A remodeler contacted me to discuss a problem he thought
he’d resolved but clearly hadn’t. Earlier in
the year, soon after beginning a major project, he’d
realized he was working for one of those “customers
from hell.” This person was extremely picky and
expected his project to be built to a higher standard than was
customary in the area. He failed to make selections on time,
demanded that work be performed out of sequence, and called
local building inspectors about perceived code violations.
There were no violations — but having to deal with the
inspectors still cost the remodeler a lot of time and
goodwill.
Neither side was happy with how things were going, so after a
heart-to-heart talk the remodeler and the customer agreed to
part ways. The remodeler pulled his crew and two weeks later
sent a final bill for work performed and materials ordered or
installed.
In the meantime, the customer had hired an attorney. Instead
of sending the final check, he demanded money from the
remodeler. He and his attorney asserted that there was never an
agreement to terminate and that the remodeler had abandoned the
project. They demanded that the remodeler pay for another
contractor to correct allegedly defective work and complete the
project.
Termination
There are a number of ways to terminate construction
contracts. Spec builders have it easy — their
contracts typically allow them to terminate problem customers
at their own discretion by notifying the customer and refunding
what has been paid. They can then sell the house to another
buyer. This isn’t an option for remodelers.
A remodeler has two choices: use the termination clause in the
contract or negotiate a settlement. Standard termination
clauses don’t kick in until one of the parties
defaults and there’s been a “material breach
of contract” (see Legal, 3/05). Unfortunately
for the remodeler who contacted me, the customer had not
defaulted, so the termination clause did not apply —
even though the customer was costing him money and driving him
crazy.
That left the remodeler with the second option —
negotiating a settlement, which is what he had tried to do
before calling me. But he failed to plan the meeting very well
and he did not properly document the agreement.
Paper Trail
When the relationship between a contractor and a customer
sours, both sides are likely to be angry and upset. Do what you
can to reduce these emotions. It helps to make a sincere
statement of sympathy and condolence — which can be
done without admitting fault or weakening your negotiating
position. Once the anger and emotion are out of the way, you
can deal with the situation as the business problem it
is.
Ideally, you should go into this meeting with a written
termination agreement that you prepared in advance. The
document should state that the contractor is ceasing work by
mutual agreement of the parties. It should list — or
have space to list — the points the parties agree on.
It should also state that if the parties can’t agree
on final terms, you will restart the job or otherwise comply
with the contract — with appropriate extensions to the
schedule — after a set period of time or after
providing written notice.
If you don’t go in with a prepared agreement, then at
least follow up immediately with an e-mail confirming that
there has been a mutual understanding to stop work on the
project and that if the customer disagrees he should contact
you. Don’t forget to ask a question you know the
customer will respond to; the return e-mail response will prove
that your message was received. (If this strategy
doesn’t work, follow up yet again — this time
with a call).
The important point is that you must document the fact that
there was a mutual agreement for you to cease work on the
project. Otherwise you leave yourself open to charges that you
abandoned the job. Abandonment triggers a default and allows
the customer to hold the contractor responsible for the
damages, including costs of completion in excess of the
remaining contract balance.
Payment
Make sure you know when you arrive at the meeting how much
money the customer owes you, and be prepared to reach an
agreement on a final payment amount. Also, be sure
you’ve addressed the issues of termination with your
subs and that you’ve included in your calculations
what it will cost to terminate their contracts. If at all
possible, get the customer to write the check then and there.
You don’t want to give him or her time to feel
“buyer’s remorse” and back out of
the deal.
If you cannot come up with an exact dollar amount —
maybe the subs haven’t completed their bills
— get the customer to agree on what work has been
completed and which bills, once received, will be paid.
Don’t forget to include an appropriate markup. The
markup should have been specified in your contract; if not,
that’s something else you need to negotiate. For
example, the agreement could read: “The parties
agree that the cabinetry has been delivered and installed to
the satisfaction of the consumer. When the contractor receives
the subcontractor’s invoice for the cabinets (list of
cabinets attached), he will forward it to the consumer, who
agrees to pay the invoice amount plus a 35 percent markup
within 10 days of receipt.”
Outcome
As it turned out, the remodeler who came to me with this
problem had a well-written contract and the customer’s
demands were well beyond any reasonable expectation of what was
required by law. Also, because of how the payment schedule was
devised, the remodeler was relatively current on
payments.
Therefore, he was able to negotiate a clean walkaway and
needed a only a small final check to come out near the
break-even point. After an exchange of letters with the
customer’s lawyer, we were able to achieve an
effective cease-fire. No one admitted fault, and the remodeler
did not get the entire amount he felt entitled to —
plus he had to pay some legal fees — but he did get
away from the client without being sued.
Kevin M. Veler is an Atlanta attorney
with more than 20 years of experience representing construction
companies.