Segmental Block Retaining Walls, continued
When we build a wall on the site of an existing building, our
first question is whether the spot we're building on was cut or
filled when the structure was originally built. We must be
absolutely sure to place the wall either on virgin ground or on
properly compacted fill.
Building a wall on uncompacted fill is an invitation to
disaster. I remember one job site where a deck contractor built
his deck on posts bearing on pad footings set below our area's
42-inch-deep frost line, just as code requires. Imagine his
surprise when the deck settled 10 inches! No one ever told him
that there was a 15-foot deposit of fill under his footings
because the house was built on a steep slope. The soil under
and around a retaining wall might experience forces greater
than the weight of a deck footing. If that wall is placed on
uncompacted fill, it's going to move.
Once we're sure the wall will rest on native soil, we still
need to know the soil type, because that determines what kind
of base preparation is required. For simplicity's sake, I'll
talk here about the broadest soil categories: sand, gravel, and
clay.
A well-drained gravel soil is ideal: It locks into place to
provide good, stable bearing, and water percolates through it
quickly. Clay, on the other hand, can seem firm and solid when
you're digging in it, but if it absorbs water and expands, it
can become a nightmare, making the wall shift up and down. Sand
usually drains well, but it can be an unstable base.
Retained soil
characteristics. The soil that the wall will be holding
back also must be assessed to determine what engineers call its
"angle of repose" — the angle at which materials are
self-supporting.
Imagine three trucks dumping three different soils and making
three cone-shaped piles of soil. The surface of each pile would
naturally rest at a different angle with the horizontal —
that particular soil's angle of repose. The steeper the soil's
natural angle of repose, the less need there is to hold the
soil back or to reinforce it behind the wall. And we always
place the geogrid so that it extends past the line of that
angle and embeds itself in soil that is self-supporting.
For strong soils like gravel, the angle of repose is about 45
degrees. But you can't assume that it's the same in every
instance. In critical cases — walls that have to support
loads imposed by decks, patios, driveways, or buildings —
we remove all the natural material from behind the wall until
we are sure that the only thing the wall has to support is our
imported granular backfill.
Consulting an engineer. We
can usually assess the site soil conditions ourselves, but not
always. If we are uncertain about anything, we bring in a soils
engineer. Good soils engineers are worth their weight in gold
— they can help you prevent a problem today from becoming
a nightmare later on.
I generally call an engineer if the wall needs to support any
unusual load, such as a parking lot or a building. I also bring
in an engineer if I feel the need for a little extra peace of
mind. For example, I consulted one recently when a customer
called me to repair a failing wall that another contractor had
built incorrectly. The engineer confirmed my assessment of the
situation, and together he and I designed a replacement wall. I
probably could have figured it out, but since the job was
already problematic, I appreciated the additional security. (If
the original builder of the wall had followed an engineer's
advice, of course, I would not have had to be there in the
first place.)
Base Preparation
Once you know your soil conditions, you can move forward with
preparing the subgrade, placing a compacted gravel base, and
beginning to place block.
Subgrade. We always compact
the existing soil in the bottom of our trench. You may need an
engineer to specify the compaction method and to verify that
you've compacted sufficiently — or at least to check the
results you're getting with your compacting equipment at the
beginning, until you're comfortable that your methods are
working.
How we treat native soil depends on the soil type. Firm gravel
is fine; we put our base stone right on top of it. If the soil
is clay, we dig down at least double the recommended depth
before placing our base material (if the manufacturer's
literature calls for a 6-inch compacted stone base for a 4-foot
wall, for instance, we'll dig a foot before placing the stone).
Loose sand should be completely removed. But if it's too deep
to practically remove, we dig extra deep and lay a
soil-separating fabric, then place our stone on top of
that.
Base material. Next we place
the base material (Figure 3). In New York, we use "crusher
run," a crushed stone mixed with stone dust to lock it solidly
into place. We can tamp that nearly as solid as concrete with a
walk-behind plate compactor.
Figure 3.A base of "crusher run," ground stone and
stone dust, is placed in the footing trench and tamped hard to
support the base course of block. The taller the wall or the
less firm the subgrade soils, the deeper and wider the base of
crusher run should be.
The base is always at least twice as wide as the wall blocks;
the planned height of the wall determines the base material's
depth. For low walls (less than 2 feet tall), we use about 3 to
6 inches of base thickness. Larger walls can have as much as 2
feet of base below them. We place the material in 3-inch lifts
and tamp it down with walk-behind plate tampers to ensure
proper compaction. Once the base is placed and compacted, you
can begin to build.
We generally bury at least half of the base course of block
below the original grade to restrain the toe of the wall from
kicking forward under the pressure of retained earth. For
taller walls subject to higher soil pressures, it may be
necessary to bury one or two full courses of block or more. The
engineering documents required for walls higher than 4 feet
should specify the embedment depth of the wall's base. In the
case where the downhill slope continues at the base of the
wall, the calculations are more complicated and the required
depth of the wall foot is typically greater (Figure
4).
Toe Embedment Anchors the Wall
Base |
Figure 4.The author likes to firmly bed his base
course of block into the granular base by beating the block
with the top of the pick handle (top). He prefers to use the
heavy Versa-Lok units shown here because in his experience they
stand up to this treatment better. The depth of the first
course of block ("toe embedment") varies depending on site
characteristics (bottom). If the ground slopes downhill from
the wall base, manufacturer specs call for a deeper embedment
to hold the base in place.
I like to pound my base course blocks into the layer of
crusher run to make sure they're firmly seated. We smack them
with the end of the wooden pick handle. That's one reason I
personally prefer solid block units like Versa-Lok to hollow
block systems — occasionally, I've broken hollow units by
hammering on them.
Some companies make oversized base units for extra stability
on very large walls. And if we're working with wall systems
that use pins to hold segmental units together in the wall, we
sometimes pin the base course blocks to the ground using
3/8-inch rebar, to help anchor the wall base to the
earth.
Drainage. Without question,
the most critical factor in retaining wall construction is
drainage (Figure 5). Without it, walls will be exposed to
hydrostatic pressure (which can double the load on the wall).
In the North, poorly drained soils will expose the walls to
frost action. If you see a wall that's bulging in the center,
chances are that it's not properly drained; it's only a matter
of time before it fails.
Figure 5.A drain tile in the granular backfill,
sloped and run to daylight, is critical for retaining wall
performance. It helps keep frost problems to a minimum and
maintains soil behind the wall in a drained condition to reduce
lateral pressure of soil against the wall.
We always bury at least a 4-inch perforated pipe behind the
wall. The pipe should be wrapped in a landscaping filter fabric
and run to daylight out of the wall and away from the
base.
Backfill and geogrid. We
backfill all walls with a #2 crushed stone, placed and
compacted in lifts of 6 inches or less, and layered with
reinforcing geogrid (Figure 6). It's important to lay landscape
fabric on the slope behind the wall, so that dirt does not wash
into the stone — silt material impedes drainage and can
clog the drainpipe or its filter fabric wrap.
Figure 6.Space behind the wall is backfilled with
1-inch and 2-inch gravel, placed in 3- to 6-inch lifts and
compacted in layers (above left). Geogrid at specified
intervals (above right) locks the compacted fill into a single
mass, which holds back the natural soil or fill behind it. The
grid also holds the face block in place, either by interlocking
with gravel placed into the block cores, or by engaging locking
pins as in the Versa-Lok system shown at left.
The geogrid spacing and the distance it runs back from the
wall into the slope are important factors in the wall's
strength. The geogrid requirements are usually determined by
the height of the wall, the soil type, and any additional load
on the earth above the wall. Most walls get geogrid at least
every 2 vertical feet in the wall and extending into the slope
twice the height of the wall at the point where the geogrid
lies. But the geogrid length varies in different soil
conditions — the material needs to extend well past the
line of the soil's angle of repose, so that it will stay firmly
embedded.
Geogrid is locked into the wall face by pins, by friction
between the block units, or by stone fill placed inside hollow
block units, depending on the manufacturer. That's to hold the
face block in place. But geogrid also separates the backfill
into different layers, working to prevent the soil from
slumping and increasing the stability of the wall. The grid
effectively locks the backfill soil into a solid mass that acts
as a heavy, bulky gravity wall.
Terraced walls. If you're
building a terraced wall, where the upper wall will be built on
the backfill of the lower wall, the geogrid becomes especially
significant. You may need engineering in those cases. In
general, terracing should be designed so that the lower wall
does not have to support the upper wall. A rule of thumb is to
set the upper wall back a horizontal distance at least one and
a half times the height of the lower wall.
A Wall That Failed
Two of my favorite books are a matched pair by Mario
Salvadori, the late Columbia University professor, titled
Why Buildings Stand Up and Why Buildings Fall
Down. Both are interesting, but I've always thought the
second one teaches more. When it comes to retaining walls, I
personally have learned more from structural failures than from
structural successes. Here's one of our stories:
We were called in to propose a wall for a client. This wall
was to be a terraced system of two walls, each to be about 4
feet of exposed wall. In addition to holding back soil, it
would support the back of the home and a deck, which would be
cantilevered over a 9-foot-tall stretch of the wall
system.
After receiving three proposals from three different
contractors, the client decided to go with the lowest price
(which wasn't us). I cautioned the client to make sure he had
structural diagrams and plenty of references from the chosen
contractor. He said he did.
The construction started in November 1995 and was finished one
month later. In January 1996, the client called me in to
evaluate the wall, which had already started to fail (sections
had started to fall over). I took a look at it and told him to
call an engineer. After many long meetings with the client and
the engineer, we decided to dismantle the wall and rebuild it.
Here's what we found when we tore into it:
First, instead of digging down deep enough to install a
12-inch base of crusher run and two courses of 8-inch block (a
total of 28 inches), the wall builders had set their base
course of block on 4 inches of crushed stone and explained that
they would fill in in front of the wall with 8 inches of
topsoil. They did not understand that the base needs to be
buried in the "inactive zone" of consolidated subsoil so as to
create a "passive wedge" strong enough to keep the base course
from sliding forward.
Second, along the 9-foot-tall section of wall supporting the
house and deck, the builders had rolled up the geogrid behind
the wall so they would not have to remove the existing railroad
tie wall. They just built the new wall in front of the old
wall, which had also been failing in the first place (that's
why a new wall was needed). There was no locked-together soil
mass to support the retained soil and the superimposed
loads.
But here's what really made me scratch my head: Instead of
running the downspouts from the back of the house into solid
pipe directed away from the wall, the builders had tied them
into the drainage pipe behind the wall! Five downspouts
deposited most of the home's roof runoff into the wall. And
they could hardly have made a worse choice for backfill: They
used blowsand, a cheap, poorly draining material that holds
about 19% moisture. In effect, they designed this wall to have
continuously saturated fill behind it.
The three most important things that make a wall strong and
durable are base preparation, drainage, and reinforcement. In
this case, all three were accomplished either shoddily or not
at all. With any of these items poorly done, the wall would
fail eventually; doing all three of them wrong was a recipe for
immediate failure.
We had quoted a price of $38,000 to build the wall originally.
When all was said and done, it wound up costing the client
$64,000. The moral of the story: Build it right the first
time.
Landscape designerBruce Zaretskyand partner Sharon Coates operate
Zaretsky and Associates, Inc., a landscaping design-build firm
based in Macedon, N.Y.