Installing a Wide Door In a Tall Brick Wall -
Continued
We used an angle grinder with a diamond blade to score the
stucco and outline the pockets that would temporarily house the
braces. A rotary hammer equipped with a chipping bit made quick
work of the brick as we cleared the pockets (Figure 5).
Finally, we inserted the four support braces. We shimmed where
necessary, using wood ripped from 2x4s and pounded into place,
and bolted the base plates securely to the footings with wedge
bolts (Figure 6).
Figure 5.After placing
the braces on their footings and marking their positions on the
wall, the author's crew cut 8-inch-deep pockets into the
12-inch-thick masonry wall for the upper shelf of each
brace.
Figure 6. Once the braces
were maneuvered into position, the crew shimmed them (top) and
bolted them securely to the concrete footings with wedge bolts
(bottom).
Cutting the Rough Opening
After marking the rough opening, we scored the wall with the
grinder and started chipping away. Although we were confident
the braces would support the wall, we still worried about the
kitchen's ceramic-tile floor and a granite countertop
positioned against the exterior wall: Too much movement might
crack one or both. So as we tackled the wall below with our
rotary hammers equipped with chisels and points, we monitored
conditions in the kitchen above. Fortunately, the braces held
everything securely in place, giving us the time we needed to
get the rough opening right.
To help smooth out the edge of the section of wall that we had
chipped away, we built a plywood form sized to cover half the
height of the wall. We first braced the form at the bottom of
the wall and then filled it with mortar, pounding the form with
a lump hammer to get the mortar to settle and fill in around
the ties we had inserted into the old brickwork. The following
day, we shifted the form up and finished the top half.
Before inserting the steel beam and installing the new door, we
had to create a level threshold. We began by cleaning up as
much of the old foundation wall coming up from the basement as
we could with a chipping gun. Then we drilled, vacuumed, and
screwed 3-inch-long masonry fasteners into the top of the wall,
leaving 1 1/2 inches exposed to help tie the new concrete to
the old masonry as we formed and poured the new threshold.
After marking both the left and right walls at 82 1/2 and 92
1/2 inches to indicate the top and bottom of the beam, we
chiseled 6 inches into the walls to create ledges for the beam
to sit on, adding 1/2 inch to the rough opening to accommodate
steel plates under each end of the beam (Figure 7).


Figure 7. Formed on top
of the broken-out foundation wall, the newly poured threshold
offered a smooth, level reference point for laying out the
rough opening. The brick side walls shown in the photo above
would receive a smooth mortar cap before installation of the
new door.
Setting the Header and Installing the
Door
The original plans called for a single W14x38 steel beam
(measuring 14 inches high by 6 3/4 inches wide, and weighing 38
pounds per lineal foot), fabricated with a brick shelf composed
of three 3 1/2-by-3 1/2-by-1/4-inch angles welded together. But
the estimated weight for that girder was 675 pounds, way more
than we wanted to handle, so Herschlag substituted two
285-pound W10x22 steel beams (measuring 10 inches high by 5 1/2
inches wide by 13 feet long, and weighing 22 pounds per lineal
foot, at $275 each) for the W14x38. While not exactly light,
these beams were easier to wrestle into position, and their
combined 11-inch width was better suited to the 12-inch
thickness of the wall. Because the exterior faade had a
cover of stucco, we were able to substitute concrete block for
brick to rebuild the section of wall above the girder, thereby
eliminating the need for the brick shelf.
After we insulated around the girder with fiberglass and spray
foam, we were ready for the door. We could have finished
patching up the exterior wall at this point and removed the
braces, sparing ourselves the risk of dropping something
through the glass below. But, for weather and security
purposes, we elected to install the door first (Figure
8).
Figure 8.A pair of 5
1/2-by-10-inch steel beams supported the masonry above the new
door opening. The author chose to install the door before
removing the braces, making it easier to secure the site during
construction.
To get the door from the street to the backyard, we had to
completely disassemble the 12-foot-wide Marvin "knockdown"
unit, which meant breaking down the frame as well as the four
door panels. Fortunately, the care we'd taken to square and
plumb the masonry paid off when we reassembled the frame in the
R.O. Installing the door first turned out to be a great
decision, as it made the site easy to lock up at night, kept
out the winter cold, and filled the basement with light.
Finishing Up
With the door installed and the steel girders in place, we
finished blocking up the opening. As we laid block, we removed
one brace at a time and filled each pocket before removing the
next. After each support was removed and the opening blocked,
we padded out the steel web with plywood, then fastened wire
mesh over the steel and block in preparation for the stucco. We
experimented with mortar dyes to approximate the existing
stucco color and did our best to blend the new with the old
(Figure 9).
Figure 9.Because the
masonry wall has a stucco finish, economical 12-inch block
instead of brick was used to fill in above the new steel header
(top). The author's crew made sure each section of wall was
well supported with block before removing the braces, one at a
time (middle). Mortar dye added to the stucco matches the new
work to the existing wall (bottom).
We spent the next week working on the interior, but that wall
of glass (Figure 10) never let us forget there was 1,600 pounds
of steel that we had paid $2,700 for sitting in the backyard.
Because the only access to the backyard was through the house,
we needed to get the steel out before turning our attention to
the extensive interior finish work. After discussing over a few
lunches whether we wanted to store these expensive braces in
our shop, we decided to keep life simple: We cut them up and
scrapped them for peanuts.
Figure 10.The wide glass
door brings plenty of light into the new ground-level living
space and offers easy access to the backyard.
Rob Corbo is a building contractor in
Elizabeth, N.J.