Armin Gollannek
I’m a stair builder in Michigan’s Upper Peninsula.
My specialty is one-of-a-kind stairs, which I build in my
millwork shop and then transport to the site for installation.
This approach reduces travel expenses and greatly extends my
working range. It also ensures that I get a professional-grade
spray-booth finish that’s much nicer than I could ever
apply on site.
In late 2007 I received a call about replacing a curved
staircase damaged in a fire. At first I wasn’t sure I
wanted to look at the project; fire-repair work is messy, and I
was concerned that the homeowners would want me to work within
an existing footprint that was too small for a comfortable
code-compliant stair.
I needn’t have worried. The house turned out to be a
total gut job, stripped to bare framing and primed white to
seal in the smoke damage. And the owners were great customers
— instead of telling me what they wanted, they asked what
I envisioned in the space. The house was perfect for a design I
had been thinking about: wood treads projecting out of a curved
wall with no visible support at the outboard end. I gave the
owners a CAD drawing and a description of how I would use a
concealed steel frame to support wooden stairs, and they hired
me to do the job.
We decided to build the stairs against a new curved wall framed
to the edge of the opening for an existing basement stair. This
wall — which would be clad in manufactured stone —
would extend from the basement to the second-floor ceiling.
Templating
After building a temporary platform over the basement stair
opening, I screwed down three sheets of 1/8-inch Masonite to
create a full-scale template for the stairs (see Figure
1). Then, using a level and laser plumb bob, I
transferred the locations of key reference points to the
template, including the balcony header, the edge of the
second-floor platform, and points plumbed up from the arc of
the existing stair opening.
Finding the center. Everything I built would be laid
out from the center point of the opening in the floor. To find
it, I drew chords between the points plumbed up from the
existing opening, then drew perpendicular lines from the center
points of the chords (Figure 2, page 2). The
intersection of these lines was my center.
The template would have to make a number of trips between the
shop and the site, so I marked the exact location of the screws
securing it to the floor, then used the same screw holes every
time I refastened it. In addition to the template, I made a
story pole showing the vertical distance between the first
floor, the raised foyer floor, and the top and bottom of the
second floor.
Layout
Back at the shop, I marked the thickness of the finish-floor
materials onto the story pole and divided the total rise into
fourteen 75/8-inch risers. I then drew a plan view of the stair
onto the master template.
The existing basement stair gave us our radii — 8 feet 9
inches at the outside and 5 feet at the inside. Subtracting the
thickness of the manufactured-stone wall cladding left us with
42-inch-wide treads. There was sufficient distance between the
balcony header and foyer landing for me to create an 11-inch
run at the line of travel, 12 inches in from the center of the
balusters.
The eight lower treads would cantilever from the wall; the five
upper treads would be suspended between the balcony header and
the cantilevered treads. Each tread would be supported by a
tubular steel frame.
Structural Design
This wasn’t the first stair I’d supported with a
hidden steel frame, but it was the largest, so I enlisted the
help of the engineers at the fabrication company, UP
Fabricating Co., in Rock, Mich. They helped me with the design,
verified that it would work, and supplied steel components
based on my drawings and cut list.
Main components. Among the parts provided were 2x4 box
tube studs, curved plates for the wall, and tread frames made
from 2x2 tubing. The tread assemblies would connect to each
other with vertical riser bars made from 11/2-inch square bar
drilled at one end to accept a baluster.
Wall Plates
To lay out the curved wall, I installed multilayer plywood wall
plates that I had made in the shop, aligning them with the
plumb beam of a laser attached to a trammel (Figure
3). The laser beam was 8 feet 9 inches out from the
pivot at the center point of the layout, so swinging the
trammel caused the beams to describe the face of the wall.
The plywood plates would provide nailing for the drywall and
cement board to be installed on the wall. Once the top and
bottom plywood plates were accurately positioned and fastened,
we installed the curved steel plates over the plywood,
through-bolting them to the floor framing. This gave us the
surfaces onto which the iron studs would be welded.
Assembling the Frame
After installing the metal wall plates, I fastened the template
to its original position on the floor so I could use it to
locate the structural parts of the stair. The plan was to
assemble the frame with tack welds and then complete the welds
later on. To save time, I hired a certified welder to complete
the welds.
Temporary support. The tread assemblies came
pre-assembled as three- and four-sided frames. With no
stringers to orient the treads in space, I built a temporary
wooden stage. This would support the treads while I positioned
them over the template by plumbing up with a laser
(Figure 4, page 4). To facilitate leveling, I
threaded 1/4x20 bolts through the stage and used them to raise
and lower the corners of the tread assemblies. Once the tread
was in the correct position, I tack-welded it in place.
Top down. I installed treads from the top of the stair
down. The first tread was welded to a plate bolted to the
balcony header; each of the next four hung from a pair of riser
bars — one bar at each end — connected to the tread
above. From the sixth tread down, there was only one riser bar
between treads because the inboard ends were welded to the 2x4
steel tubes in the wall. The tubes were welded top and bottom
to the curved steel wall plates (Figure 5).
Welding technique. Welding suspended parts is
unforgiving work; mistakes are cumulative and not easily
corrected. Vertical, flat, and upside-down welds are all
required and the heat generated has a tendency to warp and
distort the joints. The key to avoiding this problem is to weld
in short runs and alternate between opposite sides of the
piece.
After each set of welds, I checked for alignment using the
laser positioned on the floor template as well as an assortment
of magnetic levels. Since much of the welding was done indoors,
we used a 220-volt 180-amp MIG (metal inert gas) welder (Hobart
Welders, 800/626-9420, hobartwelders.com) supplied with a
mixture of CO2 and argon shielding gas, which reduces messiness
by eliminating the need for flux. The 220-volt welder is good
for thicker metal and has a longer duty-cycle time than a
110-volt machine.
Wall Cladding
When the welder was finished, I installed temporary plywood
treads on the frames and attached 2-by nailers to the tubes in
the wall. Next, the drywall hangers installed cement board on
the concave side of the wall as a substrate for the artificial
stone.
To avoid scribing the wood tread covers to the irregular stone
surface, I installed tread-shaped grounds where the tread
assemblies would enter the wall (Figure 6).
The masons butted their stone to the grounds — which,
when removed, would leave openings into which I could tuck the
treads.
Finished Parts
While the masons were installing stone, I was in the shop
making the wood parts that would cover the steel core of the
stair. Made from a combination of red and curly birch, the
cladding was designed in such a way that I could finish the
pieces in the shop and install them with the fewest exposed
fasteners possible. I fastened the tops of the treads first,
screwing in from the bottom through predrilled holes in the
frames.
Balusters. Next, I installed metal balusters
(part #40-602P) purchased from Custom Ornamental Iron Works
(customiron works.com). At the front of each tread, the
baluster passes through the wood and into a hole bored into the
top of the riser bar. I tapped a second hole drilled in from
the side to accept a set screw for locking the baluster in
place. The rear balusters dropped into holes in the treads and
were held in place with PL Premium Polyurethane Construction
Adhesive (Henkel Corp., 800/999-8920, stickwithpl.com).
Tread cladding. Once the balusters were in place, we
finished the treads by mitering a 23/16-inch-tall ogee nosing
around the edges of the support frame and covering the bottom
edge with 5/8-inch-thick curly birch. The miters were fastened
with 23-gauge pins; other joints were biscuited and glued. I
used the PL construction adhesive to attach prefabricated
covers to the riser bars (Figure 7).
The remaining work involved installing the newels, rails, and
balcony trim. Some of the components were curved and all were
prefinished, but otherwise this part of the job was typical
stair-building.
Proof of Strength
The completed stair is very stiff. One day I walked onto the
job and found that the masons had set part of their staging on
the outer edges of two treads near the center of the span. It
was quite a shock to see two burly masons and hundreds of
pounds of stone, staging, and mud creating a point load at one
of the weakest parts of the stair. My concern was short-lived,
though: A quick check with a level showed that the load had
caused less than 1/16 inch of deflection.
Armin Gollannek owns Northern Sun Woodworks in Munising,
Mich.Figure
1. The author begins the new set of stairs by building
a temporary platform over the basement stair opening and
transferring key locations onto a hardboard template. Here he
uses a laser to plumb down the location of the balcony
header.Figure
2. To find the center point of the curved basement
stair opening, the author draws chords between points on the
arc, then a line perpendicular to the center of each chord;
where the lines intersect is the center point (left). After
drawing a full-size layout of the stair on the template, he
makes patterns of the steel tread assemblies (above) and sends
them to the fabricator.Figure
3. The curved bottom plate is located by plumbing down
from a laser attached to a trammel that pivots off the center
point (above). A carpenter shifts the position of the top plate
so it’s in line with the beam that projects up from the
laser (right).Figure
4. The author uses a temporary wooden stage to support
tread frames while he positions them over the template. The
block taped to the corner of this tread has the same cross
section as a riser bar; its center is being used as the laser
target (left). With the frame positioned horizontally in space,
he checks its height against the story pole (below left). He
fine-tunes the height of the frame by turning threaded bolts in
the stage (below center). Once the frame is in the correct
position, he connects it to the preceding tread frame by
welding it to a vertical riser bar (below right).Figure
5. Posts are installed between the top and bottom
plates of the wall (far left) and then welded to the tread
assemblies (left). Once all the pieces are connected together,
the stage is removed (below) and the welds are
completed.Figure
6. Temporary wooden grounds (above left) space the
stone off the tread assemblies. When the stonework is done and
the grounds removed, the treads will slip into the recesses
with no need for scribing. The tops of the treads are screwed
to the frame from below (above), then the sides and bottoms are
glued in place (inset).Figure
7. The lower treads of the completed stair seem to
grow out of the stone (left) while the upper treads appear to
hang in the air (above).