Before work began, the building stepped back on the second and third levels. Additions on the two levels will align with the brick wall of the main level.
Slideshow: Demolition and site challenges
With the back patio demolished, block work begins.
Slideshow: Demolition and site challenges
Along with the block work, an extension of the basement-level slab is prepped for the pour.
Slideshow: Demolition and site challenges
With the basement-level block walls up, the crew receives the individual pieces of steel C-channel for the beams, threading them through a front window.
Slideshow: Demolition and site challenges
With no way to crane the steel where it's needed, carrying them through the house was the only option.
Slideshow: Demolition and site challenges
The lengths of C-channel are placed atop the block walls to be fabricated into beams.