by Paul Huijing
After working as a superintendent for a local contractor for
five years, I started my own construction company —
building custom presold homes and additions — in February
2004. Two years later, I decided to build my first spec house,
on a lot I purchased at a municipal tax auction. Fuel prices
were increasing and I wanted to explore practical ways to
increase the energy efficiency of the homes I built; a spec
house, I reasoned, would give me the freedom to try some new
energy measures.
There was a further incentive: The Energy Policy Act of 2005
offered a $2,000 federal tax credit for any new home that used
50 percent less energy for heating and cooling than a "typical"
new home. Since I had already been building Energy Star homes,
I was eager to find strategies that would allow me to
qualify.
Tax Credit Details
The Energy Policy Act references the 2003 International Energy
Conservation Code with its 2004 Supplement. The credit, which
remains available through December 31, 2008, covers only
heating and cooling energy and requires that 10 percent of the
energy savings be the result of improvements to the building
envelope. (For more information, go to
www.energystar.gov).
While the federal credit is independent of the Energy Star
program, the same rating contractors — certified Home
Energy Raters — monitor the program. I worked closely
with Craig Marden of Conservation Services Group, a local
Energy Star auditing company, to identify the best combination
of practical, proven methods to achieve the goal. We looked at
three main areas for improvement: windows, mechanical
equipment, and insulation (see Figure 1).
Figure 1. This table compares a
code-minimum reference house and the author's previous Energy
Star houses with various improvements he considered in order to
gain a federal tax credit under the Energy Policy Act of 2005.
It assumes air conditioning efficiency of SEER 13.
As it turned out, the windows I had already been using, Pella
ProLine double hungs, were fine, as was the Frigidaire propane
furnace, so those two items required no upgrade. I had already
been air-sealing my previous Energy Star houses, which was
critical for meeting the federal criteria. So I focused my
attention on insulation and bringing the mechanical equipment
and ductwork into conditioned space (see illustration).
Foundation Insulation
We determined that I would need R-10 foundation insulation.
This would also transform the basement into conditioned space,
which would have an important benefit: I would no longer have
to insulate beneath the first floor, or any ductwork running
through the basement. Moreover, insulating the foundation would
bring the furnace and water heater inside the thermal envelope
and provide a tempering effect on the space.
I first had to decide whether to insulate the inside or the
outside of the foundation. While exterior insulation is better
from a thermal point of view, it's also more difficult to
execute. On this particular house, the lot was level and the
foundation would have minimal exposure, so I decided to use
Warm-N-Dri insulation board (800/438-7465,
www.owenscorning.com/around/insulation/products/warm-n-dri.asp)
on the exterior (Figure 2).
Figure 2. Warm-N-Dri foundation insulation
board is pressed into a proprietary spray coating, which holds
it in place for backfilling. The fiberglass board acts as a
drainage mat and is said to discourage insects.
Before seeking the federal tax credit, the author typically
framed with 2x4s and used no foundation insulation. Because he
carefully air-sealed the frames, his previous houses (left) met
Energy Star standards. Meeting the new federal standard
required upgrading to 2x6 walls and adding foundation
insulation (right).
I chose the fiberglass board for two reasons. First, insects
seem to like to nest and tunnel through polystyrene insulation
but not in the fiberglass board (see "Insect Infestations in
Buried Foam," 10/98). Second, in addition to insulating, the
fiberglass board acts as a drainage mat, letting groundwater
fall through to the footing drain. My site was very
well-drained, so I wasn't worried about the insulation becoming
water-logged and losing its effectiveness.
Because concrete is a poor insulator, the exterior insulation
must be carried up to the sill plate to eliminate a "cold
bridge" through the top of the concrete wall. Otherwise, a
significant amount of heat can be lost through the narrow
section of exposed concrete.
Installation. The Warm-N-Dri insulation board is held
in place by pressing it into the system's spray-on
waterproofing membrane, called Tuff-N-Dri. (This combination is
backed by a 30-year warranty for the customer and is superior
to the damp-proofing commonly used on poured foundations in our
area.) I also added some concrete nails to help prevent the
boards from shifting during backfill.
The only problem I had was at the top of the wall, where some
of the drainage stone placed by the excavator fell behind the
board. I tried to scoop the stones out, but succeeded only in
helping them fall in deeper. Ultimately I was able to press the
board into the few stones that got in and flatten it against
the foundation. Next time I'll use additional nails at the top
of the wall, and perhaps place a tarp or a U-shaped cardboard
shroud over the top to prevent stones from falling behind the
board.
To keep the insulation board from protruding beyond the framing
at the base of the walls, I used 2x8 mudsills and cantilevered
the floor framing over it. As usual, I used a foam gasket under
the sill, and also sprayed a bead of polyurethane foam along
the sill's outside edge to ensure there were no air leaks
(Figure 3). Where the joists run parallel to the foundation
wall, I held the rim joist back 2 inches from the outside edge
of the sill, so that loads from above would be transferred
directly onto the concrete.
Figure 3. Because the 2x8 mudsill projects
2 inches over the top of the fiberglass insulation board, the
author held the rim joist back the same distance on walls where
the joists are parallel. This ensures that wall and roof loads
from above get transferred directly into the concrete
foundation. In addition to a foam sill gasket, he used spray
foam to seal the sill to the concrete.
To protect the top of the board and provide a finished
appearance, I had my siding contractor cover the above-grade
portion with vinyl-coated coil stock (Figure 4).
Figure 4. The siding contractor covered
the exposed portion of the insulation board with vinyl coil
stock. He waited until the job was nearly complete so that the
vinyl wouldn't get damaged by the work in progress.
Upgraded Framing
I had previously thought it made the most sense energywise to
frame with 2x4s rather than 2x6s and pay close attention to
air-sealing and insulation details. I always took pains to seal
around doors and windows and miscellaneous penetrations. Having
never seen a good fiberglass insulation job, I had also
switched to blown-in cellulose in the walls. I use Par/PAC
(877/937-3257,
www.parpac.com), a method
that relies on reinforced plastic stapled tightly to the inside
of the studs to confine the insulation, which is then blown in
at high density so that settling over time is not a problem
(Figure 5). The cellulose automatically fills in around pipes
and electrical boxes, and plugs any small air leaks in the
shell. For my typical 2,400-square-foot house, Par/PAC costs
about $1,000 more than fiberglass.

Figure 5. Par/PAC insulation — a
high-density blown-in cellulose — provides good air
sealing. After stapling up a reinforced poly barrier, the
insulation contractor fills each bay through small holes in the
plastic sheet, which are subsequently taped
up.
Even though my previous 2x4 houses had met Energy Star
requirements, I found that in my climate 2x4 exterior walls
wouldn't qualify for the tax credit. So I upgraded to 2x6s,
which allowed for an increase in wall R-value from 13 to
19.
Dealing With Ductwork
I've always sealed the ducts in my houses, which greatly
improves the efficiency of any forced-air system and creates a
healthier indoor environment. On this project I went a step
further and made sure all the ducts ran inside conditioned
space (Figure 6). As I mentioned above, adding foundation
insulation meant the basement was now conditioned space, so I
was able to eliminate the insulation on any ductwork in the
basement.
Figure 6. Insulating the roof plane behind
knee walls provided conditioned space for running ductwork,
which therefore doesn't need to be insulated.
In previous houses, I had sometimes run ducts through the
unconditioned attic, so these also had to be insulated. The
house featured here had knee walls upstairs; by insulating the
sloping roof plane behind them, I created a conditioned area
that allowed me to run the ductwork without insulating it.
(Bringing knee-wall space into the thermal envelope also makes
room for recessed shelves and storage areas.)
Preventing Windwashing
In addition to increasing the overall wall R-value, I took
steps to reduce windwashing of the attic insulation, as
required by the 2004 IECC. I first used precut cardboard
baffles, but the interface with the polystyrene vent chutes on
sloped ceilings was troublesome, and I ended up having to stuff
the gaps with fiberglass (Figure 7). While cardboard baffles
fit well for truss roofs, they don't work as well for a
stick-framed roof because the lapping of the ceiling joist over
the side of the rafter is a difficult area to seal. So we spent
a lot of time cutting the cardboard to fit.
Figure 7. In an effort to prevent
windwashing of attic insulation, the author first tried using
cardboard baffles above the top plates, then stuffed the gaps
between the baffles and the polystyrene ventilation chute with
fiberglass batts (top). His discovery of a plastic baffle
called AccuVent (bottom) made this process much
easier.
Then I heard about a new plastic baffle called AccuVent
(610/376.1900,
www.brentwoodindustries.com)
and decided to give it a try. The product was not yet stocked
in my area so I purchased it directly from the manufacturer. It
turned out to be much easier to cut than the cardboard baffles,
and faster to install. Instead of attaching to the top of the
top plate, which limits stapling access, the AccuVent baffle
has a vertical tab that you staple to the front of the plate.
This feature made it possible for me to install AccuVent under
a 4/12 dormer pitch where I couldn't hold the stapler upright
to install the cardboard baffle.
Wherever we had to make a transition between the AccuVent and
standard polystyrene roof vents, we used expanding foam to seal
the gaps. The manufacturer of AccuVent now sells extensions
that mate with the baffle profile, for use in cathedral
ceilings and other insulated roof planes.
Tax Credit Recalculated
At the end of the project, I was disappointed to learn that the
$2,000 tax credit was somewhat of an illusion, because I had to
deduct that amount from my expenses before determining my
income. Thus I had in essence an extra $2,000 in income to pay
taxes on. Assuming a 40 percent total state and federal tax
rate, I had to pay an additional $800 in taxes — meaning
the credit was actually only $1,200.
Even so, I think the process of improving the energy efficiency
of my houses was worthwhile. In fact, I went on to build a
second house that qualified for the tax credit. I didn't have
to change many of the techniques I had already been using, and
the additional costs were fairly easy to absorb in the market
value of the homes. Most important, at a time when more and
more buyers are demanding efficiency, I've been able to
demonstrate to potential customers that they don't have to
sacrifice their design goals to achieve big reductions in
energy use.
Paul Huijing owns Paul Huijing, Inc.,
Construction & Engineering in Wilbraham,
Mass.