In the fall of 2008, our design-build company took on the job
of converting an 1810 barn to living space. The barn was being
used for storage and was in rough shape; in fact, other
contractors looking at the job advised tearing it down and
starting over. But since the building stands in a prominent
location in a historic district, the owners feared a public
protest and thus a long, contentious approval process for
demolition. So instead, we proposed going forward with the job
as a repair under an engineer’s supervision — an
approach that got us the permit.
By the time we completed the structural revisions, we’d
replaced approximately 70 percent of the building, preserving
the original roof framing and some of the walls. But because we
never actually leveled the barn, the process was relatively
quick and we created a lot of good will in the community.
Existing Conditions
On its north side, the 32-foot-by-36-foot barn shares a common
wall with the main residence. The roof is a mansard-style
double hip with a 12-pitch lower slope and a 6-pitch upper
slope. A 6x6 purlin supports the break between slopes.
Modifications were made over the years with little apparent
regard for the laws of gravity. The rafter plate had been cut
to accommodate dormer windows, and collar ties were few and far
between. While the attached residence on one side provided some
resistance to rafter thrust, the south wall was pushed
seriously out of plumb. In places, the dry-laid stone
foundation had settled into the clay soil, bringing the framing
in contact with the ground. This was causing walls to rot and
exacerbating the structure’s wobbly lines.
Clearly the barn had to be jacked up, the foundation replaced,
and the framing replaced or restored.
Other than its sag, the roof framing was in good condition, but
many of the original balloon studs were rotted near the bottom
and would have to be replaced. Because we didn’t
completely trust the wall framing to support the roof while we
lifted the building, we decided to jack the walls and roof
separately. We figured that by taking the weight of the roof
off the walls, we could install a new crawlspace foundation,
then replace the walls a section at a time with new platform
framing. We’d also replace the undersized first- and
second-floor joists with new I-joists and AdvanTech
subfloors.
Shoring
In the course of our remodeling work, we do a fair amount of
house lifting, so we own around $20,000 worth of cribbing and
long steel I-beams. Although we shored the roof and walls
independently of each other, we did so off the same six stacks
of cribbing (see Figure 1). We cut through the
first floor and set the cribbing on grade in two parallel rows.
The rule of thumb when you set cribbing is to lay the bottom
course at least 6 inches deeper than any anticipated
excavation. It’s common sense; you never want to risk
undermining the crib. We were excavating for a minimum 3-foot
crawlspace and dug the cribbing in accordingly.
Figure 1. A grid of steel I-beams held up the
barn’s walls and roof while the foundation was removed
and replaced.
The cribbing supported two primary 60-foot-long steel I-beam
“needles” running front to back through the
structure. These beams picked up doubled 2x12 cleats that we
lag-screwed to the front and back walls, and also supported
four 40-foot perpendicular I-beams that in turn picked up 2x12
cleats along the side walls (Figure 2).
Figure 2. The eight I-beams provided multiple lifting
and jacking points. Besides supporting the perpendicular beams,
the two 60-foot-long needles picked up the doubled 2x12 ledgers
lag-screwed to the wall framing at each end of the barn (bottom
left). Four 40-foot crossmembers caught the ledger along the
side walls (bottom right).
To support the roof and provide jacking points, we laid two
20-foot-long I-beams across the needles, directly below the 6x6
purlins that support the break between the lower and upper roof
planes. We then built six site-laminated 6x6 posts, running
them from the 20-foot I-beams up through the second floor to
the purlins. Below the roof, we installed plenty of 2x6
cross-bracing to help the posts act as a unit and prevent
bowing (Figure 3).
Figure 3. Built-up posts ran from a pair of 20-foot
I-beams through the second-floor framing (top) to the roof
purlins (middle). This arrangement allowed the roof framing to
be jacked independently of the walls. Three-ton chain hoists
stretched between the top plates helped pull the walls back
toward plumb as the sagging roof was lifted (bottom).
Jacking
This arrangement allowed us to jack under each I-beam and the
needles to gradually restore the building to a relatively level
condition. We use ordinary, 20-ton short-throw hydraulic bottle
jacks, set on cross blocking inside the cribbing, to make
height adjustments. We never lift more than an inch at a time
before reshimming and resetting the jack. If a hydraulic seal
blows, you don’t want the building suddenly dropping
several inches and pancaking on you.
We set a benchmark in the loft at a location along the 8x8 wall
top plate where we’d determined the barn had not settled
and checked the rest of the plate against it with a laser level
as we jacked the walls. Instead of reversing all of the
settling (more than 8 inches overall) in one abrupt session, we
jacked 1/2 inch at a time, then let the building relax
overnight. We knew we couldn’t reverse all of the
settling and ultimately settled for a variance of about 2
inches overall from the original elevation.
Jacking the roof could not alone pull the bowing 8x8 plates and
leaning walls back in. For this, we cut holes in several
locations above and below opposite plates, wrapped chains
around the plates, and tensioned them with HIT 3-ton lever
hoist come-alongs (purchased through
Arizonatools.com for
about $400 apiece). To help distribute the force and prevent
the chains from biting in, we placed 4-foot lengths of 6x6 on
the outside, under the chain, and armored the corners with
angle iron. These hoists are capable of pulling the building in
on itself if you’re not careful.
As we jacked the roof, we retensioned the chains and the plates
moved inward, bringing the walls closer to plumb. We made
1/2-inch corrections each day, taking about a week in all to
finish. When the plate sighted reasonably straight and the
walls were within a few degrees of plumb overall, we called it
good. (Later, when the new walls were in place, we created
plumb interior surfaces by stretching gauge lines and adding
tapered studs and shims as needed.)
Foundation Replacement
Because of the barn’s historic designation, the exposed
stone foundation at the back had to remain intact, even though
it was structurally useless. However, most of the shallow
foundation along the front and sides had long since vanished
into the site’s clay soil, so here we were allowed to
pour new grade-beam footings and crawlspace foundation walls
(Figure 4). Since the barn was built on a
mostly unexcavated slope and we needed to create a 3-feet-deep
crawlspace, we first gutted the first-floor framing, then
excavated from the interior, working around the cribbing with
our mini-excavator and skid steer loader. Where the machines
couldn’t go, we shoveled by hand.



Figure 4. A mini-excavator helped clear the
way for the new crawlspace foundation (top). Reinforced stepped
footings and stem walls replaced the original foundation a
section at a time (middle). Temporarily supporting the original
balloon-framed walls on the new foundation ensured stability
until the wall framing could be replaced (bottom).
To preserve the rustic foundation at the rear of the barn, we
poured a 12-inch-thick steel-reinforced footing directly inside
the stonework and framed a pressure-treated pony wall on top
(Figure 5). After cutting away the old studs
for clearance, we extended new floor joists past the pony wall
over the top of the stone, for a total overhang of around 18
inches.
Figure 5. According to the permit, the historic stone
foundation at the rear of the barn had to be preserved. Rather
than rebuild it, the crew opted to cantilever the new floor
framing (top left) over a pressure-treated pony wall set on a
reinforced footing poured just inside the stonework (top
right). A string line provided orientation for the joist ends,
set back 3 inches for a double rim joist (middle). With mortar
closing the gap, the addition appears to bear on its original
foundation (bottom).
Working Around Cribbing
Since the cribbing was critical to the building’s support
throughout the repair phase, we had to frame the floors around
each stack. We did this by framing and sheathing the deck to
either side, then shoring with cribbing beneath the new joists
and shimming it snug. Then we continued cribbing up to the
underside of the I-beam and shifted the load over onto the
relocated stack (Figure 6).
Figure 6. The new first-floor framing had to be
installed around the cribbing (top). To fill in the gaps, the
crew repositioned the cribbing above and below a completed
floor section, then transferred the beam loads to the new stack
(middle). With the first floor and wall framing replaced, only
the roof supports remained to shore the structure while the
second-floor joists were installed (bottom).
Once we completed the first-floor deck, we installed temporary
supports under the joists overhead and replaced most of the
two-story balloon studs with new platform framing. Because the
roof framing was still supported independently, this was a
relatively straightforward swap-out. After the first-story
walls were in place, we framed the second-floor I-joist floor
system, working around the six posts propping up the
roof.
Steel Roof Truss
To support and unify the roof framing, our engineer designed a
rugged tube-steel truss that bears on four 4-inch-square steel
columns extending up from the concrete foundation. The truss
was custom-cut on site and fitted in place under the irregular
roof framing (Figure 7). We made plywood
patterns to enable the welder to cut the steel accurately. The
steel fits snug under the 6x6 collar beams, shouldering the
entire load of the roof system and eliminating any need for
collar ties. Diagonal bracing within the truss provides the
roof with the necessary resistance to wind loads, a real
concern in this 110-mph coastal wind zone.
Figure 7. After being jacked to its original
elevation, the original roof framing was supported by an
engineered tubular steel truss (top and middle left), which was
cut on site and assembled in place (middle right), then welded
together (bottom left). The truss (painted white) eliminated
the need for collar ties and provided a flat ceiling plane
(bottom right).
We set the bottom chords of the truss dead-level to a laser
line, creating a nice flat ceiling plane. Short lengths of
threaded rod tack-welded to the bottom chords hold 2x10 cleats,
which we used for face-hanging the 2x10 ceiling joists. A
scuttle through the ceiling provides access to the new
attic.
Looking at the plumb walls and flat ceilings in the new
interior, you’d never know what rough shape this building
had been in. And with new roofing, trim, and siding outside,
the barn is good for another 100 years.
Fred Ambrose owns Ambrose Homes in Wellfleet, Mass. Ezra
Ambrose, his son, manages the job site.