Building a Reinforced Concrete Block Wall,
continued
Bucket Brigade
In typical "high-lift" masonry wall construction, it's most
common to lay block to the full height of the wall, then pump
grout into the cells from the top down. Because dropped mortar
and masonry debris can build up in the cells and block the
grout's passage, inspection and cleanout ports are incorporated
at or near the bottom course to ensure complete filling. But
the various openings, lintels, and intermediate bond beams on
this job, along with the fireplace construction, made that
approach impractical. Instead, we did the grouting in 3- to
5-foot lifts, which allowed simple, top-down inspection. We
moved the grout from mixer to wall in 5-gallon buckets (Figure
9).
Figure 9. It took more
than 30 yards of grout, passed up in buckets, to fill the block
shear walls.
Thanks to the volume of job-mixed, 3,000-psi grout needed to
completely fill the block cells, the crew members had their
hands full. It took as much time to set steel and pour grout as
it did to lay the block. On average, we had four or five masons
and four to six laborers working on this job. In all, we used
six tons of #6 rebar, 10 tons of #5 rebar, and three-quarters
of a ton of #3 stirrups. And we mixed and poured 30 to 35 yards
of mortar, grout, and concrete.
Stepped Chimney Construction
The most complicated aspect of the two walls was the fireplace
and chimney construction. The large fireboxes required
16-by-26-inch flues. Each firebox was located 8 feet off the
gable walls' midpoints, which meant that the chimneys had to be
progressively offset, floor by floor, by that distance to break
through at the roof ridge (Figure 10). One flue moved not only
8 feet laterally along the wall, but also 2 feet through the
wall.
Figure 10. To end up in
the center of the ridge three stories up, the flue has to
stairstep nearly 8 feet laterally (left). A series of
structural pads, one at each floor, provides support for the
stepped construction. A hand-laid herringbone brick pattern
lends an artful touch to the fireboxes (right).
Shifting a chimney this distance goes well beyond the
supporting capacity gained from a graduated corbeling of the
block courses. Instead, we poured 6-inch-thick structural
concrete slabs at each floor level and just below the roof.
Above the first floor, we reduced the chimney dimensions to
minimum size to squeeze past window openings in the wall above.
But above the roofline, the chimneys expanded again to finish
at approximately 4 by 6 feet, which required a final structural
slab just below the rafters.
The structural slabs were supported at either edge by the CMU
wall and a W10x22 steel I-beam framework standing parallel to
the wall and supported on high-strength steel columns (Figure
11). Smaller, W8x18 I-beams running between the CMU and the
main I-beams bordered the slab ends. Shear anchors welded to
the I-beam webs locked the steel to the concrete, while rebar
set in the slabs and grouted into the masonry completed the
tie-in.
Figure 11. A steel
frame, offset from the block wall but tied into it, supports
the flue mass at each floor level.
We formed the underside of the slabs with cement board.
Although plywood is typically used in this application and
later removed, cement board works well as a leave-behind form.
It's smooth, fireproof, and completely compatible with masonry.
Our use of leave-behind forms made it simple to pass the flues
through the slabs as needed; cement board cuts easily with a
small diamond wheel on a grinder (Figure 12).
Figure 12. Shear anchors
and rebar provide a mechanical connection among the steel,
concrete, and masonry elements of the chimney. Cement board
made a good leave-behind form for the slabs supporting the
flue. Insulation wraps the flue tile to allow for thermal
expansion.
The lower flange of the steel I-beam supported the cement
board. To prevent the board from sagging under the weight of
the pour, we temporarily propped the undersides of the largest
slabs, which measured approximately 8 by 10 feet. The
conventional 30-inch-wide hearth slabs required no additional
shoring.
Bolting Into Block
To attach the floor framing to the masonry on the interior
side, we relied on Hilti's HIT epoxy adhesive anchor-bolt
system (Figure 13). The anchor bolts (800/879-8000;
www.us.hilti.com) are especially convenient
because you can drill directly through the material that is
being fastened into the block without having to remove it to
expand the holes in the masonry, as with other anchoring
methods.
|
Figure 13. Epoxy-set Hilti HIT
anchor rods secure LVL floor girders to the
masonry. Asphalt felt provides a capillary break
between wood and concrete (above). At left,
a saddle-top steel post supports the ridge of
a lower roof abutting the masonry
gables.
|
Exterior Stone Veneer
We used that same Hilti fastener system on the exterior side to
mount bearing lintels for the stone veneer above window
openings and on the cheeks above lower rooflines (Figure
14).
Figure 14. Galvanized
steel lintels will support the exterior stone veneer above
window openings. The lintel is bolted to the solidly grouted
blockwork using epoxy-embedded anchor rods (left). Short
lengths of steel lintel stairstep up the gables to support the
finished stone veneer (right).
Because building wings extended out under lower rooflines from
both masonry gables, we had to provide a means to support the
heavy stone veneer on the cheeks above these roofs. We
installed short lengths of galvanized steel angle to the
blockwork, stairstepping up the roof slope much like step
flashing. An orange-colored, rubberized spray-on coating
protected all exterior-facing blockwork from moisture
penetration, although copper flashing will still serve as the
primary barrier against water intrusion in the completed
installation.
When this job is completed, we'll have applied approximately
300 tons of stone veneer to the exterior walls, a process I'll
discuss in a future article.
Mike DeBlasioowns and operates M. DeBlasio Inc. in
Littleton, Mass.