First Time Out With ICFs, continued
Reinforcement. Polysteel's
specs call for a minimum rebar placement of #3 bar at 2 feet
on-center, horizontally and vertically. They also say to
consult local building codes, but they provide a reinforcement
engineering table that tells you how much rebar to place for
walls of any height or thickness in various soil types. It's a
lot more rebar than most contractors place, I'd bet. On our job
we placed the bar 2 feet on-center as specified, but I went up
from #4 to #5 bar, just to be conservative. The added cost was
insignificant, but, according to the table, this change
increased the strength of the wall considerably. We placed the
bar as we stacked the forms (Figure 3). The vertical bars sit
beside the stubs sticking out of the footings. Horizontal bars
lie in metal chairs, or hammocks, that span the forms and keep
the bars centered within the wall space. When you use the metal
chairs, you don't need to tie the horizontal and vertical bars
together with wire.


Figure 3.Polysteel's instruction manual includes a
reinforcement table that specifies the rebar size and placement
for any soil condition, wall height, and wall thickness. Wire
saddles placed across the forms keep the bars centered in the
concrete core section (left). If saddles aren't used, the
vertical and horizontal bars must be tied together with wire
(right).
Window openings. There were two windows and a door in
one of my basement spaces. Since Polysteel is designed for
above-grade as well as basement walls, the company has given
windows a lot of thought. They're not hard to deal with: You
just build a window buck of pressure-treated wood to the
rough-opening dimensions and add bracing to hold them in place
during the pour (Figure 4). The permanent attachment between
buck and wall is provided by 1/2-inch lag screws, 4 inches
long, which are driven through the wood into the form voids.
When the concrete sets up around the lag screw threads, the
whole assembly is firmly locked in place.

Figure 4.Window openings are created with simple
site-built window bucks made from pressure-treated 2x10 stock.
A slot between the two spaced 2x4s that serve as the bottom
sill makes it possible to pour concrete into the forms below
the window opening. Temporary wooden flanges help position the
bucks (the inside flanges are not yet in place in this photo),
while added exterior bracing keeps them plumb during the
pour.
Bracing. Adequate bracing is
a critical part of any concrete pour, and this is especially
true of ICFs. Don't try to get by with fewer braces than the
instruction manual specifies. We shot 2x4s into the footings on
both sides of the wall at the bottom and then made a sort of
ladder built of 2x4s to lie along the top edge of the forms
(Figure 5). These upper and lower frames are connected with
vertical 2x4 members spaced about 8 or 10 feet apart, and we
braced them to stakes driven into the ground with additional
2x4s.
Figure 5.Vertical 2x4 braces spaced about 8 feet
on-center tie into a 2x4 "ladder" laid over the top of the
forms to stiffen them. Diagonal braces run from the vertical
braces back to the ground (top), and a working platform tied
into the bracing system provides easy access to the tops of the
forms (bottom). It's important to use at least the minimum
bracing specified in the manual.
We also attached a working platform of 2x10s to the vertical
braces at about half-wall height wherever access was at all
difficult. It would be tempting to dispense with this working
platform, but that would be a big mistake: It's very helpful to
have good, comfortable access to the whole top of the wall as
you pour, so you can easily move the hose along and manipulate
it.
The Pour
The waffle shape of the wall system conserves concrete: A
Polysteel wall uses about 25% less concrete than a
conventionally formed wall of the same nominal thickness.
Polysteel's handbook provides a formula for estimating concrete
quantities based on the number of form blocks you use, and it
seemed accurate -- we had enough concrete and little waste. The
handbook recommends a 3,000-psi mix at a 5-inch slump, with
superplasticizer added at the job so the mix will flow easily
into the forms and around the reinforcing.
To reduce stress on the forms, it's important to pour in
1-foot to 2-foot lifts, at a total rate of about 4 vertical
feet per hour. The superplasticizer wears off quickly, and the
concrete in each lift stiffens enough that the pressure will
not build up too high as the pour progresses.
Pumps and hoses. The
standard way to place concrete in foam forms is to pump it
(Figure 6). A 4-inch hose won't fit between the forms and work
around the form ties and rebar, so Polysteel's instructions say
to use a reducer to adapt the pump hose from 4 inches down to 2
or 3 inches. This lets the hose reach all the way to the bottom
of the forms, allowing you to gently deliver the concrete into
the bottom of the form on the first lift, rather than dropping
it from a height of 6 or 8 feet.
Figure 6.A concrete pump delivers a 3,000-psi mix
using small aggregate, and the mix is treated with a
superplasticizer (left). The author's concrete sub did not use
a 2- or 3-inch reducing adapter on the pump hose, which would
have made the pour more manageable. Rapping the forms with a
hammer and a block of wood during the pour helps consolidate
the concrete and prevents the formation of voids and air
pockets (right).
We did not use a hose adapter on our job, and the effect was
noticeable. At the beginning we were dropping the concrete
several feet, and at the bottom of the forms I later noticed
some bulging -- as much as 1/2 inch of convexity between
vertical braces in a few places. Since there was no finish
issue in our case, this wasn't a big concern, but I did think
to myself that we were approaching the strength limit of the
forms. Compared to conventional methods, using foam forms takes
a bit of a delicate touch -- the bracing and the placing
methods really matter, because there is not a lot of tolerance
for carelessness.
We actually did have a couple of minor blowouts -- nothing
catastrophic, but enough to cause some yelling and running
around. One happened when the guy who was directing the pour
mixed up his signals with the concrete pump operator. Instead
of stopping the pump, the operator kept the crete flowing, and
very quickly we had a high mountain of concrete at one spot in
the wall. Under the increased pressure, a splice in a cut form
about a third of the way up the wall bulged out and threatened
to give way. Fortunately, we were able to contain the damage by
jamming a piece of plywood over the tender spot and shoving in
some new 2x4 braces against the side of the trench. We had a
similar problem partway up a low section of wall where there
was relatively little pressure involved (Figure 7). In that
instance, we hastily shoveled some backfill back into the
trench and tamped it down to offset the pressure of the
concrete.


Figure 7.Inadequate bracing at a spliced form and
a too rapid pour in one area caused a section of form to bulge
outward (left). The affected area was located partway up a low
section of wall, so the damage was contained by tamping
backfill against the bulging form (below).
In hindsight, I think it would be wise to create some sort of
augmented through-ties at any location where the form's
strength is at all dubious. I would also make the plywood
gussets stronger and thicker next time and brace them back more
thoroughly. It's best not to allow wishful thinking into the
work at all. Next time, I'll definitely use the adapter, even
though it's tiring to have to continually slide the business
end of the hose into the forms and lift it out again as you
progress around the walls.
Curing. When you use ICFs,
you're doing your concrete a huge favor. The insulation
contains the warmth that the concrete creates as it sets, and
it keeps the moisture from evaporating. The temperature stays
more uniform across the entire concrete section, and the
concrete cures moist. That decreases the internal stress that
often forms within a mass of concrete as it dries and cools
differentially from the outside in. As a result, the shrinkage
cracks that form will tend to be fewer and smaller. Also, a
moist cure adds significantly to the concrete's final strength
-- it's reasonable to estimate that concrete cured inside ICF
forms would end up at least 25% stronger than concrete that is
wet-cured for seven days, and perhaps double the strength of
concrete that is exposed to air a day or two after the
pour.
Capping off. As you finish
the pour, you place anchor bolts into the wet concrete just as
you would for a conventional wall. In a few days, when the
concrete is hard enough, you apply a pressure-treated sill in
the usual way, although the sill itself is wider. The added
thickness of the forms means that a nominal 6-inch wall is
actually 9 1/4 inches across, which makes for a nice fit with a
2x10 sill. A nominal 8-inch Polysteel wall gets a 2x12
treated-wood sill cap.
The portion of the foam form on the exterior surface that's
above grade, between the ground and the house, needs to be
protected. We used a cementitious stucco called California
Stucco, from Silpro (www.silpro.com). It comes dry in a sack,
and you mix it with water on site. Polysteel's literature says
you can apply the stucco directly to the foam if you rough up
the foam with a wire brush first, and it's true -- that's what
we did, and the stucco does adhere. But in the future I think I
would use expanded galvanized-metal lath, because the stucco we
applied has developed some fine cracking. Another option would
be to screw pressure-treated wood to the steel furring strips
in the foam, or to apply some kind of fiber-cement sheet
material.
Would I Do It Again?
When the forming and pouring were all done, and we stepped
back to assess the results, my crew and I were impressed. I've
got a crew of the usual cynical home-building types -- each of
my guys has been doing this kind of work for 25 or 30 years.
And everybody, myself included, felt that this system was worth
the effort and lived up to its promise.
I'm still not sure how the cost of this job would compare to
the cost of bringing in a regular poured-wall subcontractor.
There were a lot of wild cards in this particular project,
including the unusual wall heights and my desire to protect the
site. And as I mentioned, this was not the kind of job where I
needed to work up precise bid figures or compare all the
alternatives. This customer was ready to pay for quality.
But when I do figure up all the costs, I won't be surprised if
I find that this way was actually cheaper as well as better. I
avoided the separate cost of insulating, and I avoided having
to bear the cost of a specialty contractor's markup and the
cost of any delays caused by working around his schedule. The
well-insulated basement space saves energy for the homeowner
and is also more comfortable and livable than the usual
basement.
In addition, by including a generous amount of steel
reinforcement and by curing the concrete under ideal
conditions, we've built what I am convinced is a very strong
and durable wall.
I'll be using ICFs on my next basement, even though I'll be
working at the opposite end of the market, building a small,
bare-bones house with a tight budget. Even for a client who is
by no means a moneybags, I think this system is
worthwhile.
Malcolm Meldahlis a design-build contractor in Truro,
Mass.