Heavy Lifting: A Housemover's Journal,
continued
Placing the Beams
One of the many challenges to raising an existing building
from its foundation is access. A steep or otherwise limited
site increases the difficulty and therefore the cost of
lifting. It's a definite plus to have clear, open space around
the building to insert the long, 12x12-inch steel H-beams and
wood cribbing that provide the main lifting support (Figure
3).
Figure 3.While the author swings a two-ton main
beam into position with the backhoe, a worker makes sure the
far end doesn't take out the neighbors' place across the
street.
Happily, access was not a problem on this job. There was
plenty of room to maneuver a backhoe and dig starter trenches
and cribbing pits for the two main beams at the building's
gable ends. We completed the trenching under the house by hand,
digging deep enough to account for the combined depth of the
main beams and the crossing "needle" beams, the tops of which
had to plane out coincident with the underside of the chimney
slab we'd just poured. This point was about 18 inches lower
than the sill.
Ordinarily, lifting a house of this size takes a pair of main
beams and four 8x8-inch needles — one on either side
of center span and one under each outside bearing wall (Figure
4).
Figure 4.Two main beams and four needle beams
supported the house for lifting. To avoid deflection from the
masonry load on the main beams, the author placed the needles
under the chimney mass first.
The needles either go in tight against the floor joists or,
when a chimney lift is involved, are inserted below the hearth
slab at a lower level than the sills and shimmed between their
tops and the underside of the floor joists. The shims we use
are various blocks of wood, from 8x8 off-cuts on down to cedar
shingles. Compressible rigid foam board also comes in handy for
cushioning the pressure points and filling irregular
gaps.
Pre-loading the chimney. On this job, we inserted the center
needles under the chimney mass first (Figure 5). We slid the
first one in and jacked it snug against the modified chimney
base, so that it began to shoulder, but not raise, some of the
masonry load. Then we inserted the second needle and snugged it
up, too, effectively transferring the full weight of the
chimneys onto the needles.
Figure 5.After carefully removing every other
stone supporting the three chimneys and pouring a unifying
reinforced concrete slab between them, the author slipped two
needle beams beneath the masonry, initially jacking them just
enough to transfer the load.
Usually, you'd place the main beams, then set the needles; but
then, this wasn't a usual case. Despite the overall bearing
capacity of the H-beam needles, there is still considerable
mid-span deflection under a masonry load, which moves
independently of the wood structure. We accounted for that
deflection by transferring the chimney weight first. Lifting
the building was then a matter of placing 40-foot-long
12x12-inch main beams under the center needles, installing the
outer needles, then shimming as needed.
We chute the beams in on rollers set on low cribbing stacked
just outside and just beyond midway inside the foundation
(Figure 6). My derrick usually does the heavy work — a
40-foot H-beam weighs 3,600 pounds — and also pivots
the far end of the beam up or down to clear the floor by using
the outside roller as a fulcrum. There's always a man under the
house keeping an eye on the blind end of the beam and shouting
directions.
Figure 6.Rollers facilitate beam placement under
the structure. The beam is chained to the backhoe bucket to
keep it from launching itself forward like a battering
ram.