Furthermore, the stickers are laid out on a standardized
grid, six to a package. This enables us to stack each package
atop another without any additional blocking.
Wrapping the package. All of our packages are
wrapped to protect them from moisture and ultraviolet light. We
order all our materials wrapped to help keep them in the best
possible condition. We recycle all of our lumber wraps as
covers for the completed product. When we run short of
recyclable wrapping, we use a 6-mil black plastic cover.
|
|
Figure 6.
Carpenters assemble pre-cut wall panels on site
(top). Wall plates are stacked at the far end of
the table, headers, sills, cripples, and tees are
stacked to the left, with finished walls to the
right. Everything required is in the package. The
compact lumber packages will result in an enormous
pile of wall panels. Two short walls at the bottom
of the pallet are used to create clearance for the
forklift (middle). Carpenters can spread and erect
wall panels very quickly. Notice how clean the area
is (bottom).
|
On Site
The walls are assembled in a prefab area on site (Figure 6
above), stacked, and the plastic cover reused to protect the
finished walls until they can be installed (often this is the
third useful life for these covers). In this way, fabrication
can start well before the concrete slab is completed. By the
time the slab is ready, all the walls for that building are
framed and ready to be stood up.
Getting a head start on the walls can greatly reduce the
time required for framing, thereby accelerating the overall
project schedule. However, we feel that the greatest benefit
from the system is realized by placing a framing table directly
on the slab and assembling the walls near where they are to be
used. Another small crew can then erect the walls once the unit
is completed. This eliminates the need for stacking, banding,
and moving the packages of finished walls, which is in itself a
time-consuming process.
No waste
. When we started
on our current project, we had a large dumpster delivered to
the yard for all the scrap that we expected to generate. After
three weeks of operation we don't have enough waste to fill the
back of a pickup truck (Figure 7).
| Figure
7. This is all of the framing waste from a
60,000-square-foot project, plus somebody else's trash
— barely a small pickup load. |
I look at it this way: You pay for lumber, you pay to have
it delivered, you pay to have it cut up, and if you throw it
away, you pay to have it hauled off. So to me, careful use of
materials and recycling is just good business. Whether you want
to save the world or save a buck, you end up doing many of the
same things.
Most importantly, the guys in the field love our packages
because they are right. Not sort of, not really close, but
right on the money!
Michael
Davis is the owner of MDI in Albuquerque, N.M., which
offers hybrid prefab services to contractors on Colorado's
Western Slope.