Foolproof Layout For Winding Stairs - Continued
My next step is to mark tread divisions on the face-skirt line
by dividing its total length into equal segments. Depending on
the total run and configuration of the stair, there may be a
number of "common" treads — full-width treads that occur
in a straight section of the U. You can determine this by trial
and error, trying to keep the narrow ends of the wedge-shaped
treads as close to the minimum 6 inches as possible. The stair
shown here had two commons.
With the tread spacing marked equally along the face-skirt
line, I connect those marks to the divisions along the walk
line and extend each line to the wall. This gives me the
complete finish riser line for each step; from there, it's easy
to mark the back of the 3/4-inch finish riser, then the back of
the plywood subrisers, which tells me where the rough stringer
plumb cuts go. (I also add other details to the drawings as
needed — nosing, wall skirts, newels, baluster, and
railing.)
Stringer Layout
I use LVL for stringers; it's 1 3/4 inches thick and very
stable, and comes in a variety of widths. Because the winders
cross the stringers at different angles, the stringer shapes
become complex and require wider-than-normal stock. For this
stair, I used 16-inch-wide LVL.
All the information I need to lay out each stringer is right on
my full-size plan. I draw 3/4-inch offset lines behind the
finished risers and inside the skirtboard line to represent
their respective thicknesses. Then I draw secondary offsets 3/4
inch behind those lines to represent the thickness of the
plywood subrisers. I draw the stringers according to their
actual spacing on the plan. This stair was only the minimum
allowable 36 inches wide, so I used three stringers. On any
stair wider than 36 inches, I use four stringers. I draw the
stringers with a red pencil to distinguish them from all the
other pencil lines.
This is where the story pole becomes indispensible. By holding
it at right angles to the stringer lines, I can accurately mark
the risers where they occur on each stringer — no two
stringers will be alike (Figure 4).
Figure 4.By laying the story pole perpendicular to
the plan and snapping out riser lines, the author can project
full-scale templates for the rough stringers.
I make all of my stair carriage components in the shop —
this one took a couple of days — and then haul them to
the site for assembly as a rough stair. Installation usually
takes two guys about a day to complete. We lag the stringers
together at the turns, and to the walls, with
5/16-inch-diameter GRK star-head screws (GRK Fasteners,
807/474-4300, www.grkfasteners.com), driven with an impact
driver fitted with a Torx bit. The screws are rated for shear
and provide a rugged connection.
Starting at the bottom and working up, we glue and screw the
plywood treads and risers, using construction adhesive to
eliminate squeaks. We continually check the stringer heights
with the story pole and check the subtreads for level,
front-to-back, and side-to-side accuracy. We try to keep the
face side of the stair about 1/8 inch higher than the wall side
to counteract deflection. Once all the treads and risers are
attached and the glue dries, the entire carriage becomes one
strong, monolithic structure (Figure 5). Before leaving the
site, we install all the blocking needed to secure finish
components — for instance, where railing meets wall
— and install a temporary 2x4 handrail that's screwed,
not nailed, together for easy removal.


Figure 5.Shear-rated lag screws connect
intersecting stringers and fasten the inside members to the
walls. Plywood subrisers and treads, installed with screws and
construction adhesive, convert the individual stringers into a
strong monolithic structure. Temporary, 2x4 guardrails, screwed
together for easy removal, provide fall protection for workers
using the rough stair.
Once the flat plastering is done, we return to fur out the
underside, or soffit, of the stair so that it can be plastered
to a pleasing, sculptural curve. To do this, we first fasten
flexible wood battens or contoured plywood strips to the wall,
following the underside of the wall stringers (Figure 6). We
adjust the battens by eye to form graceful, flowing lines that
connect the upper and lower ceilings. The face stringer line
requires no additional adjustment, as it follows an equal
offset from the tread nosings. However, keep in mind that a
slender face skirt looks better than a heavy one; I control
this by leaving about 4 inches of solid lumber under the
tread-riser cutouts.
Figure 6.Carpenter Mike Kennedy adds a plywood
batten beneath the wall stringer to create a visually fair line
for the plaster furring to follow.
We bridge between the face and the wall with metal "high-hat"
furring, named for its hat-shaped cross section. High-hat is
easily cut using sheet-metal snips, and is fastened with
drywall screws on 12-inch-average centers. It's important to
install each piece of furring level, to keep the soffit
parallel between the top and bottom of the stair (Figure 7).
The pitch of the stringers is not the same at the wall side and
at the face side, but the high-hat can be readily twisted to
accommodate the difference.
Figure 7.Pieces of metal high-hat furring channel
get individually leveled across the underside of the stair to
ensure a level start and end to the transition between upper
and lower ceilings (top). Leveling automatically fans the
furring across the plane of undercarriage (bottom). The eye is
the final judge of appearance: To ensure a pleasing line,
individual furring pieces may need slight
adjustment.
Once all the pieces are installed, I adjust pieces up or down
to fair the overall plane. Then the plasterers screw expanded
wire lathe to the furring and apply a plaster scratch coat, the
first in a three-coat job.
Newel posts. Because they would be partly embedded in the
plaster, we installed the newel posts at the rough stage of
this project, using GRK screws to fasten them (Figure 8). The
assembled rough stair carriage was strong, but the furring and
continuous diaphragm of plaster made it even stiffer. Before
the finishing coats could be applied, we had to install the
face skirt, because the plaster would finish directly against
it.
Figure 8.The author lays out the newel notch
directly on the winders (top left), then transfers the
information to the post. After notching, the post is positioned
(top right), then shimmed plumb and bolted from the back
(bottom). Plugged bolts are added later through the face for
reinforcement.
In any job, the skirt, like the stringer, has to be cut from
wider-than-common lumber — in this case, glued-up walnut
boards. We fit the face skirt between newel posts, scribed the
soffit profile on the back side, and cut it to shape (Figure
9). Then we held the skirt in place to scribe the tread and
riser cutouts. Although the winders didn't form 90-degree
corners at the skirt, I made all the skirt cuts at 45 degrees
and adjusted each riser angle to fit (Figure 10).
Figure 9.A plaster scratch coat establishes a
rough plane against which the face skirtboards can be scribed
(left). The author cleans up the skirt's curving profile before
gluing on a decorative edge bead (above left). After the face
skirt is installed (above), the final plaster coat will fill
any gaps and provide a smooth surface that flows between
ceiling levels.
Figure 10.The author uses a 45-degree default angle
for the vertical skirt cuts and adjusts the finished riser
angles individually. The shim space behind the skirt allows the
miter joints to be adjusted plumb and tight.
Hand Railing
We custom-make balustrade components in the shop. This is not
only the best way to match existing architectural details, but,
in some cases, it's the only way to get the unique transitional
pieces needed to assemble a complex, flowing handrail. The
balustrade on this job was a relatively simple post-and-rail
configuration, in which railing segments butt into the newel
posts at all points of transition. Nonetheless, the handrails
had to be custom-shaped to follow the stair's irregular fall
line.
We handle this kind of situation by producing and delivering
the balusters first, so that the painter can prefinish them
before installation. This approach saves time and gives the
finished railing a crisp, professional appearance. Ideally, we
also install all of the landing nosings before the finish
flooring goes in, so that it scribes to the stair rather than
the other way around.
The woodwork — treads, risers, skirtboards, moldings,
balusters, and railing — is installed using conventional,
high-end finish carpentry skills and a bag of special
stair-builder tricks, but that's another topic for a future
article.
Jed Dixonowns North Road Stairbuilders in Foster,
R.I.