My First ICF Foundation - Continued
With the first ICF course in place, we made preparations to
pour the slab. I covered the crushed stone and the exposed
interior portion of the footing with 1-inch-thick extruded
polystyrene, topped with a 6-mil poly vapor barrier. We then
poured a 4-inch slab with fibermesh in the mix (Figure
4).
|
Figure
4. The first course of block acts as a form for
the basement slab. The finished slab provided a level
work surface, since the foundation is built from the
inside. |
Carpenters, Not Form
Setters
Engineering tables provided by the manufacturer specced
5/8-inch (#5) vertical rebar every 16 inches, to provide the
necessary lateral resistance. I chucked a 5/8-inch
carbide-tipped bit into a rotary hammer, drilled a 2-inch-deep
hole in the footing in the center of each core of block, and
then enlarged the hole with an 11/16-inch drill bit chucked
into a 1/2-inch drill. This gave us some wiggle room to set the
rebar.
The manufacturer strongly suggested that I use carpenters
rather than concrete workers to stack the blocks, because the
skills required to place the blocks are more compatible with a
carpenter's background than a concrete worker's. After working
with the blocks, I agree with him. (While writing this article,
I heard several stories about ICF walls built by concrete
workers — walls so out-of-plumb that they had to be
shimmed out before interior wall finishes could be
applied.)
Therm-O-Wall blocks make tongue-and-groove connections with
each other, so I squirted a 1/2-inch bead of aerosol urethane
into each groove before pressing the next block into place
(Figure 5).
| Figure
5. Aerosol urethane foam cements the
tongue-and-groove connections between blocks. Note the
plastic webs, which hold the sides of the blocks
together and provide support for horizontal
rebar. |
When a block had to be cut to length, we formed a tongue or
groove as needed to join with the abutting block. Sometimes
these fits were sloppy, so we shot in extra foam. Where we
thought we might have a weak joint, we reinforced the area by
screwing 1x4 strapping into the plastic tees.
Number 5 horizontal rebar was cradled in the first course of
16-inch-high block (Figure 6) and clipped into place with
Snap-Lok rebar fasteners, 4 feet on-center. We inserted the
horizontal rebar every four courses, as well as in the top
course, overlapping the ends 24 inches.
| Figure
6. A preshaped wire wraps under the plastic web
and over the rebar to keep the steel in
place. |
For window openings, we scabbed together pressure-treated
2-by material equal in width to the ICFs. The manufacturer
insisted on 1/4x2x2 angle iron at each horizontal corner
— four lengths per opening — to give the window
bucks additional strength. But with small windows, this was
overkill. Since we were essentially casting a lintel in place,
I'm confident that two pieces of rebar spaced apart and placed
above the buck would have been sufficient.
We set four courses and then erected 2x6 commercial-weight
steel studs as wall braces, approximately 7 feet on-center. The
studs were also screwed to the plastic tees. Next we hung
Lite-Form scaffold brackets from the steel studs; this way, the
wall braces doubled as staging for laying more courses as well
as for pouring the concrete. At the top of each steel stud, we
fastened a diagonal 2x4 kicker attached to a turnbuckle brace.
Turnbuckle braces are available from masonry distributors and
some ICF manufacturers. Each turnbuckle brace has a steel plate
at the bottom, designed to be fastened to the slab with
concrete screws. The turnbuckle attached to the kicker provides
the necessary adjustment to plumb the walls and keep them
aligned.