Maine was one of the last states in the nation to adopt a
statewide energy code for homes, and there are plenty of Mainers
who still don’t like the idea. But Maine also has its share
of energy-efficient builders, including some who are leading the
nation with exemplary cold-climate high-performance homes. Case in
point: Dan Kolbert and Portland-based Kolbert Building.
new house with a double-wall frame and dense-packed cellulose
insulation, hit ultra-low air leakage numbers and earned a LEED
Platinum rating (see “
Building a Tight House
,” by Dan Kolbert, JLC 6/09).
Kolbert’s current project, however, is if anything more
challenging: he’s working on a complete gut/rehab of a
1970’s post and beam house, aiming for zero net energy
consumption. “I don’t know if we’ll get
there,” he says, “but we’ll get close.”
There’s more to any gut-rehab than just energy, of course.
It’s a dirty job — literally. Right off the bat, says
Kolbert, the team realized that the slope the house was built on
included unstable fill: “We had to build a whole concrete
retaining wall there.” And because the original house was
built with reclaimed timbers from an old barn that had never been
thoroughly cleaned, Kolbert hired a local firm to come in and
soda-blast the grime off the old timbers in place.
But the energy package is the core mission: “That’s
the whole point of the project,” says Kolbert. “And
that’s pretty much what we do. We’re a small company
— we do maybe one big job a year, and frankly, if it’s
not shooting for pretty ambitious energy goals, we’re not
particularly interested. We have a limited amount of time, and we
don’t want to spend it on jobs where people don’t agree
with those goals.” Sticking to that niche has worked for
Kolbert, he says: “So far, we’ve been very lucky.
We’ve stayed as busy as ever during this down time. Part of
that is just that we’re really tiny, which helps. But part of
it is that we do have a reputation for knowing this kind of work,
and we’ve been doing it long enough that it’s pretty
clear that we’re not greenwashing.”
For this 1970s-era timber frame, shooting for net zero started with
the envelope. Kolbert tore out most of the old infill 2x6 stud
framing. He says, “Originally we were going to leave the
exterior walls alone and just skin the place with foam from the
outside. But we found some really serious rodent infestations, and
we saw some structural problems that we needed to address. So in
the end we ended up tearing out all the drywall, all the fiberglass
insulation, and a lot of the infill framing too, which had not been
done very well. And that’s one of the lessons of this kind of
deep energy retrofit — you’ve gotta be prepared for all
sorts of surprises.”
After re-framing, Kolbert skinned the whole building with
ZIP System System coated
plywood and sealant tape. “We wanted to get our air barrier
right there,” he explains. “We needed to re-sheathe it
for structure anyway, so we used ZIP Wall so we could get a good
air seal.” Over the ZIP sheathing, the crew tacked up a layer
of 2-inch polyiso rigid insulation board using cap nails, and then
installed another 2.5-inch layer of high-R nailbase suitable for
shingle siding, fastened through to the studs with 6.5-inch SIP
fasteners (all components supplied by
Hunter Panels). For the infill cavities,
Kolbert hired Manchester, Maine-based energy contractors
“
The Breathable
Home
” to install dense-pack cellulose behind netting.
When Coastal Connection talked with Kolbert last week, the
insulators were on site, installing the final component in the
building’s insulated envelope. “Our blower door numbers
were pretty good back when we installed the ZIP sheath\ng,”
he said. “Now that the foam is on the outside and the
dense-pack is going in, I’m hoping they’ll be even
better.”
Of course, there’s more to a net-zero house than a
high-performance envelope. In later phases, the project plan calls
for photovoltaic rooftop panels, a solar water heater, air-to-air
heat exchangers, and “lots of LED and low-voltage
lighting,” Kolbert says. We’ll update the story for you
when the project is complete and test results are in.