Raising the Ceilings in a Whole-House Remodel -
Continued
We would be lifting the entire second floor — walls,
roof, and all — a total of 15 inches. We settled on this
height because the existing stair risers were a comfortable 7
1/2 inches each. We decided that one riser wasn't enough and
three would be disproportionate to the house. With a 15-inch
rise, the new first-floor ceiling height would become about 8
feet 9 inches. Because the stair was more or less centrally
located in the house, we had room on the first-floor level to
elongate the flight by two treads. The stairwell remained
unaltered, but we determined that it was best to build an
entirely new staircase rather than supplement the existing one
(Figure 6).
Figure 6.Though the staircase would be rebuilt,
the original stair helped determine the distance that the
first-floor ceilings were raised: two riser heights, or 15
inches.
Due to the greater load we'd be lifting this time — I
allowed for a dead load of 15 psf, multiplied by the second
floor and the roof square footage combined, for a total of
about 19 tons — and the increased height of the lift, we
took some additional preparatory steps and precautions.
First, instead of using 2x4 retainers to prevent the building
from moving out of alignment as it rose, we fabricated 7-foot
lengths of 4-inch steel angle for that purpose (Figure 7). We
drilled holes for 1/2-inch through-bolts to pass through the
wall, where they would be captured in the same way that
sidewall staging brackets are mounted, with the capture blocks
spanning pairs of wall studs on the interior side. Instead of
costly 10-inch or 12-inch carriage bolts, we bought much more
economical 1/2-inch threaded rod and cut it to the lengths we
needed.
Figure 7.To prevent the upper story from being
displaced when it was lifted, the author installed 4-inch steel
angles to restrain it (top). At the overhanging front elevation
(middle), the crew cut L-shaped slots for the angles to pass
through the second-story floor (bottom).
As yet another precaution, we tied the middle front and middle
rear of the building's second-floor joists to the first-floor
joists with heavy chains in two places. This backup system
would help hold the top and bottom portions of the house
together if a sudden wind came up (Figure 8).
Figure 8.As a precaution against sudden strong
gusts of wind, the crew tied the front and back of the house to
the first story with a pair of heavy chains.
New Front Wall
Part of the original remodel design included the elimination of
the 1-foot overhang of the second floor at the front of the
house. In effect, we were changing the house from a garrison
colonial to a more traditional center-entrance colonial. This
change actually simplified the task of raising the first-floor
ceiling, because we could precut and build a new, full-height
wall to support the joists along the front wall. Elsewhere, at
the middle and rear bearing partitions, we'd have to tackle
more elaborate, piecemeal framing measures. Stacking short
cripple studs or a solid beam on the existing plate would
create a potential "hinge" in the wall framing that could
buckle during a wind or seismic event, so we chose to sister
longer studs alongside the existing ones, instead.
At the front of the house, we poured a new foundation alongside
the old one, filling the gap between the old and new walls with
2-inch rigid foam insulation to save on concrete, which we had
to place by hand in wheelbarrows in order to protect the
existing landscaping (Figure 9).
Figure
9. A new grade-beam concrete
foundation, poured directly along the existing basement wall,
and new wall framing provided direct support to eliminate the
overhang of the second-story eaves wall.
To further cut down on concrete, we formed the foundation as an
18-inch-high grade beam on top of concrete piers placed every 4
to 5 feet. We reinforced the piers vertically with rerod bent
at right angles to join the horizontal rerod we placed in the
grade beam.
With the second floor raised, we were able to put the new front
wall in place quickly and focus on the rest of the house
(Figure 10).
Figure 10.While the front wall went up quickly to
support the building at its new height (top), the center and
rear partitions had to be revised one stud at a time, by
cutting and sistering in full-length studs under a new top
plate. Nonbearing interior partitions were elevated with short
cripple-wall sections (bottom).
To secure the rear wall and middle bearing partition, we worked
piecemeal. We sistered the existing studs with longer ones cut
to the new height and toenailed them to a new, double top
plate. Above the interior, nonbearing partitions, we simply
added small knee walls to extend the tops.
Since the increased height of the first-floor lift exceeded the
10-inch reach of the screw jacks, we purchased a quantity of
16-foot 4x4s and cut them into 4-foot lengths. We used these as
cribbing underneath the pyramid jacking stands. This provided a
stable, strong method that could be quickly placed as needed
(Figure 11).
Figure 11.The screw jacks were limited to a 10-inch
lifting range, so the jacking stands had to be supplemented
with 4x4 cribbing placed in crosswise layers under the
base.
To set the cribbing, we used a screw jack on a nearby pyramid
to temporarily transfer the load. A pair of crossed 4x4s added
7 inches to the jack-stand height, slightly more than needed to
finish the job.
Stitching It All Back
Together
The original wall sheathing was in good condition, but it was
only 3/8 inch thick, once a basic sheathing standard. After
patching the new gaps with same-thickness material, we ran a
new, secondary layer of 1/2-inch CDX plywood over the entire
structure. This allowed us to bridge the existing and new
framing with a unifying skin. In all, the structural revisions,
including labor and materials, added about $120,000 to the cost
of the original contract.
David Morganowns DRM Design Build in Southborough,
Mass.