One of the most difficult problems a
contractor can encounter on a project is
responding to the demands of an
unreasonable inspector. Inspectors are
charged with ensuring that the contractor
performs in strict compliance with
the plans and specifications, but this
does not mean the inspector has unlimited
authority to require the contractor
to meet standards not contemplated by
the contract.
If this situation occurs, however, the
contractor can claim that its contract
has been changed and, as a result, that
it is entitled to recover any costs
incurred in attempting to meet the
inspector's demands.
A case that came before the Armed
Services Board of Contract Appeals, J.J.
Barnes Construction Company, Inc.,
ASBCA No. 27876, 85-3 BCA paragraph
18,503 (1985),