I’m an independent framing carpenter and experienced
ironworker. Over the years, that combination of skills has
landed me a number of unconventional and challenging projects.
The contemporary home I’ll discuss in this article
featured large expanses of glass separated by slender columns
supporting a flat roof. Because I work in a 110-mph coastal
wind zone, wall bracing was an especially vital
consideration.
But in a facade composed of more glass than studs and plywood,
there’s little opportunity to incorporate conventional
shear walls or engineered panel systems. Instead, you have to
resort to a steel moment frame. Whether bolted or welded, the
moment connections in a steel frame don’t allow the joint
rotation seen in wood-to-wood connections and can therefore
resist wind and structural loads that would overwhelm common
wood connections.
For this house, the architect and the engineer designed a
moment frame — 11-foot-tall steel columns topped by steel
I-beams — that wrapped the building’s perimeter.
Wood I-joist roof framing hung between the interior faces of
the perimeter beams. It was my job to integrate all this steel
within the 2x6 walls of a conventional wood frame.
Layout
The engineer specified 3 1/2-inch-square tubing columns
supporting 10-inch-tall, wide-flange (W10x19) steel perimeter
beams. To provide nailing for plywood sheathing and finish
trim, I decided to box the columns on three sides with 2-by
lumber, a 2x4 on the exterior face and a 2x6 on either side to
match the general exterior wall framing (see Figure
1). As a result, the steel framing line lay 1 1/2
inches inside the actual building line — which was
helpful because part of the home was built on an existing and
somewhat irregular foundation, and this allowed some fudge room
for squaring up the new layout.
Figure 1. Where glass walls eliminate the possibility
of shear panel construction, welded connections between steel
columns and beams provide the necessary resistance to lateral
wind pressure. To simplify the application of wood finishes,
the moment frame is clad in nonstructural framing lumber
attached with powder-actuated fasteners.
Following the plans, I first transferred the centerline spacing
of the 29 columns to the existing deck, then snapped lines
representing the inside face of the 2x6 perimeter walls, as
well as perpendicular lines for key partitions and roof beams.
I like to use black chalk because it’s highly visible and
remains so for months under tough job-site conditions. I wanted
these lines to be visible later when it was time to true the
perimeter beams to a laser plumb line.
Accommodating elevation changes. The columns
weren’t fastened to the wood framing, but directly to the
concrete. So at each column location, we cut away the floor
framing and mudsill, exposing the foundation (Figure
2). Next, I took accurate elevation readings with a
rotating laser and found a difference of 1 1/2 inches between
high and low points in the floor joists. Because the lot
slopes, the foundation was also 8 inches higher at the back of
the building than in front.
Figure 2. The moment frame begins at the foundation.
MDO templates ensure that the holes in the column baseplates
match the bolt holes in the concrete (top left). The baseplates
rest on setting nuts (top right), which are used to plumb the
column and adjust it to finished elevation. The top nuts
rigidly hold the columns in place. After the complete frame is
assembled, the author packs the voids under the plates with
fast-setting hydraulic cement (bottom).
I picked a value about midway between gross high and low as my
baseline against which to establish the top-of-steel (TOS)
line. The architect specified a finished ceiling height of 10
feet above the finished floor. To determine the top of the roof
framing, I added ceiling plaster and I-joist dimensions, then
deducted the thickness of the 2x6 nailer affixed to the top of
the perimeter beam. This nailer established the top of the
I-joist framing and enabled the deck plywood to finish to the
outer edge of the steel.
Due to the unevenness of the original foundation, I specified
four averaged baseplate elevations and column lengths for the
29 columns. Four 1/2-inch-diameter anchor bolts bonded into the
concrete held the baseplates. To accommodate irregularities in
the surface, it’s standard practice in steel construction
to keep column baseplates about one inch above the concrete.
When the column is first set, it rests on setting nuts threaded
onto the anchor bolts. Turning these nuts one way or the other
adjusts the column both to plumb and to its final height. Once
set, a second set of nuts and washers secures the column to the
anchor bolts, and later the void under the plate is filled with
nonshrink grout.
Shop Fabrication
My brother, Matt, owns Wellfleet Steel Works, which specializes
in fabricating and placing structural components and often
provides the steel for my jobs. When working with steel, we try
to keep to a minimum the variations among parts of each type.
For example, we make a standard baseplate for all corner
columns, and we keep the centerline spacing on bolt holes the
same for every beam connection. It’s common sense:
Repeatable details lead to fewer mistakes.
I make anchor-bolt patterns for the baseplates out of scrap MDO
plywood or PVC trim board. We make sure our patterns —
unlike the CDX patterns Matt often receives — are dead
accurate. I make them in triplicate, using three layers of
material screwed together and milled at once to ensure a
precise match. I drill the bolt-hole centers on a drill press,
using a 1/4-inch bit. One pattern goes to the person making the
columns, and the other two go back to the job site to guide
anchor-bolt installation.
Variations in steel members.
It’s commonly assumed that steel members are uniformly
straight and dimensionally true, with no twisting or bowing,
but this isn’t the case. Though steel is better than
lumber, irregularities exist. You have to sight each piece to
orient it properly in the frame. Severe bowing is impossible to
correct and must be rejected. Flange widths can vary, even on
the same beam. Fortunately, on this job, every piece was
straight.
Bolt or Weld?
The moment connections we make are of two types, bolted and
welded (Figure 3). I prefer welded connections
because they’re stronger and easier to fit — you
can make adjustments with a grinder or a torch right up to the
last minute. The fitting of a welded joint should be precise,
with parts fully touching, though the weld can bridge gaps up
to 1/8 inch.
Figure 3. The drift-punch handle of a rigger’s
wrench aligns beams for bolting (left). Though bolting alone is
sufficient, the author likes to add a couple of tacks to the
joints to eliminate all possibility of movement (center). At
welded perpendicular joints, the beams are coped for a snug fit
(right).
Bolted connections, on the other hand, require precise layout
of holes, usually six to eight per connection — a
time-consuming process. Also, we drill holes only 1/16 inch
larger than the bolt size, so just one misaligned hole can
prevent installation of one or more bolts, or limit fine
adjustments between the parts. Then you have to “egg
out” the errant hole to accommodate the binding
bolt.
Nevertheless, engineers generally prefer bolted connections
because the special-order bolts carry an ASTM rating, giving
them known performance properties. Welders like bolted
connections, too, because bolting cuts down the amount of
welding that has to be done on site — often from a
ladder. And because they go together more quickly, bolted
connections also reduce the crane time.
On this job, half of the right-angle connections between beams
called for bolted angle clips (Figure 4). The
rest were specified as full perimeter welds, meaning a
full-contact, coped fit between the beams and a continuous weld
around the entire joint — a task that can take 20 minutes
or longer.
Figure 4. Bolt-on angle clips can support wood
framing, as in the case of this LVL stairwell header (left). A
welded bolt flange (right) stiffens the beam web beneath a
second-floor column location and also supports a right-angle
beam.
The columns were also welded directly to the beam bottom
flanges; we made simple square cuts at the tops, then beveled
them for welding to the beam flange (Figure
5).
Figure 5. Wood cladding on the underside of the
perimeter beam (left) precluded the use of bolting flanges for
the columns. Instead, they’re direct-welded. Beveled
edges on the tops of the columns (right) expose the full
thickness of the tubing wall for an optimal welded
bead.
Attaching lumber. Working in the
shop, we drilled pairs of 9/16-inch holes on 16-inch centers
through the beam webs for through-bolting 2x10 packing. The
packing provided nailing for joist hangers on the interior and
cladding on the exterior. We fastened most of the packing to
the beams while they were still on horses at the shop —
which is a lot faster and safer than doing it on site from
ladders 20 feet off the ground.
Though you can use powder-actuated fasteners for attaching
plates to the flanges, I prefer to use screws, since the lumber
occasionally needs to be temporarily removed to provide
clearance for welding.
Setting Columns
I use the baseplate patterns to locate the anchor bolts for
columns. I ran a 3/16-inch masonry bit in a cordless hammer
drill through the holes in the pattern to mark the concrete,
then followed with a hammer drill and a 9/16-inch bit to expand
the holes for the 1/2-inch-diameter threaded rod. I used
two-part A7 (800/348-3231,
itwredhead.com), a
fast-curing acrylic adhesive, to set the bolts. To hold the
alignment while setting the rods, I used the third copy of the
pattern with its holes enlarged to 9/16 inch. Once the adhesive
solidified, I leveled the setting nuts to receive the
baseplates.
We stood all of the first-floor columns by hand in about three
days, spending about a half-hour setting each one. We used the
setting nuts to plumb the columns and set them generally level
to a laser dot by measuring down from the column tops.
To attach the headers above the sliding doors to the columns,
we shop-welded flanges at a uniform distance down from the top
(Figure 6). To avoid potential cumulative
dimensional errors, we decided to install these headers only
after setting the top perimeter beams and welding them to the
columns. The headers were made up of double, 11 1/2-inch-wide
LVLs, faced on the exterior side with 2x12s to pack them out to
the building line.
Figure 6. Where an LVL header meets the steel post,
the author welded 3-inch-deep bearing plates to support the
beam. Though the LVL adds no structural strength to the frame,
it matches the column thickness and provides stiff backing for
the finish trim.
Crane Day
It’s important to educate everyone on site about the
hazards of working around a crane. There is always the risk a
beam might slip from its sling, so everyone needs to stay
focused on the load and stay out of the fall zone. At least two
of the crew should be familiar with the hand signals used to
guide crane operators. If the operator’s line of sight is
blocked, one person must be in view of both the operator and
the workers receiving the beam. The deck needs to be clear of
debris and obstacles, with pipe staging and stepladders
arranged and ready.
Before the lifting starts, we use powder-actuated nails to
fasten 2-by cladding to the outside faces of the corner columns
so we can attach temporary braces for steadying and plumbing
the frame as it goes together. On this job the GC, Art Hultin,
provided us with dozens of adjustable concrete form braces.
These can’t be beat for quick fine-tuning during assembly
(Figure 7).
Figure 7. Adjustable form braces provide the
fine-tuning required to compensate for the jostling that occurs
when heavy perimeter beams are set (left). The author clamps
2x6 cladding to a column and secures it with powder-actuated
pins (right).
Setting beams. Beginning at a corner,
we set the first perimeter beam and tack-weld it to the column
(Figure 8). A tack weld is about 1/2 to 1 inch
long. That’s long enough to hold, but not so long as to
require extensive grinding to remove in case of error. The
square cut on top of the column is no guarantee that the beam
sits plumb, but if a web isn’t plumb, we’ll have
trouble lining up holes between the connecting members. So
while the welder tacks the column, a helper pulls the beam
plumb using a bar clamp or a wrench as a lever (Figure
9). Since the action of welding tends to forcefully
pull pieces toward the weld, the first tack goes on the side of
the beam that needs to move down.
Figure 8. Working with a 68-foot boom, the crew set
the first-floor perimeter beams in one long day. Installing the
wood cladding while the steel was still at the shop saved
plenty of on-site labor.
Figure 9. Because steel parts tend to pull toward the
bead during welding, a worker uses an extension handle on the
rigger’s wrench to steady a beam while the welder applies
a tack.
Next, we tack the corner column at the other end of the beam,
and then take a moment to check our bracing. Each time you
lower a beam into position, it acts like a wrecking ball to
pound the framework out of plumb. To keep tabs, I use a PLS5
vertical laser to project a dot from the chalk lines on the
floor. We adjust the braces until the dot streaks the edge of
the 2x6 plate on top of the beam. This takes only a few seconds
and ensures precise alignment.
As we work our way around the building, we inspect for a
consistent TOS. Just as with framing lumber, one steel beam of
a stated height may be slightly shorter or taller than the
adjacent one. We can still adjust the columns up or down on the
setting nuts to maintain a consistent top alignment.
Once most of the beams are on columns and tacked, we finish the
welds and tighten the nuts and bolts at all connections, using
a socket wrench on a cordless impact driver. This is a lot
faster than tightening by hand and ensures that each bolt is
tightened with equal force. Even though the bolted connection
is engineered to stand alone, we still weld a few inches of
bead along each angle clip to eliminate even the slightest
movement in the connection.
Packing the baseplates. With every
beam leveled, bolted, and welded, I grout the voids under the
column baseplates, using hydraulic cement. Because it sets so
fast, I mix the cement in small batches. I premeasure the
powder, use ice water to give me a little more working time,
and mix the material to a stiff consistency. I wear good
nitrile gloves and pack the cement with my fingers under the
baseplate and around the bolt shanks. It’s faster and
more thorough this way, and it saves me from having to clean
tools later.
Second-Story Steel
Before tackling this building’s second-story steel, we
installed the roof I-joists and plywood decking. The frame
shook noticeably while we were slamming the pieces of lumber
into place, so we kept the braces on the columns for the
duration. Once the roof diaphragm was completed, though, most
of the shaking disappeared.
The second-floor steel installed much like the first, except
that the columns were 2 feet shorter and bolted directly to the
first-floor beams. At all column locations, whether above or
below the beam, we welded stiffeners to the web (Figure
10). Without these stiffeners, the beam flanges would
distort when they were welded to the column and throw it out of
plumb.
Figure 10. Web stiffeners at column locations are
critical to preventing distortion of the beam flange during
welding (left). Stainless steel shims help plumb second-floor
columns (right).
Since the top of the first-floor beam was completely level, we
didn’t need setting nuts on the upper floor. Instead, we
used stainless steel shims to plumb the second-floor columns.
We buy these shims in an assortment of thicknesses — down
to 1/1,000 inch — from Manhattan Supply (800/645-7270,
mscdirect.com).
With the second-floor frame fully assembled, the bolts snugged
tight, and the welded connections complete, we welded the
bolted baseplates to the beam flange. Structurally, these welds
were redundant, but we knew that they would take a small but
perceptible amount of shimmy out of the frame.
Overhangs and Cantilevers
The roof over the second floor was designed with a 7-foot
overhang hovering above a rooftop sun deck (Figure
11). The overhang was supported by three projecting
W10x22 beams, with wood I-joists filling in between, parallel
to the face of the building. Steel beams and moment connections
perform exceptionally well under these conditions, ably
resisting both sagging and wind uplift. In my experience, long
overhangs framed with wood develop problems, often right from
the beginning. Steel is the way to go.
Figure 11. Three projecting steel beams support the
wood I-joist framing in this 7-foot-deep roof overhang (top). A
cantilevered shading trellis (center) projects from the western
face of the house, attached to the steel posts by welded butt
connections (bottom left and right).
The trellis structure on this house incorporated a true
cantilever: Level channel struts projected several feet from
the building and were simply welded to the face of the steel
columns. This type of right-angle joint isn’t possible to
execute in wood.
Cost
Considering both the recent doubling of the price of steel
(along with every other metal) and the fact that this building
couldn’t be built using conventional wood framing
techniques, there’s not much point in making a direct
cost comparison. However, for the record, labor and material
costs for the rough framing ran about $175,000, or $53 per
square foot.
Ed McPartland is a framing carpenter in
Wellfleet, Mass.