Just as it sounds, "breach of contract" means that someone has
not done what he contractually promised to do. But a breach of
contract does not automatically mean that the contract is dead
— that is, unenforceable.
A Material Breach
To kill the contract before the project has been completed,
there must be a "material" breach of contract. In other words,
the breach is so serious that, in effect, there just isn't a
contract anymore. There's nothing to enforce, because the
contract has been so damaged it's beyond fixing — even if
your standards for fixing it aren't very high. At this point,
all you can do is pick up your tools and go home to sort out
who owes what.
The "beyond fixing" part is important: Not every failure to do
what you promised — or for your customer to do what he
promised — is such a big deal that the contract is
irrevocably destroyed. Only a material breach can kill a
contract.
A less than material failure to perform might give the injured
party some other kind of remedy, but it can't kill the
contract. The thrust of contract law is to enforce valid
contracts even if there are some bumpy spots along the
way.
Minor Errors
For example, suppose a contractor does a kitchen remodel that
includes a tile floor. He does a good job installing the tile,
but the grouting is poorly done.
Does this mean the contract is so breached that the contractor
does not have the right to fix the problem and complete the
rest of the job? Or does the contractor have the right to leave
the tile the way it is and continue working on other parts of
the project? Does it mean that the customer can tell the
contractor to get off the job and not come back, and then sue
him for breach of contract for not doing the job
correctly?
While the contractor's failure to perform is a breach of
contract, he still has the right to fix it ("cure" is the legal
term). But even if he doesn't fix it, the customer's only
remedies are to haggle over the final payment or sue for breach
of warranty after the project is finished.
The contract is still in force, because sloppy grouting is
simply not that big a deal. The bad grout job is not a material
breach of contract because the problem can be fixed. Maybe it
can't be fixed in a way that will make the customer want to
call that contractor for his next remodeling project, and it
may not be fixed in a way that will allow the contractor to
collect every nickel of the contract price, but it's fixable
enough to keep the contract alive.
Serious Mistakes
But suppose, through a monumental misreading of the plans, the
contractor neglects to install electric heating elements under
the tile floor. This would be a material breach of
contract.
The contractor still has the right to tear out the tile and
install the missing heat or to work out a settlement with the
customer, but if he doesn't repair the mistake in a reasonable
amount of time or get the customer to agree that the floors are
fine the way they are, the customer could throw the contractor
off the project and get someone else to complete the
work.
If the customer wanted to, he also could sue the contractor for
breach of contract, and would probably win.
The thrust of contract law is to enforce valid
contracts even if there are some bumpy spots along the
way. |
When Clients Breach
It works the other way around, too. Suppose the customer
regularly fails to make progress payments when the contract
stipulates, but does eventually make them. Can the contractor
just get fed up and walk off the job? No, because the customer
did finally make those payments and the contractor did accept
them.
But what if, one of the times that the customer was late, the
contractor was so fed up that he refused to accept the late
payment and walked off the job? Are that customer's habitually
late payments such a material breach of contract that the
contractor can simply quit, contract or no contract?
Probably not, because the customer was ready and willing to
make his payment. He had made all the past due payments, and
the contractor (in this example, anyway) had no reason to
believe that the customer would not continue to make those
payments.
Some states, like Arizona, have passed right-to-payment laws
that greatly simplify the whole issue of who has exactly what
right to do what. In these states, the contractor can suspend
work or even terminate the contract — after giving notice
— when payments are late. But even where such laws exist,
once the late payments — and the expenses caused by them
— have been taken care of by the customer, the contractor
has no further rights to stop work.
Remedies for the GC
Does that mean the contractor has absolutely no remedy if the
customer paid the correct amount, but paid late?
Not at all: If, for example, the contractor has to pay late
charges or fails to get his usual discount from suppliers, he
is entitled to back-charge the customer for those expenses. He
can probably collect for some other kinds of damages, too, but
he may not walk off the job, because the customer has fixed
this breach of contract by paying.
It's worth noting that any suit deriving from a breach of
contract is a "contract suit" rather than a "tort suit" —
meaning the lawsuit is about money, not about a physical injury
or negligence. Punitive damages are not allowed in contract
suits, so the prevailing party is limited to collecting actual
economic damages. This type of case usually hinges on whether
the contract breach was material, which is why I advise clients
not to walk off the job or initiate legal proceedings unless
the breach is unequivocally material and they can prove it in
court.
Once in court, neither the contractor nor the customer gets to
decide if the contract has been breached or the breach is
material. If the dispute goes that far, the decision will be
made by a judge, a jury, or an arbitrator.
has practiced and taught law for more
than 25 years and is the author of The Contractor's
Plain-English Legal Guide
(www.craftsman-books.com).