Your construction company does excellent work, you try hard to
please customers, and when there's a problem, you always find a
way to work things out. But this time it's different: You find
yourself in a dispute over a remodeling project. You followed
the advice of your attorney and put a clause in your contract
that requires arbitration in the event of a dispute. What
happens now?
Arbitration is a way to settle disputes without filing a civil
lawsuit. It's less expensive than going to court because it
takes less time. Lawsuits can drag on for years; most
arbitrations are completed in nine months or less. In a
lawsuit, a judge or jury decides the case. In arbitration, a
professional arbitrator listens to evidence and arguments
before issuing an "award" in favor of the winning party. In a
lawsuit, either party can appeal the decision, but the decision
of the arbitrator is final and there is normally no
appeal.
Arbitration is not required by law; it's something the parties
agree to, usually in advance and as part of the contract
between them. The parties decide for themselves what kind of
arbitration they want and what kind of arbitrator should hear
the dispute. For example, the parties could agree to place time
limits on the length of the arbitration, to limit the size of
the award, or to have a person with substantial construction
experience act as the arbitrator.
Arbitration Service Providers
Arbitrations are usually conducted by private
dispute-resolution services. Some of these companies have
offices all over the country, while others operate locally. Two
of the better known national services are the American
Arbitration Association (AAA; 800/778-7879;
www.adr.org)
and the Judicial Arbitration and Mediation Service (JAMS;
949/224-1810; www.jamsadr.com). I'm associated with AAA
and a California group, Action Dispute Resolution Services
(ADR; 310/201-0010; www.adrservices.org). These and similar
organizations have established arbitration procedures and can
provide experienced arbitrators and administrators to handle
cases from start to finish.
Arbitration service providers charge a fee to administer the
case, and most arbitrators charge an hourly fee to hear and
decide it. Fees vary but are usually based on the amount of the
claim. For example, if the claim is between $10,000 and
$75,000, the AAA charges an initial filing fee of $750 and a
case service fee of $300 for cases that proceed to the first
hearing. The hourly rate for an experienced arbitrator is
usually about $350 per hour. Arbitration is not cheap, but it's
almost always less expensive than going to court.
One reason arbitration is less expensive than litigation is
that arbitrations do not include formal "discovery." Discovery
is a process where the parties take depositions, send written
questions called interrogatories, and exchange demands to
produce documents before trial. While discovery helps each
party learn about the claims and defenses in the case, it's
also very expensive. In arbitration, no discovery is permitted
unless the parties agree otherwise, either in their contract or
during the time before the hearing starts.
Contract provisions. Each
party can agree to pay half, or you can include a clause in
your contract that allows the arbitrator to award the
"prevailing party" all or part of the fees. There is some risk
in doing this because if the homeowner wins even a small award,
you might have to pay the legal expenses for both sides. Most
construction disputes involve the use of expert witnesses, so
the contract could also require the loser to pay the expert
witness fees.
Initiating an arbitration.
The arbitration starts with a "demand for arbitration" from the
person who is filing the claim. This involves filing certain
paperwork with the arbitration service that the parties agreed
to use. The person who files the claim is the "Claimant," and
the person it's filed against is the "Respondent." Let's say
the claim was filed by the homeowner. If the contractor thinks
the homeowner actually owes him, he can file a counterclaim
that will be heard in the same arbitration as the original
claim by the homeowner.
The arbitration service will provide a list of proposed
arbitrators, and each party is allowed to disapprove a certain
number of them until an arbitrator is selected by mutual
agreement. If the parties can't agree, the arbitration service
picks the arbitrator.
The Arbitration Hearing
An arbitration hearing is similar to a trial, but more
informal. The parties are usually represented by lawyers. The
arbitration takes place at the arbitration service provider,
the office of one of the lawyers, or at a place agreed to by
the parties. (Sometimes it takes place at the construction
site.) There may be a room fee.
Before the hearing, the parties are required to exchange
documents ("exhibits") that support their claims, disclose the
names of their witnesses, and submit legal briefs to the
arbitrator that explain their positions. The hearing itself
resembles a court case in that evidence is presented, witnesses
testify under oath, and the parties or their lawyers make
statements. Unlike a court case, the parties are allowed to
cross-examine witnesses, and the arbitrator can ask questions
too. The hearing could last for part of a day or stretch out
over several weeks with sessions every few days.
The arbitrator listens to the testimony, reads the exhibits,
and listens to arguments from both sides. When all the evidence
has been presented, the arbitrator will close the hearing or
ask the parties to submit additional legal briefs. Once the
hearing is closed, the arbitrator must issue an award within 30
days. The award is in writing and may be as simple as "The
Arbitrator awards the Claimant the sum of X dollars." It may
also contain an explanation of the arbitrator's
reasoning.
Unlike a judge who presides over litigation, the arbitrator
does not have to follow the strict rule of law and is entitled
to render an award that is fair to the parties. If you believe
that fundamental fairness is on your side, you will probably do
better in arbitration than in court. Another difference is that
the rules of evidence do not apply in arbitration unless the
parties agree otherwise. This means that hearsay and other
forms of evidence that could not be heard in court are
perfectly permissible in arbitration, with the arbitrator
deciding what weight to give to the evidence.
In the Matter of the Arbitration between:
Re: Harrison Homeowner (hereinafter named
"Claimant")
VS
Best Remodeling, Inc. (hereinafter named
"Respondent")
AWARD OF
ARBITRATOR
I, THE UNDERSIGNED ARBITRATOR, having been
designated in accordance with the arbitration
agreement entered into by the above-named parties
and dated {May 13, 2003}, and having been duly
sworn, and oral hearings having been waived in
accordance with the Rules, and having fully
reviewed and considered the written documents
submitted to me, do hereby, FIND, as follows:
1. The arbitrator finds that the parties
entered into an agreement under the terms of
which Claimant retained Respondent to perform
certain remodeling services as Claimant's
residence (hereinafter the Remodeling
Work);
2. Claimant contended that Respondent failed
to complete the Remodeling Work on time and
within the stated price, and further that
certain aspects of the work were defective or
otherwise deficient. Claimant terminated the
Respondent's services prior to the completion
of the Remodeling Work;
3. The parties presented evidence, including
testimony of experts with regard to the cost,
timing, and quality of the work;
4. The Arbitrator finds that the although the
work was not completed on time and on budget,
the Respondent should not bear the
responsibility for this fact because: (1)
Claimant made numerous changes to the design
and scope of the project, each of which
increased the time and expense of the project;
(2) Claimant ran short of funds and was not
able to make timely payments to
Respondent;
5. With respect to the claim of construction
defects, the Arbitrator finds that many of the
items claimed as construction defects were in
fact "punch list" type items that would, in the
ordinary course of events, be completed or
repaired had Respondent finished the Remodeling
Work. In this regard, because the Arbitrator
has found that Respondent was not at fault with
respect to the timing of completion or cost
increases, the Arbitrator finds that Claimant
did not have cause to terminate the contract.
Accordingly, the Arbitrator finds that the
Respondent should have been given the
opportunity to have completed or repaired the
various claimed defects.
Accordingly, I, hereby render this AWARD, as
follows:
1. The Claimant shall recover nothing on its
claim; and
2. The Claimant shall pay Respondent's
attorneys fees and costs plus costs of the
arbitration.
3. The administrative fees of the American
Arbitration Association ("the Association")
totaling Four Thousand Dollars and Zero Cents
($4,000.00) shall be borne by the Claimant, and
the compensation of the Arbitrator totaling Two
Thousand Nine Hundred Dollars ($2,900) shall be
borne by Claimant.
____________________________ Dated:
__________________
Robert S. Mann, Esq., Arbitrator
|
Confirming the award.
After the award is issued, either party can ask the court to
"confirm" the award, which has the effect of turning the award
into a court judgment. If the other party objects, he can ask
the court to "vacate," or nullify, the award. This rarely
succeeds, because the only grounds for vacating an award are if
the arbitrator has an undisclosed conflict of interest or if he
fails to admit relevant and material evidence during the
proceedings.
How to Develop a Winning
Strategy
There are a few simple things to remember about arbitration.
Arbitrators are impressed by professionalism and
reasonableness. This means you will do better if you and your
lawyer are organized and well prepared. Arbitrators are more
interested in fairness than in legal technicalities, so it's
better to concentrate on what's fair than to argue and nitpick
about peripheral issues. Arbitrators are always interested in
the truth. If you and your lawyer are truthful and forthright,
if you admit what must be admitted, even if you think that it
is "bad" for your case, and you demonstrate that the other side
has not been honest, you will do better. Arbitrators have an
easier time understanding a case that's presented logically and
sticks to the facts. You're more likely to prevail if you can
be brief, focus on the important issues, and leave out what is
not essential to proving your point.
Robert Mann, Esq., is
principal of the Mann Law Firm and a member of the National
Panel of Construction Neutral Arbitrators and Mediators. He
arbitrates and mediates construction disputes in Los Angeles,
Calif.