I remember tearing out an old tile shower early in my
remodeling career and being surprised to find not greenboard
but a layer of cement under the wall tile. Even more surprising
was the lead pan liner beneath the mortar bed on the floor.
Like most people, I had mistakenly assumed that a grouted tile
surface was waterproof; it had never occurred to me you might
need backup moisture protection.
In the 20 years since, I’ve installed hundreds of
showers, all of them with pan liners — although
I’ve adopted more modern liner materials. When it comes
to the walls, however, I often still do it the old way, with
floated mortar walls. I work a lot in vintage homes, and
there’s no better way to create a flat, plumb tile
substrate over the irregular framing I so often
encounter.
In this article, I’ll explain how I prepare the pan
liner and mortar setting bed for a custom tile shower with
floated walls.
Preparing the Space
According to industry standards, a wood-framed floor under a
ceramic tile shower should deflect no more than L/360. Having
no practical way to assess this in old framing, I use my best
judgment, standing and bouncing on the area to test its
stiffness and reinforcing the floor where needed.
Drain layout. The shower floor looks better and is
more comfortable to stand on if the drain is centered. If it
isn’t centered, the floor will slope more from the walls
closest to the drain. In an extreme case — if, say, the
shower is 5 feet across and the drain is a few inches off one
wall — the variation in slope will make it impossible to
tile the floor with anything larger than the smallest
mosaics.
Rough curb. Unless it’s a wheelchair-accessible
shower, I always install a curb. According to most plumbing
codes, the top of the curb should be at least 2 but no more
than 9 inches above the top of the drain (see Figure
1). On a wood-framed floor, we nail down three or four
2x4s on the flat. If the shower is on a slab, we make the curb
from bricks (Figure 2) or cast it from
concrete.
Figure 1. A floated mortar bed provides a flat, plumb
setting surface over the irregular wall framing often found in
older homes. A typical installation includes a water-resistant
barrier and expanded metal lath fastened directly over the
studs, followed by two coats of mud. When the wall framing is
fairly close to the desired plane, the author first attaches
drywall backing to the studs, then follows with a single mortar
coat application, as shown here. The view at upper right shows
a typical cement backerboard installation. Shower floor details
are the same for both types of wall substrate.
Figure 2. On wood-framed floors, the author makes the
rough curb from 2x4s (left); on a slab, he lays brick, then
skims it with thinset (right).
Blocking. Pan liners need continuous support, so I
install blocking between the studs to a point 10 or 12 inches
up the wall.
When the walls will be covered with cement backerboard, I
notch the base of the studs 1/4 to 3/8 inch or pad out the
upper part of the studs by the same amount, so that the liner
fits into the recess. Otherwise it will bunch up and push the
backerboard out at the bottom of the wall.
When the walls are to be floated, as I’ll describe in
this article, there’s no need to recess the liner.
Instead, if the walls are flat enough to allow for a one-coat
job, I’ll simply nail up ordinary drywall as a backer for
the mud work. When the framing is badly out of whack,
I’ll have to apply two coats of mud anyway (a base coat
and a leveling coat), so I leave the framing open for
now.
Shower Floor
The shower base consists of a sloped substrate; the waterproof
liner, which connects to a three-piece clamping drain; and a
mortar setting bed for the tile. When the shower is in use,
most of the water runs over the tile and down the drain. But
inevitably, some gets through the tile and grout and into the
setting bed; that water is stopped by the liner and channeled
to weep holes in the drain assembly
Liner material. In a few parts of the country, lead
or copper pans are still required by code, and in California
some contractors use hot-mopped asphalt liners. But it’s
more common to use plastic liners, either CPE (chlorinated
polyethylene) or PVC (polyvinyl chloride). I prefer CPE because
it folds and handles more easily than PVC. For regularly shaped
showers like the ones in this article, I use Chloraloy, a CPE
product from Noble (800/878-5788,
noblecompany.com),
and its companion adhesive, Noblesealant 150. For curved or
irregularly shaped showers, I’ll use a liquid-applied
membrane such as Laticrete 9235 (203/393-0010,
laticrete.com) or
RedGard (800/272-8786,
custombuildingproducts.com).
Sloping the liner. By code, the surface under the
liner must slope at least 1/4 inch per foot so that water
hitting the liner will run toward the weep holes in the drain.
This is important: If a pan liner doesn’t have enough
slope, or if the weep holes are blocked, the mortar bed may
never dry out, which leads to surface mold, discolored grout,
and bad odors.
The two most common ways to create slope under the liner are
to frame the floor so it slopes toward the drain and to build
up a slope with drypack mortar. We typically use drypack. Also
known as deck mud, it’s usually mixed with four parts
coarse sand, one part portland cement, and just enough water so
it sticks together when compressed (Figure 3).
If the subfloor is wood, we float it onto galvanized expanded
metal lath that has been stapled over building paper. The lath
reinforces the mortar bed, and the paper prevents the wood from
sucking moisture out of the mud. On concrete subfloors we omit
the lath and bond the mud to the slab by applying it over a
fresh coat of thinset mortar.
Figure 3. Deck mud is mixed dry and crumbly so that
it holds its shape. It can then easily be packed and scraped to
the desired slope.
To prevent mud from clogging the drain and bolt holes, we
cover them with duct tape. We then mix a batch of mortar,
spread some of it around the perimeter of the shower, and use a
trowel or board to compact it into straight level screeds
(Figure 4). We make the screeds high enough to
maintain the minimum drop of 1/4 inch per foot between the most
distant part of the shower floor and the top of the drain
flange.
Figure 4. After skimming the concrete
slab with a bond coat of thinset, the tile setter packs a
mortar screed along one of the walls (top left), then checks to
make sure that it’s straight and level (top right). Next,
he makes screeds all the way around the shower, then fills
toward the center, taking care to create a straight slope
between the screed and the drain (bottom left). When complete,
the mud bed is level at the perimeter and slopes at least 1/4
inch per foot toward the drain (bottom right).
We complete the slope by adding mortar, packing and smoothing
it between the screeds and the drain. When we’re
finished, we cover the mud with a piece of roofing paper so it
retains moisture while it cures overnight.
Sizing the Liner
The key to a good installation is to carefully measure, mark,
and label the liner before doing any cutting. We start by
measuring the floor and curb to within 1/8 inch, then make a
drawing of what the sheet will look like once it is cut. It has
to be large enough to turn up the walls and run over the curb,
so we add 9 inches to the sides that butt walls and 12 to 15
inches at the curb. We place the membrane material on a clean,
flat surface, draw the shape of the floor and upturned sides on
it with a Sharpie, then cut the piece to size. To prepare the
liner for placement, we fold it inward along the lines where
the floor meets the walls and curb (Figure
5).
Figure 5. With the shape of the shower
floor and sides of the pan marked on the Chloraloy, the liner
is cut to size (left) and creased along the lines where the
walls and curb meet the floor (right).
Chloraloy comes in 4-, 5-, and 6-foot rolls. It’s
expensive, so to minimize waste we stock all three sizes. When
the floor is larger than the widest material, we glue pieces
together with Noblesealant 150. The typical sequence is to
clean the material, apply sealant, lap the pieces, apply
pressure with a roller, and then allow the joint to cure. When
the liner is really large, it’s often easier to seam the
pieces in place.
Installing the Liner
To prepare for installation, we remove the duct tape from the
drain, loosely install the bolts, and spread a bead of
Noblesealant around the perimeter of the flange. The sealant
prevents water from seeping out between the drain and the liner
should the drain ever clog.
We install the liner by positioning it so the creased edges
butt to the walls and curb (Figure 6). This is
one time when it helps to have a second set of hands. When
working alone, I spot the studs and blocking with Noblesealant
so the liner hangs in place when I press it up onto the
wall.
Figure 6. The liner is first positioned in the
opening (top), then its sides are folded up one at a time and
secured to the framing (bottom left). In the corners, the
excess material is folded back and snugly fastened (bottom
right). Note how layout lines on the membrane align with the
corners of the opening.
Vertical leg. To turn the liner up, I put one hand
under the folded material at the center of the wall and press
it tightly into the corner between the wall and the floor. I
use my other hand to lift the material against the framing,
then secure it with a nail or screw, keeping the fastener
within an inch of the top edge. I repeat this process all the
way around the shower, working from center to corner and
fastening every 12 inches or so. There will be excess material
at the corners, which I take up by making a triangular fold.
When the liner is properly installed, it should lie flat
against the framing and fit tightly into every corner. If the
material cuts across a corner, it will form an unsupported cove
— a natural stress point that might someday spring a
leak.
Drain attachment. At this point of the installation
process, the liner runs over the drain but doesn’t lie
flat because the bolt heads are holding it up from below. So
that the bolts can pass through the liner, we use a utility
knife to cut small X-shaped slots over the heads of each one,
then squeeze them through the openings (Figure
7). Next, we mark the drain opening by turning the
upper half of the drain upside-down, placing it over the bolt
heads, and tracing its opening onto the membrane with a
Sharpie. We then remove the upper half of the drain, cut out
the drain opening, and reinstall it right side up.
Figure 7. Using a utility knife, the tile setter
slits the liner above the bolts and pops the bolt heads through
(left). He then cuts out the drain opening, removes and
reinstalls the bolts in sealant (middle), and snugs the bolts
over the clamping ring (right).
To prevent water from escaping through the bolt holes, we
remove the bolts one at a time, squirt Noblesealant into the
holes, then reinstall them. We tighten the bolts just enough to
slightly compress the pan liner. This is not like tightening
lug nuts — snug is good enough.
Over the curb. The final step is to run the membrane
across the curb, which we do by slitting the liner vertically
at the ends of the curb and folding the flap out. This leaves
studs exposed at either end of the curb. We cover the exposed
framing with Chloraloy patches, gluing them on with
Noblesealant. There’s still a small hole at the three-way
corner where the liner was slit. We patch this area by gluing
on a preformed corner dam from Noble (Figure
8).
Figure 8. The liner must be slit where it runs over
the curb (top left). Rectangular patches of Chloraloy bedded in
Noblesealant help to waterproof the jambs (top center), but
there is still a tiny hole at the inside corner where the jamb
meets the curb. A preformed outside-corner dam from the
manufacturer seals this spot (top right). Having passed a water
test, the completed liner is ready for installation of the wall
substrate and setting bed (bottom).
It’s critical that every part of the liner lie flat and
tight against the substrate. Bulky folds and loose areas will
prevent cement board from lying flat or create hollow spots
under a mortar-bed substrate.
When the glue on the liner has cured, we plug the drain and
test the pan for leaks by filling it with water and then
leaving it overnight or until the inspector has signed off on
it.
Floated Walls
Once the liner has been leak-tested, we protect it with a
piece of drywall or plywood and get to work on floating the
walls. The mortar is applied over wire lath and a
water-resistant underlayment such as 15-pound felt or Grade D
building paper. Lately, I’ve been using a tile
underlayment called Aquabar B (800/773-4777,
fortifiber.com). The
underlayment serves two purposes: It prevents moisture from
being pulled out of the mud while it is curing and provides
backup moisture protection when the shower is in use.
As I mentioned above, when the framing is badly bowed,
I’ll often have to apply two coats of mortar. In that
case, I nail the membrane and lath directly to the studs. If
the framing is flat and true enough, I can float the wall with
a single coat of mud — around 1/2 inch thick at the
thinnest point, but thicker where the studs bow back or are out
of plumb. For a single-coat job, I’ll install the
underlayment over a solid backing material like drywall. I
bring the drywall down to the top edge of the liner but stop
short of lapping onto it. I then install the water-resistant
underlayment over the drywall, lapping shingle-style at the
seams and extending it all the way down to the liner on the
floor.
Next, I cover the walls with galvanized expanded metal lath,
nailing through to the framing (Figure 9). The
walls are now ready to be floated with mortar.
Figure 9. In preparation for mortar, the wall is
covered with a moisture-resistant membrane, followed by a layer
of expanded metal lath.
Wall mud. To adhere to vertical surfaces, wall mud
must be wetter and stickier than deck mud. I make the wall mud
by mixing four parts sand, one part portland cement, and one
part masonry lime with enough water or liquid latex to give it
the consistency of stiff brick mortar.
Float strips. Creating a flat wall requires the use
of a screed guided by float strips — thin strips of
material that are temporarily embedded in the mortar at both
ends of the wall (Figure 10). Some tile
setters use rips of wood for float strips; I use 1/4-by-1-inch
flat aluminum stock.
Figure 10. An aluminum float strip is pressed into
the mortar along each side of the wall, then straightened and
plumbed with a level (top left). After the remaining area has
been built out with mortar (top right), the wall is screeded
flat by pulling and sawing an aluminum angle along the face of
the float strips (bottom left). The float strips are removed,
the recesses are filled in, and the surface is smoothed with a
float or trowel (bottom right).
To install a float strip, I spread some mortar up the edge of
the wall and press the float strip into it, tamping it in with
a level to make sure it’s straight and plumb. After
installing strips at both edges of the wall, I fill the area in
between with mortar, then scrape off the excess by screeding
and sawing across the face of the float strips with an aluminum
angle. Next, I remove the float strips and use mud to fill in
the recesses they leave. The final step is to smooth the
surface of the wall with a float or trowel. If the float strips
were installed correctly, the floated surface will be nearly
perfectly flat and plumb.
Wall tile. The wall tile can be set as soon as the
mortar is hard. I set it so that the bottom course is just high
enough for the shower floor to tuck underneath.
Shower-Floor Setting Bed
Once the walls are tiled, it’s time to install the
setting bed for the floor tile. The liner is already sloped, so
the setting bed can be the same thickness throughout. According
to the Tile Council of North America, it should be between 1
and 1 3/4 inches thick. I prefer not to go any thinner than 1
1/4 inches.
Drain stem. We thread the drain stem into the
clamping drain, stopping when the drop from the wall to the
drain strainer gives us the desired slope of 1/4 to 1/2 inch
per foot. To keep mortar from clogging the weep holes, I cover
them with tile spacers, pea gravel, pieces of broken tile, or a
Positive Weep Protector from Noble (Figure
11).
Figure 11. Tile spacers (left) or a plastic protector
from Noble (right) prevent mortar from clogging the
drain’s weep holes.
Starting at the rear wall, we build and compact a mortar
screed to about the width of the trowel. The screed should be
level, straight, and just far enough below the wall tile to
accommodate thinset, floor tile, and a caulk joint. We repeat
this process at the side walls and curb, checking with a level
to make sure the slope to the drain is correct (Figure
12).
Figure 12. The setting bed is installed in much the
same way as the mortar under the liner: Screeds are built up
around the perimeter (top) and material is packed in toward the
drain (middle). The top surface of the completed setting bed
(bottom) should be slightly more than one tile thickness lower
than the wall tile and drain.
When the mortar screeds are flat, compacted, and level, we
begin filling in with deck mud, starting at the back of the
shower and working toward the entry. We use a steel trowel and
wood float to move and compact mud all around the drain. As
with any other mud work, we use just enough mortar to slightly
overfill the area; it’s a waste of labor to move a lot of
extra mud around.
Once the back half of the shower is filled, we use
straightedges of varying lengths to shave down the high spots,
removing material a bit at a time until a straightedge can be
laid on the slope in full contact with the mud and just
touching the screed. It’s important to avoid digging into
the screed and to keep the mud just far enough below the top of
the drain so the tile will flush out with the strainer.
We’re especially careful if the floor is large, because
once we’ve mudded the front we won’t be able to
reach the back to make repairs. When the back half is done we
repeat this process at the front.
Wire reinforcing. Tile industry guidelines call for a
layer of 2-by-2-inch galvanized wire mesh reinforcing to be
placed in the approximate center of the setting bed. Mesh is a
hassle to install because it won’t lay flat and must be
held down while mortar is packed over it. We always use wire
mesh in large showers over wood framing, but we omit it if the
shower is over a slab or is small and over sufficiently stiff
framing.
After finishing the mud bed, we mist it with water, cover it
with building paper, and allow it to cure for a day or two
before setting tile on the shower floor.
Robert Zschoche owns Robert Zschoche Remodeling in
Chantilly, Va.