- Lumber
- Nails
- Framing Connectors
- Subflooring
- Dimensional Lumber Floors
- Engineered Lumber Floors
- Floor Trusses
- Wall Framing
- Sheathing and Shear Panel
- Dimensional Lumber Roofs
- Engineered Lumber Roofs
- Roof Trusses
- Structural Insulated Panels
- Seismic and Wind
- Steel
Truss Types
Floor trusses can be designed to sit on either their bottom chord or their top chord (below).
Figure: Truss Types
Caution: Loose Plates
Connector plates should be centered over the joint and firmly embedded in the wood. Never refasten a loose plate: The bond cannot be restored once it’s been broken.
Handling Trusses
Trusses are vulnerable to damage until they are installed, sheathed, and braced. To prevent damage, use the following precautions:
- Inspect trusses when receiving a shipment. Look carefully for loose plates and reject any damaged trusses.
- Banded trusses should be lifted off the truck from two points on the top chords. Individual trusses should be lifted the same way (Lifting Trusses, below).
- Store trusses horizontally on relatively level, dry ground. To prevent any bending or twisting that could loosen truss plates, support the trusses with blocking placed every 8- to 10-ft.
- If trusses must be stored vertically, make sure they are braced and blocked in a stable manner. Gable trusses should be stored with their peaks up, scissors trusses with their peaks down.
Figure: Lifting Trusses
Bracing Roof Trusses
Trusses are inherently unstable until sheathed and require two types of bracing: temporary and permanent.
Use temporary bracing to safely erect the trusses; permanent bracing is required to stabilize the trusses throughout the life of the structure. The truss fabricator or “designer of record” should provide a permanent bracing plan.
Usually some of the elements of the temporary bracing stay in place as part of the permanent bracing. In general, all bracing should be placed near panel points (where truss members meet).
Temporary Bracing: The First Truss
It is important to accurately plumb the first truss and to brace it substantially, since additional trusses rely on the first one for stability.
All bracing must be of 2x material.
Start with the gable-end truss. Most builders start by sheathing the gable-end truss on the ground and lifting that first. Unfortunately, the gable-end truss is difficult to brace back to the deck without the braces interfering with the second truss. On a one-story building, the gable-end truss can be braced to stakes driven in the ground.
Start several trusses in. Alternatively, start the first truss 8- to 12-ft. in from the gable end and brace it to the deck (Bracing to the Deck, below). Then work away from the braced end, filling in the open 8- to 12-ft. section last, after permanently bracing the rest of the trusses.
Or brace the trusses to an end wall (Bracing to the End Wall, below). It may first be necessary to solidly brace the end wall to the deck to keep the top plate rigid.
Figure: Bracing to the Deck
Figure: Bracing to the End Wall
Temporary Bracing: Subsequent Trusses
Spacers. As trusses are added to the roof, they can be spaced from the preceding truss with short 1x4 or 2x4 spacers pre-cut to length, with light-gauge metal spacers
or with heavy-duty fold-out metal braces. (The heavy metal braces can also serve as temporary lateral bracing for the top chord.)
Top-chord bracing. As soon as the fourth truss is up, start fastening lateral bracing across the top chords — one brace near the peak and one near the midpoint of each top chord. If required, place diagonal bracing at each end of the roof and at 20-ft. intervals in between (Diagonal Top-Chord Bracing, below).
All lateral bracing should be minimum construction-grade 2x4s, at least 10 ft. long and nailed with two 16d nails at each intersection. Individual pieces should lap at least one bay.
Roof sheathing. To quickly stabilize the top chords, some builders start installing sheathing after about a dozen trusses have been installed. The sheathing acts as both temporary and permanent bracing for the top chords.
Figure: Diagonal Top-Chord Bracing
To simplify installation of the sheathing, some builders keep the lower top-chord braces 5 ft. up from the eaves line to allow room for the first course of sheathing. Unless the sheathing is installed shortly after erecting the trusses, diagonal top-chord braces may be needed to prevent racking in the roof or truss collapse.
Bottom-chord bracing. After the fourth truss is up, also start installing lateral bracing on the bottom chord (along its top edge if the bottom chords are receiving drywall). Install bottom-chord bracing according to the permanent bracing plan and leave in place. On large trusses, diagonal bottom-chord bracing may be required at each end and at 20-ft. intervals in between.
Web cross-bracing. After the fourth truss is up, also start fastening diagonal cross-bracing to the vertical webs. Cross-bracing of the vertical webs goes in an X pattern at each end of the building and every 20 ft. in between (Bottom-Chord Bracing and Web Cross-Bracing, below). Install web cross-bracing according to the permanent bracing plan and leave in place.
Figure: Bottom-Chord Bracing and Web Cross-Bracing
Permanent Truss Bracing
To perform as designed, roof trusses require permanent bracing after assembly, as specified by the “designer of record” on the job. In the absence of an architect or engineer, this responsibility may fall to the general contractor.
Permanent bracing typically consists of many of the same elements as the temporary bracing (see above), most of which are left in place after construction. One exception is any top-chord bracing, which must be removed to allow installation of the roof sheathing. The roof sheathing then serves as permanent top-chord bracing.
Piggyback Trusses
When trusses exceed 12- to 14-ft. in height, they are typically shipped in two sections to comply with highway transportation limits. These so-called “piggyback trusses” have special bracing requirements. Ignoring these requirements can lead to catastrophic failure under heavy loads such as snow.
In particular, it is critical to stabilize the top chords of the lower truss sections with either plywood or diagonal bracing (below). Other permanent bracing may also be required.