A Curved Porch on a Grand Scale, continued
Columns 101
The classical formula for Tuscan column proportions states
that the column's height must be equal to seven times its
diameter, including the plinth and capital. So, technically
speaking, a 16-inch-diameter column ought to stand 9 feet 4
inches overall. When designing with and specifying columns,
this is a good rule of thumb to keep in mind to ensure a good
appearance.
The column also features true "entasis," or an aesthetic
tapering over its length. Ours measured 16 inches in diameter
at the bottom and 13 1/2 inches at the top. The tapering occurs
in the upper two-thirds of the column's length, and any
necessary shortening is done at the bottom. These columns were
10 feet long in the rough and had to be cut to finished length
before standing. We cut them about 1/4 inch short to allow for
shimming and leveling.
Cutting. There's some kind
of mineral component in the columns' fiberglass matrix that
gives the material a stone-like appearance. You can effectively
cut one or two columns with a carbide-tipped blade, but the
teeth quickly dull. Instead, we used an abrasive diamond chip
masonry blade in a circular saw, resting the columns in a basic
cradle to hold them at a comfortable cutting height (Figure 4).
One worker did the cutting while another slowly rotated the
column.
Figure 4.A simple plywood cradle held the columns
at a comfortable height for cutting to length. The crew found
that carbide-tipped blades dulled quickly, but that abrasive
diamond blades worked well.
Lifting and setting. A
single column of this size weighs about 200 pounds. We looped a
nylon choker strap around the top of each column in turn and
used a Lull to lower them over the 4x4 posts. After each column
was set, a worker slid the one-piece cast polyurethane plinths
and capitals over the top. We set all 17 posts, including the
4x4s, in about six hours. Although we'd anticipated having to
brace the columns after standing, that proved unnecessary.
Thanks in no small part to careful cutting and pier
preparation, as well as the columns' own mass, they stood
nearly plumb all on their own.
Carrying Beams
The roof's straight carrying beams were a series of composite
box beams, built in sections to bear on three or more columns
each and butting over column centers (Figure 5).
Figure 5.Instead of strap ties, the author used
4x4 posts running through the columns as hold-downs for the box
beam on top. Square holes in the top and bottom flanges of the
box beam allowed the beams to drop over the 4x4s. Square
notches in the ends of the beams fit around the posts, allowing
the sections to be fastened together. After the beam was
fastened to the posts with bolts, the protruding tops (right)
were cut off.
A 3 1/2-inch-square opening cut through the top and bottom
plates of the beam on layout captured each post. A worker on a
ladder guided the 4x4s into their pockets as the crane operator
lowered each beam into place.
For the two circular beams, Mike laminated two 4-inch-thick
ring beams from 16 layers of 1/4-inch lauan plywood, bonded
with West System epoxy. The rafters were set in pockets cut
into the rings' inner face. Below the ring beams, he
constructed an open framework of plywood plates and 2x4 struts
to continue the 28-inch-wide entablature band around the
circular porch sections.
Fastening the Columns
The beam rested directly on the fiberglass columns, which we'd
modified at the tops with four pieces of 2x blocking, screwed
and urethane-glued to the interior circumference (Figure
6).
Figure 6.The composite beams were built around a
glue-laminated plywood web, 2 1/2 inches thick by 28 inches
high. The overall 19-inch width of the beam accommodated the
columns' square capitals. Four pieces of wood blocking, shaped,
glued, and screwed to the top interior of each column, provide
an attachment for wood screws driven down through the beam's
bottom flange.
The blocks allowed us to screw directly down through the
bottom plate of the beam into the tops of the columns, drawing
them up tight to the beam. We used steel shims under the column
on the concrete pier to raise the column and beam to final
height, checking level with a dot laser. Once the entire beam
was leveled, we secured it with three 1/2-inch carriage bolts
passed through the post and flange. To plumb the columns, we'd
left about 1/2 inch of play between the concrete nipple and the
columns' interior diameter. Using a stick level held against a
straightedge equipped with standoff blocks to compensate for
the column's taper, we nudged the bottom around until the
column stood plumb in all directions. Later, we grouted the
shim gaps at the pier with cement mortar, leaving weep holes to
allow any condensation inside the columns to drain.
Finishing Up
We left the cast plinths and capitals loose on the columns,
wedged partway up the columns, out of the way of the framing
and finish work (Figure 7).
Figure 7.A nonstructural frame under the circular
roof (top) aligns with the box beam entablature. The circular
roof loads are carried to the columns by a site-laminated round
top plate. Note how the plinth and capitals are wedged safely
out of the way during construction (bottom).
We framed the porch floor on independent supports, with the
column piers buried below the framing line. The 1x4 tropical
Ipe decking was fitted around the columns, then covered by
lowering the plinth. The beam trim was cut around the tops of
the columns; then the capitals were slid up into place. We
secured the castings to the columns with Excel XPress
polyurethane glue (AmBel, Cottonport, La.; 800/779-3935,
www.excelglue.com) and a couple of
countersunk stainless-steel screws. The countersinks were
capped with epoxy filler and sanded to disappear. The columns
arrived with rough-ground molding seams that required
top-dressing with thickened epoxy (using West's 401 filler
additive), followed by sanding to produce a uniform smooth
surface before painting. The completed assemblies were sprayed
with latex primer, caulked, and finished with high-quality
exterior-grade latex trim paint.
David Baudis president of Baud Builders in
Narragansett, R.I.