Roof trusses may offer speed, economy, and a lot of open interior space, but many residential contractors view them as mysteries rather than old friends. Everyone has heard stories of truss disasters – I have one of my own – but following some simple guidelines for ordering and installation will eliminate most of the risk and give you a roof in no time at all. Ordering This is one of the most important phases and one of the most neglected. The big problem is procrastination. Many fabricators look for a minimum of four weeks lead time. This means ordering your trusses about the same time you pour the foundation, not when the walls are going up. As with any
Fast Framing with Trusses
These engineered giants can do wonders–but only if ordered right and handled well