Excited to see an unexpected set of plans in the mail, I
ignored the accompanying cover letter and took a quick look.
The plans showed a nearly round addition to an elegant 1888
Victorian that would enclose a new window-filled dining area.
They also called for a gut and remodel of the kitchen and
adjoining bath downstairs, and a new master bathroom
upstairs.
After reading the accompanying project documents more
carefully, I realized that there were a lot of details that
would make bidding difficult — but my main concern was
the dining room. Could we build it without losing our shirts in
the process? Eager to get this interesting project, my partner
and lead carpenter Danny DoCouto pointed out that the room was
essentially a regular 16-sided polygon. While the angles would
slow us down a little, the actual construction — he
assured me — wouldn’t be all that different from
the more typical rectangular additions we usually build.
Foundation Layout
Normally we would build the foundation on a project like this.
But the adjoining part of the old house had so many problems
— including undersized girders and rotten joists and
posts — that needed to be addressed during the
renovation, we decided to sub out the new foundation. That way
we could repair the existing structure while the masonry work
was being done and be on site to oversee the layout of the
foundation.
The total width of the addition measured 15 feet from sill to
sill, with the polygon overlapping the existing house at the
sill plate by 6 inches. This put the center point of the
addition 7 feet away from the outside edge of the existing
sill, and the outer edge of the new polygon foundation 14 feet
6 inches away (see Figure 1).
Figure 1. Dividing the 360 degrees of a
circle by the number of sides in a regular polygon gives you
the apex angle (here, 22.5 degrees) of the isosceles triangles
that can be drawn around the center. Bisecting this angle gives
a right triangle that can be used to solve for the lengths of
the sides (x) with either a Construction Master calculator or
trig function (for example, tan 11.25 = opposite/adjacent). The
answer? x = 2 feet 11 13/16 inches.
A 16-sided polygon can be divided into 16 equal isosceles
triangles, each with a central angle of 22.5 degrees (360
divided by 16). Using this angle and the 7-foot 6-inch distance
from the center of the addition to the midpoint of each side,
we calculated the length of the sides.
Before digging the hole, we opened up the side of the house to
benchmark the height of the existing foundation and floor
framing and to locate the center of the new 10-foot 6-inch
opening that would connect the house to the addition. With
those dimensions for reference, we outlined the rough perimeter
of the foundation with spray paint, then used a rented
mini-excavator to dig a hole that would put the bottom of the
12-inch-thick footing more than 36 inches below grade —
below frost depth for our part of New Jersey.
Trench footing. I suggested that, instead of building
the angled footing form shown on the plans, the masons pour a
much simpler 2-foot-wide circular trench footing — a
change I ran by the building inspector. From the center of the
opening, we strung a perpendicular line off the house, then
measured 7 feet out from the sill and drove a form pin into the
ground directly underneath this point (Figure
2). From that center pin, we swung 6-foot and 8-foot
arcs representing the inside and outside of the footing
trench.
Figure 2. The addition’s block
foundation was built on a circular trench footing, laid out
from the center point of the 16-sided polygon (left). The
12-inch-deep by 2-foot-wide footing was dug by hand in the
bottom of the excavation and reinforced with rebar
(right).
Because the 16-sided room isn’t freestanding, the
footing layout had to deviate from its circular shape as it
approached the house, creating more of a horseshoe shape. The
masonry crew hand-dug the 12-inch-deep footing trench, laid up
the rebar on chairs, and poured the footing.
To lay out the block wall, we made a plywood template designed
to pivot on the center pin and used it to mark the sides of the
wall on top of the footings (Figure 3).
Starting at the outermost wall segment, we moved the template
left and then right, marking 11 segments on the footing. We
turned the next wall section on each side to intersect the
house at 90 degrees, as indicated in the illustration.
Figure 3. To lay out the foundation, the author cut a
plywood template based on the dimensions of one of the
isosceles triangles that make up the 16-sided polygon. The
template registers against the form pin at the center of the
addition; the end of the template represents each 2-foot 11
13/16-inch side of the polygon.
Block foundation. Because of all the angles, it made
more sense to stack the block than to use a running course. To
strengthen the wall, the mason used Durawall galvanized mesh to
overlap each joint and poured the cores, adding vertical rebar
on each side of the angles. To help the mason check his work
while laying up blocks, Danny mocked up a sill out of a pair of
2x4s cut at 11.25 degrees and joined together (Figure
4).
Figure 4. The stacked blockwork was reinforced with
galvanized wire mesh on each course. A mock 2x4 sill cut to the
exact angle and dimensions of two wall sections helped the
masons get the corners right as they laid up block.
While virtually every other block needed to be cut to fit, the
foundation was only five courses high, so it didn’t take
long to build. Once the masons finished parging and
dampproofing, they laid a vapor barrier and reinforcing mesh on
the inside and poured a 4-inch-thick rat slab. Before
backfilling, we also installed a 4-inch-diameter perforated
footing drain protected by a fabric sock.
Floor Framing
By the time we were ready to bolt down the PT sill and get
started on the framing, we had completed most of the structural
repairs to the existing house. Floor framing was
straightforward — except for having to cut 11.25-degree
bevels on both ends of 15 pieces of sill and rim joist, and
bevel seven of the 11 2x12 floor joists (Figure
5).
Figure 5. The rim joist was cut from 2x10 stock to
match the elevation of the existing floor, but the floor joists
had to be cut from 2x12 stock for the longest spans of the
polygon.
We used 2x12 joists to ensure that we ended up with a stiff
floor, notching the bottoms at each end to match the 2x10 rim
joists. (Code allows notching at the ends of joists — up
to a fourth the width of the member, or 2 13/16-inch in a
2x12). We also installed bridging down the centerline, then
sheathed the floor with 3/4-inch T&G plywood.
Wall Framing
To lay out the walls, we had to take into account the widths
and angles of the polygon sections, the required rough openings
for the windows, and the frieze board running around the
perimeter of the existing house. We began by cutting pairs of
2-foot 11 13/16-inch-long plates for each wall section and
laying them out around the perimeter of the deck. To tie the
wall sections together, we cut the double top plates so they
overlapped the bisected angles where the plates met
(Figure 6). To further strengthen the wall, we
ripped angled 2-by fillers to fit into the triangular-shaped
voids between the outside edges of adjoining studs.



Figure 6. With rough-opening sizes that left no room
for trimmers, each window wall section was a simple frame
consisting of 2x6 bottom and top plates and 8-foot studs (top
left). A 2-by ripping fills in the triangular gap between
adjacent studs at each corner (top right). An overlapping
double top plate helps hold the wall sections together, while
roof loads are supported by a box header installed on top of
the plates (bottom).
There was enough room in each wall section to accommodate a
window rough opening, but not enough for a pair of trimmers to
support a header. Instead, we carried the roof loads with a
continuous box header installed above the double top plate
— a pair of 2x8s nailed together with lumber spacers,
with a 2x6 plate across the top. The home’s existing
windows tuck in under a frieze board, a detail we matched on
the addition. This put the top of the rough openings at about 8
feet.
Completing the polygon. On the exterior, the 16-sided
polygon is interrupted where the outside walls return to the
house. But on the interior, the polygon shape is continuous at
ceiling level, so we needed to extend the wall plates and box
header so they wrapped completely around the room. To do this,
we completed the full 16-sided polygon layout on the deck and
transferred this layout up to the top plate (Figure
7). Then we continued the plate construction around
the room, butting it into the new LVL beam we had installed
above the opening into the addition.
Figure 7. The interior walls at ceiling level
continue the 16-sided form of the polygon, so the wall plates
and box header needed to be extended to meet up with the
existing wall.
Roof Framing
We planned the roof framing so that half of the rafters
— the hips — bear at the top on a
“boss,” or finial. This avoided the headache of
having 32 roof rafters all meet at a single point. The other 16
rafters bear on a ring of blocking installed between these
rafters about 24 inches from the peak of the roof. The boss is
a stack of seven 16-sided polygon blocks cut from 2x8 stock and
glued and nailed together. We used a temporary post at the
center of the room to support the boss at the proper elevation
while we installed the rafters (Figure
8).
Figure 8. The 16 2x8 hip rafters were cut
and installed first and bear on a 16-sided boss cut from 2x8
stock (top left). Blocking installed between the hip rafters
(top right) supports the other 16 common rafters, which bisect
each wall section. The rafter tails, fascia, and window trim
all had to match the existing frieze detail (bottom).
Danny installed the hips first, then blocked between them to
catch the tops of the commons. We dropped this ring of blocking
far enough from the peak so that we could reach in easily with
a framing nailer. Normally you might drop a hip to match the
roof plane of the common rafters; in this case we had to tweak
the seat cut of the commons slightly to bring their tops in
plane with the unbeveled hip rafters. We sheathed the roof with
5/8-inch plywood, then added a simple cricket where the new
roof meets the existing wall.
Typically, continuous ceiling joists or rafter ties prevent
roof loads from causing the walls to spread, but the plans for
this room featured a prefabricated 6-foot- diameter by
14-inch-deep fiberglass dome
(imperialproductions.com,
800/399-7585) right in the center of the ceiling, which
complicated the ceiling framing. We first installed a pair of
doubled 2x8 headers 6 feet on-center, spanning the room
parallel to the existing house (Figure 9).
Fastened to the box beam with toenails and metal angle
connectors, these joists help tie the opposing walls together
and provide the framework for the ceiling grid.
Figure 9. A beefy 2x8 grid ceiling reinforced with
metal connectors helps tie the walls together while
accommodating an opening for a prefabricated dome in the
ceiling center. Before the dome was installed, an insulation
contractor sprayed the unvented attic space with closed-cell
foam insulation.
To square up the opening for the dome, we hung another pair of
doubled 2x8 joists 6 feet on-center between the first pair,
then hung the other ceiling joists off these girders on 16-inch
centers, using metal hangers and connectors wherever possible
to reinforce the grid. Finally, we installed angled 2x6
blocking at the corners of the opening to turn the square into
an octagon.
Still concerned about lateral thrust, we also installed two
pairs of collar ties perpendicular to each other and high
enough above the box header to provide clearance for the
14-inch-deep dome. Securely nailed to opposing pairs of hip
rafters, these 2x8 collar ties support a vertical post under
the boss, creating a sort of king post under the peak.
After we framed up the grid, the insulation contractor filled
the rafter bays with closed-cell polyurethane spray foam, both
insulating and air-sealing the unvented roof.
Figure 10. Each of the subtrades working on
the project — from the roofer installing the soldered
copper finial (top left) to the flooring contractor installing
the inlaid linoleum floor (top right) — had to take into
account the angles and proportions of the addition’s
16-sided layout (bottom photos).
Cost
It’s hard to estimate how much more this polygon cost to
build per square foot than a similarly sized rectangular
addition. There’s no question that the room’s
angles slowed us down and added to labor costs. But the shape
of the room also dictated a number of finishes that probably
wouldn’t have been used in a more conventional structure,
including a copper finial on the roof (a compromise from the
copper roof originally spec’d), granite sills, and an
inlaid linoleum floor (Figure 10). In the end,
we didn’t lose our shirts, and we learned a little math
along the way.
Rob Corbo is a building contractor in Elizabeth,
N.J.