Before
Last summer, a homeowner here on Cape Cod called to ask if I'd
look at a large skylight he wanted to replace. The house
— which he'd bought earlier that year — was an
earth-sheltered, passive-solar structure dating from the late
1970s. On its south-facing roof was a site-built 12-by-16-foot
skylight glazed with three layers of translucent,
fiber-reinforced plastic sheets separated by stacked 2x4
framing. It leaked, and the sheets had become too yellowed to
see through. I was surprised it had lasted so long without
blowing away.
My client, however, loved the dramatic size and the interior
daylight. He wanted to replace the entire skylight area with
manufactured roof windows, which would be both transparent and
presumably more energy-efficient. I liked the idea and agreed
to help design and install the replacement.
Layout and Framing
The unusual 70-inch-on-center truss spacing created three basic
bays that I would need to subdivide into smaller mulled
openings. The trusses measured 5 1/2 inches wide, leaving a
5-foot-4 1/2-inch space between them. I found that two Velux
306 roof windows (www.veluxusa.com) — with a unit size
of 30 9/16 inches wide by 46 1/4 inches high — would fit
side-by-side between the trusses, with just enough room for a
double rafter between them. In fact, the two units' combined
width of 61 1/8 inches left only 3 3/8 inches — not quite
enough space for the framing and the recommended 1/4-inch
rough-opening clearances. But because the units would be
deck-mounted, not inserted into the openings, I figured I
didn't really need any wiggle room provided the framing was
meticulously square.
Referring to installation information on the Velux Web site, I
drew a layout schematic. The final design contained a total of
18 windows — six across stacked three high, with
alternating 3-inch and 6-inch spacing in between. Fortunately,
the side-to-side flashing options allow for spacing from 2 1/2
to 12 inches wide in 1/2-inch increments. Head-to-sill stacked
spacing is restricted to 4 inches. Along the top and bottom,
about 12 inches and 6 inches, respectively, are needed to
accommodate the head and sill flashings.
Before providing a quote, my vendor faxed the drawing to the
Velux distributor to verify my assumptions. In response we
received a confirmed list of all the proprietary flashing
components needed. In all, we'd be using 14 fixed units, four
venting units, and a slew of proprietary flashing components,
at a cost of just under $7,000. On delivery, we were buried in
cardboard boxes.
After tearing out the old skylight, we found that the existing
opening was within 1/8 inch of square — a great start
(see Figure 1). To ensure that the new framing would be
accurate, I made story sticks showing the unit dimensions and
the flashing spaces between them, one for the horizontal layout
and one for the vertical layout.
Figure 1. The original rough opening
(left) was almost perfectly square, a lucky start on a project
that demanded accurate framing (below).
We used 2x8s for the openings, to match the existing built-up
insulated roof. The framing rested securely on the trusses and
the exterior bearing wall below. After a couple of days of prep
and framing, we were ready to install the skylights.
Installing the Units
On the ground, we prepped the units by removing the aluminum
cladding as instructed and folding the installation brackets
out from their shipping position. The bracket locations were
already offset from one side to the other to avoid conflict
when combining units. We snapped a chalk line square and
parallel to the opening's bottom edge and screwed the story
stick down alongside it (Figure 2). The stick supported the
first row of units and guided its placement. We started
arbitrarily at the lower right corner and worked to the
left.
Figure 2. The author laid out the units
and the flashing spaces between them on a 1x3 story stick that
he nailed to the roof to guide framing. Here, the stick is
screwed to a chalk line below the completed rough opening to
support and position the bottom row of windows. Plywood gauges
ensure accurate spacing between the window frames and prevent
dimensional creep.
The window package includes 1 1/4-inch annular-ring
installation nails, but we used 2-inch-long #8 Fastap Plus
screws instead (800/847-4714,
www.fastapscrews.com). Screws are easier to
remove when adjustments are needed, and they're plenty strong.
I cut plywood spacers to precisely control the flashing gap
between units — 3 inches wide and 6 inches wide for the
side-by-sides, and a set 4 inches wide for stacking the units
vertically.
The installation manual requires roofing underlayment around
the window frame, folded up from the roof onto the sides and
wrapped in sequence from bottom to top around the four corners.
According to the manufacturer's rep (who was attentive and
helpful throughout our unusual installation), this helps
prevent problems from moist interior air condensing on the
underside of the aluminum flashing. I don't quite agree with
that premise; that's what minimal-expanding foam is for. But
providing a carefully installed secondary barrier against
wind-driven water and ice dams does make sense.
We used self-adhesive membrane (Figure 3), beginning with Vycor
(Grace Construction Products,
www.na.graceconstruction.com) in 6- and
9-inch-wide rolls. Between units, we had lots of three-way
U-shaped folds to make. We scored the release paper on the back
so we could bond first to the roof deck and then to the frames.
But in the August heat, Vycor's release paper tore away in
annoying, uncontrolled strips. Picking at it only made the
problem worse, rendering the product useless. Vycor is
undoubtedly great when laid flat around a vertical window
— the problem was in the folding.
Figure 3. U-shaped and L-shaped pieces of
self-sticking roofing membrane seal the transition between roof
and frame (top). The author cut strips from a 3-foot-wide roll
of ArmourGard Ice & Water Protector, then scored the
release sheet so it could be peeled away a section at a time
— first the middle (bottom left), then the sides (bottom
right).
We switched to 3-foot-wide ArmourGard Ice & Water Protector
(IKO, 888/456-7663, www.iko.com), which has a silicone-plastic
backing that reliably peeled away in one piece. We cut it into
the widths needed and scored the backing with a razor knife.
Although thinner than Vycor and a little trickier to score
without slitting all the way through, it worked like a charm,
even in 90°F weather.
With the underlayment wrapped around the frames, we next
installed the flashing, starting with the bottom aprons.
There's an integral rubber underglass gasket on the unit that
must be pulled over the top of the apron's rim (Figure 4). A
slide-on clip engages the aprons' upturned hems and makes a
watertight connection between them. U-shaped aluminum channel
flashing fits between units and overlaps the apron flashing by
6 inches. The channels are made for use with all models and, in
our case, had to be cut to length. I used a plywood sled on the
table saw, rotating the piece to cut one side at a time with a
shallow-set 40-tooth ATB carbide blade. This made a clean,
factory-grade cut (Figure 5).
Figure 4. The head and apron flashings
have an open hem (top) that engages an interlocking clip
(bottom left), completing the water barrier. It's important to
draw the rubber curb seal over the top of the apron flashing to
prevent leaking (bottom right).
Figure 5. Cutting the flashing on the
table saw prevents the distortion created using snips. The
channel gets cut flush with the heads and is then overlapped 6
inches by the combination head-sill flashing.
Tricky Access
We were able to install the bottom and middle rows by standing
on the roof and on scaffolding set up inside. The vertical
perimeter was easy to get to and we step-flashed and shingled
as we went. But installing the field flashing was a bit of a
challenge. To get access, we rigged up a sledlike scaffold that
straddled the installed bottom row (Figure 6).
Figure 6. Access to the middle row of
skylights was provided by staging inside the house (top) and,
on the outside, a pair of planks spanning the installed bottom
row (bottom left). The 2x8 planks were attached to the roof
framing with 12-inch-long timber screws. Intermediate support
runners, secured to the planks with 6-inch bolts (bottom
right), gave additional support.
First, we stood 2x8 "runners" on edge on either side of the
general area, running from top to bottom. I had some
12-inch-long hex-head TimberLok bolts (FastenMaster,
800/518-3569, www.fastenmaster.com) left over from
another job, which were perfect for anchoring the top ends into
the roof framing. I figured the bolts would help prevent the
boards from rolling over. For insurance we used two bolts at
the top end, about a foot apart.
The runners supported two 18-foot 2x12 planks spanning the
windows. Above the truss locations, on top of the channel
flashing, we slid shorter lengths of clean, smooth 2x8 under
the planks from below, taking care not to scratch the
flashing's bronze finish or interfere with the head-flashing
installation, which drops 6 inches below the heads. These
intermediate supports broke the spans into sufficiently stiff
6-foot sections. We held them in place with 6-inch TimberLoks
driven through the planks. The roof had a 6/12 slope, so it
wasn't too awkward to work from the planks; any steeper,
though, and I'd have added some angled blocks to level the work
surface.
We lined up the first middle window above the bottom corner
window and used the 4-inch plywood spacers to stack them. The
rest of the windows more or less fell into place with the
spacers guiding their placement. After finishing the
underlayment, we replaced the cladding pieces and installed the
combination head-apron flashings. These fit quite snugly and
needed to be forced into place with firm pressure. The flashing
also trapped the rubber gasket against the frame; it took some
finessing to fish out the gasket and place it over the top of
the flange where it belongs. The head flashings interconnect
the same way as the aprons, with a slide-on clamp.
There was one slight catch in the installation process. On each
side of every head flashing is a dimple, intended for a wood
screw that holds it down and against the frame (Figure 7). With
only a 3-inch space between units and two layers of aluminum to
punch through, I couldn't think of any way to install those
screws. Instead, I decided to hold the flashing down with
3/16-inch-by-1/2-inch aluminum rivets, drilled through a
vertical fin that the flashing wraps over at the top of the
unit. I knew the rivets wouldn't compromise the flashing
— but I also didn't want to compromise the warranty, so I
called the manufacturer's rep, described the problem and my
solution, and got the go-ahead. Since the rivets are just
visible from the ground, we treated the 6-inch-wide channels
the same way.



Figure 7. The combination head-sill
flashings fit snugly in the 4-inch space between stacked units
(top). Four small screws hold the finish cladding in place. A
right-angle Phillips screwdriver (bottom left) would make good
standard equipment in the installation kit, since the author
had to run out and locate one mid-job. Note the stainless steel
rivets (bottom right) — the author's solution for
securing the head flashing because there wasn't enough room
between units to insert a screw in the dimple along the
side.
With the middle row completely flashed, we reset the scaffold
for the top row. Initially, it seemed possible that we could
install the windows by working from above, but a brief trial
got rid of that notion — it was much too awkward and
risky.
There were four venting units along the top row — one at
each outside corner and two in the center truss bay. After
installing four units using the plywood spacers as usual, we
sighted a misalignment from down below, when we peered up the
channels. This made no sense at first, but we found that,
unlike the fixed windows, the venting units allow the frames to
rack out of square. Good thing we used screws. We pulled three
windows, realigned the first corner unit, and the rest went
according to plan.
There was a masonry chimney to the left of the top row of
windows, only about 12 inches away. I peeled back its lead
flashing, wrapped the brick with underlayment just as we'd done
with the roof windows, and tapped the lead back down. Roof
shingles and 30-pound asphalt paper provide separation between
the two flashings, in case aluminum and lead aren't
compatible.
Figure 8. The 18 roof windows are a
dramatic improvement — in both appearance and performance
— over the original translucent plastic.
Eight months and several cold, wet, windy storms later, the
installation is leak-free (Figure 8). When the customer is
ready, we'll trim out the interior. Given the precise alignment
between units, that job should go like clockwork.
Dave Holbrook is a builder on Cape Cod,
Mass., and a JLC associate editor.