Fast-Tracking a Pop-Top Addition - Continued
We measured the floor deck and found that it was about 2 inches
out of square. This wasn't a surprise: I had known something
was off when I measured the house during the design phase.
Instead of trying to figure out the exact problem then, I'd had
the panel producer make the panels as if the house were
perfectly square. I knew we could make field modifications
later.
The out-of-square floor deck required that we shorten one wall
panel and extend another. The process was easy: With two guys
working, the alterations took about 10 minutes (Figure
5).
Figure 5. Because the existing floor was 2
inches out of square, the crew had to lengthen one wall panel
by removing the last stud (A), cutting off the plate (B), and
replacing the stud (C). Another panel was lengthened with
plywood spacers (D).
We finished out the day straightening the walls. The panels
come with a single top plate; you add the double plate to
stitch the wall together, then plumb and string it or site it
as usual.
We were lucky that we had great weather, because effectively
tarping the second floor with the walls standing and no roof
would have been nearly impossible. If rain had been in the
forecast, I probably would have kept the crane on site and
worked as long as necessary to set the trusses. With the
trusses up, I could have tarped the structure; luckily, this
wasn't necessary.
Thursday: Setting Trusses
The next day, while waiting for the crane, we installed a
two-ply girder truss for a small intersecting gable over a
bedroom bump-out (Figure 6). We knew having this in place would
make setting the rest of the trusses go much faster. We also
prepped the gable trusses and got some braces and spacers
ready.
Figure 6. In preparation for the crane's
second visit, the crew installed the girder truss for a small
bump-out (A). The gable truss was prepped with building paper
(B) and preinstalled blocking for the drywall ceiling (C). When
the crane arrived, truss-setting moved quickly (D); note the
vertical bracing for the gable truss, installed on the inside
rather than the outside of the end wall.
When the crane arrived, we began by lifting the interior wall
studs and the roof sheathing up onto the second-floor deck,
then started placing trusses. With the first gable in position
but still suspended from the crane, we installed temporary
bracing. Most framers place vertical braces on the outside of
the building, which requires ladders or staging, but I like to
put them on the inside because it can be done easily from
stepladders.
The rest of the trusses were set very quickly. To keep things
moving, we typically have the crane lift the trusses in pairs.
The timing works perfectly: While we're setting and bracing two
trusses, the operator can pick up another pair and have them
ready for us by the time we're done with the first two (Figure
7). We were able to stock the second floor with material and
set all the second-floor trusses within the three-hour minimum
crane charge.
Figure 7. Lifting trusses in pairs
eliminates waiting: There's just enough time to set the two
trusses, using precut braces marked with the layout (right),
while the crane operator picks up the next pair. Unlike longer
braces, the 491/2-inch-long pieces don't get in the way of the
next trusses to be set.
Once the trusses were in place, we immediately started
sheathing the roof. Handing the sheathing up from the
second-floor deck, we tacked it in place, aligning the trusses
as we went, then had one guy finish it off with a coil framing
nailer. He was responsible for making sure all the sheathing
was solidly nailed and that nothing was missed.
The main roof was completely sheathed by the end of the day. We
could have stuck around for another hour or two and felted the
roof, but with no rain in the forecast we went home.
Friday: Roofing
The roofers showed up Friday morning. They got started on the
front side of the roof while we finished up filling in the
valleys on the gable bump-out and installing subfascia on the
back.
By noon the roof was shingled and I was able to breathe a
little easier.
Planning Paid Off
The following week, we built the porch roof, finished off the
interior partitions, and moved on to doors and windows.
The rest of the job was a matter of scheduling subs to bring it
all together. The granite countertops and custom shower doors
were templated the day before I left on vacation. When I got
back, the countertops and finished flooring had been installed,
so I just had to arrange for the plumbing trim-out and for
final inspections, and complete a few items on the punch
list.
The house had gone through quite a transformation (Figure 8).
In addition to gaining an extra 1,000 square feet of living
space, it now had a luxury master bath, a porch, a back deck,
and a wood-burning fireplace.
Before
After
Figure 8. The completed home (left) looks
vastly different from the original structure and has 1,000
square feet of additional living space. The family-room
addition on the back of the house (below) contains a cathedral
ceiling and a wood-burning fireplace.
The project's $270,000 price tag might seem high, but in this
area it's tough to find an existing home for less than
$500,000, and you'd pay a similar amount for a 1/2-acre
building lot — if you could find one.
Dave Haines owns Haines Contracting in
Doylestown, Pa.