Before
Occasionally you have the opportunity to drastically improve
the appearance of a house as part of a living-space upgrade.
That was the case on the project shown here — a master
suite and porch addition on a home that had a 3/12 main roof
and an attached garage with a flat roof. Buildings with low-
and no-slope roofs are just asking for trouble in the wet
coastal part of Washington state where I work, so we decided to
raise the roof to a 6/12 pitch as part of the job. This would
reduce the likelihood of future leaks and enhance the
house’s curb appeal.
Plan of Action
Since the budget was limited, I had to come up with a way to
do the work without damaging the finished rooms below. Instead
of tearing off and replacing the existing roof structure, we
would leave it more or less intact and stick-frame a new,
steeper roof over it. We would use trusses on the addition and
the porch and for converting the flat garage roof to a gable
(see illustration).
New Truss Roof
To reduce the risk of water damage, we scheduled the project
for the driest part of the year. We started by framing the
addition, then turned to the garage roof, so that we could
leave the main house protected for as long as possible.
The garage roof framing consisted of 22-foot-long 6x12 beams
that pitched slightly away from the house, covered with 2x6
T&G decking — a good work platform for staging the
new garage roof.
After removing the edge metal, we installed 2x6 top plates
along the perimeter of the garage roof deck to create a level
surface for the new trusses (see photo). Using
a builder’s level to check elevation, I blocked and
shimmed the plates level, then used 8-inch lags to fasten them
to the 6x12 beams.
After adding a level plate, the author transformed the
flat garage roof into a gable with trusses (top). The new main
roof was stick-framed over existing trusses (middle). In back,
the cross gable above the addition was framed with gable
trusses and the porch’s shed roof with mono trusses;
infill stick framing bridged the gap to the main roof
(bottom).
The trusses arrived the following day, and with the help of
two framers I quickly installed them on the garage and the rear
addition.
New Stick-Framed Roof
At this point we were ready to begin work on the main gable
roof, which would be stick-framed over the existing roof. To
avoid the possibility of rain damage, I waited until the
forecast called for 10 days of dry weather, then called in the
roofing company to strip off the shingles.
We faced a couple of challenges. The existing roof had 24-inch
rafter spacing over 16-inch joist spacing, so space would be
tight for nailing new rafters alongside the old. I also wanted
to maintain the original 2-foot soffit overhang, but without
encroaching on the windows below, which steeper rafters would
do.
For these reasons, I decided to install the new 2x10 rafters
directly on top of the existing 2x6 rafters and connect them
together at the plate line. This would make it easier to attach
the rafters and allow me to preserve the original wide
overhang.
After stripping off the shingles, we removed the lower course
of roof sheathing to expose the top plates (see
photo). We then rolled back the old batt insulation
and cut the existing rafter tails and eaves overhangs flush to
the wall. Next, we cut a series of large openings through the
sheathing for access and venting (see photo)
and installed a new 2x12 ridge supported by posts that ran to a
bearing wall below.
New notched 2x10 rafters sit directly on top of the
existing 2x6 rafters, held in place by pairs of plywood gussets
(top). Openings in the original sheathing provide access and
venting to the area between the old and new roofs
(bottom).
Fitting the bottom end. We laid out the plumb cut on
the new rafters in the usual manner, but made a 3/12 seat cut,
to match the slope of the rafter below. We then installed the
new rafters on top of the old, connecting them on both sides
with 3/4-inch plywood gusset plates fastened with closely
spaced 1 3/4-inch medium crown staples. (Although this project
was not engineered, the plan checker at the building
department, himself an engineer, had no qualms about signing
off on it.)
The original rafters had only been toe-nailed to the top
plates, so we reinforced that connection with hurricane ties.
We also installed cardboard insulation baffles at the eaves
while the area was still accessible from above.
The finished remodel adds curb appeal to the front of the
house (top) and needed space in back (bottom).
Cross-Gables and Infill
The next step was to tie in the new trusses to the new stick
framing. The lower-pitch mono trusses over the back porch
stopped at the wall of the house, so we completed the framing
by gusseting 2x6 rafters to their top chords and running them
back to sheathing on the new stick-framed gable. We also framed
a new, steeper gable over the entry and filled in the
transition between the addition and the main roof with overlay
stick framing.
Finally, we sheathed the rest of the roof, built vented
soffits, and called in the roofers. All told, it took three
carpenters eight days to reframe the roof.
Elmer Miller owns Miller Estimating & Consulting in
Lynden, Wash.