Recently, our company was hired to remodel a 1950s beach
cottage just south of San Francisco. The job included repairing
the house's seriously damaged foundation (see Figure 1).
Figure 1.Creosote-treated wood piles supported the
cottage 5 feet above the beach, so storm surge could flow under
it. The decks were carried by shallow concrete piers (top).
About half of the piles showed signs of rot (middle), as did
most of the beams that carried the floor system and decks
(bottom).
Our original plan was to shore up the building, replace the
support beams, and reuse the existing wood piles. But once we
got the house supported by cribbing and temporary steel beams
(Figure 2) and started excavating around the piles, we found
that they extended only 4 or 5 feet below grade rather than the
15 to 20 feet we'd been expecting.
Figure 2.The crew members did not want to
undermine the shoring when they dug down to repair damaged
piles, so they excavated the areas where the cribbing would go,
then built "forms" around the cribs to protect them from being
buried if waves came under the house (bottom).
Since the existing foundation could not be saved, we had to
design, gain approval for, and build a new one from scratch.
And, with the house up on cribbing, we had to hurry. The house
mover's liability insurance would not cover us if the shoring
remained in place for more than 90 days, a real concern with
the winter storm season approaching. If a big wave hit before
the foundation was done, the cottage could be destroyed.
Although we had already planned to drill new piers for the
decks, these weren't an option for the house unless we moved it
out of the way or drilled from below with a handheld rig. But
moving the house would be too expensive, and drilling with a
handheld rig would be difficult with so little headroom above
and so many stone cobbles in the sand and gravel soil
below.
Instead, we decided to remove the piles and support the cottage
with concrete columns extending up from a modified version of a
mat foundation, which was designed for us by Joshua B. Kardon,
a structural engineer in Berkeley, Calif. A mat foundation is a
thick and heavily reinforced concrete "slab" stiff enough to
span weak areas of soil. The mat is usually continuous, but
this one would be grid-shaped, because we planned to leave the
house where it was and form around the temporary cribbing. We
would place the foundation in a monolithic pour, so that the
cured grid and columns would act as a unified whole.
Replace the Beams First
The design called for new Port Orford cedar glulam support
beams, which we decided to install before forming the mat and
columns. That way, there would be fewer things in the way. We
could hang the beams from the joists, install the column caps,
and then form and pour up to the caps (Figure 3). Since the
house was so close to the ocean, we opted to use only stainless
steel fasteners and hardware for extra resistance to
corrosion.
Figure 3.It was easier to install the beams before
bringing the supports up from below. Here, the beam is hung
from the joists before installation of the support
columns.
Forming the Grid And Columns
On the plans, the foundation looked like a perforated mat
— a grid of intersecting wide grade beams, four going one
way and four others crossing at 90 degrees. Each grade beam
measured 4 feet wide and 18 inches thick. Of the 20 columns
extending out of the grid, 16 would support the cottage and
four would support the deck (see "Mat Foundation
Details").
Steel reinforcing. The grid was
heavily reinforced, with each grade beam containing 10 #6 bars,
five on top and five on the bottom (Figure 4). The crew
connected them with #3 ties every 14 inches on-center and
spaced them off the ground with small precast blocks called
dobies.
Figure 4.The concrete sub used a skid steer to
excavate a flat surface for the grid to sit on (top). Next, his
crew formed the perimeter (middle), then laid and tied all the
steel before forming the inner parts of the grid
(bottom).
The columns projecting up from the footings contained cages of
four #7 bars with #3 ties 6 inches on-center. We had the cages
tied off site and sent out to be hot-dip galvanized. Before
tying the cages into the grid, the crew slipped
16-inch-diameter Sonotubes over them (Figure 5). Fourteen-inch
columns would have been strong enough, but with all that salt
water around, we upsized them to get an extra inch of coverage
over the steel.
Figure 5.Once the steel was tied, crew members
finished the formwork by boxing out the grid openings with 2-by
lumber, then installed the rebar cages for the columns. They
wrapped the Sonotubes with plastic to protect them from
exposure to heavy rain.
Special concrete for a saltwater
environment. Standard concrete is porous and
prone to cracking, because as the material hydrates, bleed
water forms internally around the aggregate. Once the concrete
dries, there are open pores where the water used to be. On
larger pours, the heat of hydration can cause thermal shrinkage
cracking all by itself. We were concerned that salt spray
— which attacks and corrodes even galvanized steel
ferociously — would make its way to the rebar through the
cracks and pores that would inevitably exist if we poured the
foundation with standard concrete. We wanted the concrete on
this job to be impermeable and to contain no cracks at
all.
With advice from the manager of our local concrete plant, we
came up with a mix containing water, cement, fly ash, 1/2-inch
and 1-inch aggregate, two types of sand, fiber, and three
additives. Along with the varied size of the sand, the large
and varied size of the aggregate would limit shrinkage —
but it also would make the material difficult to pump. Still,
because access was poor and we wanted to do a monolithic pour
with close to 80 yards of concrete, we needed to pump.
While a concrete pumper's natural response to these
circumstances might have been to add more water, we wanted to
avoid weakening the concrete, which is why we dealt with the
problem by using additives that made the mix easier to
pump.