By Quenda Behler
Story
The change order clause in many construction contracts calls
for the architect or the customer to receive a certain number
of days' notice in advance of proposed change orders and/or to
preapprove contract changes in writing. If you run a
construction company and work regularly with subcontractors,
you want to follow the contract procedure, because otherwise
you might find the architect or the customer refusing to pay
for those change orders.
But we all know what happens on the job site. The site
superintendent sees that, although the specs call for 2x8 floor
joists, the span will actually require 2x12s. The job is in
Grand Rapids, Mich., where hunting season has started, and
whoever is supposed to approve change orders has his cell phone
turned off so he won't scare the deer. The superintendent knows
that waiting will bring the job schedule to a very expensive
halt, so he tells the subs to go ahead and use 2x12s.
The work proceeds, but then, when the site superintendent
starts the second floor, he discovers that things don't line up
properly between the floors. This time he doesn't even try to
chase down whoever is supposed to preapprove change orders; he
just goes ahead and tells his subs to make the necessary
changes.
So, suppose you're the contractor in this example. You know
those change orders were not approved in the way the contract
called for, but maybe you don't worry about it, because it was
all essential to the job, the architect or customer was
informed (after the fact) and didn't object, and, anyway,
nobody is going to try to get out of paying people for
necessary work that actually saved them money in the long
run.
Excuse me, I have to stop and snicker.
Case in Point
An appeal of a lawsuit, Amprite v. Tennessee Stadium
Group, is pending in the Tennessee courts on this very
question: If change orders are issued differently from what the
contract calls for, can the subcontractor -- who, after all,
has a copy of that contract -- get paid for his work on those
change orders? This is such an important question -- and one
that comes up all the time -- that the American Subcontractors
Association has intervened in the Amprite appeal to help
the subcontractors win.
The Amprite case involved one of those "fast track"
contracts with an early completion bonus, so everyone on the
site was under pressure to move the job along as quickly as
possible. Following the contract procedure on every change
order would have slowed things down, so the contractor didn't
follow it. When the subs expressed their concern that the
contract approval procedure was not being followed (which they
did on several occasions), they were told not to worry, they'd
get paid anyway.
But when it came time to settle up, the owners, who were not
the ones who had made what amounted to a waiver of the change
order clause, wouldn't pay. So the contractor said, in essence,
to the subs: Sorry about that.
The electrical subs then sued the contractor for payment of
almost $2 million worth of change orders.
Why should you care if the Amprite subs get paid, especially
considering that you probably never expect to have a job with
$2 million worth of any kind of change orders?
One reason you don't want to see your subs have trouble
getting paid for change orders is that if the property owner
weasels out of paying, the subs usually can't sue the property
owner -- so they'll sue you. (After all, that's why they're
called subcontractors -- because they contract with the general
contractor, not the customer.)
Also, even though the contractor is the defendant in
Amprite, in many cases involving improperly authorized
change orders, the contractor is the plaintiff and is trying to
collect from the property owner. And that contractor is going
to be relying on the same legal arguments the Amprite subs
used.
Legality vs. Fairness
The electrical subs in Amprite won their case at the
trial level, where the court's 36-page opinion discussed the
various legal theories -- such as quantum meruit arguments,
possible waivers, and implied contracts -- that might be used
to order the defendant to pay the subs. Ultimately, the judge
boiled down all of those theories to this idea: No matter what
the contract says, it's not fair for someone to stand silently
by while a subcontractor does the work and, then when the bill
comes in, yell, "Gotcha!"
The Amprite judge wound up saying to the contractor, in
effect: Hey, remember that bonus you got for early completion?
You were able to finish early by promising your subs that they
would be paid, so that is an implied contract, between you and
the subs, to pay them from your bonus money.
Does that judge's opinion mean that you and your
subcontractors can rely on those legal theories when it comes
to collecting from the property owner for an unauthorized
change order that caused a $500 cost overrun? No, you
cannot.
The sheer number and variety of legal theories on this subject
clearly indicate that the outcomes of these cases are not
predictable. Sometimes the subcontractors will win, and
sometimes they won't. Generally speaking, courts don't like to
rewrite contracts. After all, if the parties to the contract
didn't want to use the change order procedure prescribed in it,
why didn't they just renegotiate the contract?
Because there's so much unpredictability in these kinds of
lawsuits, the contractor in Amprite appealed the trial judge's
decision. That's why the ASA got involved: The organization is
trying to firm up the legal ground beneath its member's feet by
establishing a precedent that will support the best interests
of subcontractors.
So what's the lesson here for you? First, if you're a
contractor, pay close attention to how those change order
procedures are written in the contract, because you need to be
able to work with them in the real time of the job. If you're a
subcontractor, read the clause on change orders before
you do the work. This is important, because you might not be
able to collect on a change order that was not authorized
exactly according to the contract procedure.
has practiced and taught law for over 25
years and is the author of The Contractor's
Plain-English Legal Guide
(http://www.craftsman-book.com).